Planning application

Blackhillock Electricity Substation Keith Moray

Decided Moray 21/01460/SCN Screening Opinion

Decided. The decision notice on the council portal carries the outcome in full, including any conditions.

Proposal

Install a battery energy storage system (BESS) with assocaited infrastucture at

As published by the council, reference 21/01460/SCN

Application record

Reference
21/01460/SCN
Type
Screening Opinion
Status
Awaiting decision
Decision
Screening Opinion Issued
Received
17 Sep 2021
Validated
21 Sep 2021
Decided
21 Dec 2021
Ward
Keith And Cullen
Parish
Strathisla
Decision by
Answer to PE/ID or application

Site history

Applications at this address on the Moray register

This site has had 3 applications since 2021: 2 approved, 0 refused.

  • 24/00986/APP Granted

    Blackhillock Electricity Substation Keith Moray

    Variation of conditions 6, 13, 15 and 18 imposed on 22/00067/S36 due to the change in bund dimensions at

    Decided 23 Oct 2024 Full applications
  • 22/00067/S36 Granted

    Blackhillock Electricity Substation Keith Moray

    Install a battery energy storage system (BESS) with associated infrastucture at

    Decided 1 Jun 2022

Timeline

Dates from the published record

  1. 17 Sep 2021

    Received by Moray

  2. 21 Sep 2021

    Validated

    Checked as complete and ready for consideration.

  3. 21 Dec 2021

    Decision issued: Screening Opinion Issued

  4. 24 Aug 2026

    Added to PlanIndex

After the decision

Moray has decided this application; the outcome above is the register's own wording and the decision notice on the council portal carries the detail. More in our guide to what happens after a planning decision.

About outline applications

An outline application tests the principle of developing a site, holding back details such as appearance and landscaping as reserved matters for later approval. More in our guide to planning application types.

Nearby applications

Within 0.3 miles

  • Blackhillock Quarry Keith Moray AB55 5PA

    25/00917/APP Submitted 30 Jul 2025 200 yards away

    Proposed southern extension at

    Granted Full applications Extension 16 docs
  • Blackhillock Keith Moray AB55 5PA

    20/01146/S36SCN Submitted 8 Sep 2020 200 yards away

    Screening Opinion for energy storage modules synchronised condenser housed in a building and other associated ancillary electrical infrastructure at

    Decided Outline
  • Blackhillock Quarry Keith Moray AB55 5PA

    25/00916/APP Submitted 30 Jul 2025 250 yards away

    Proposed variation of conditions 2 and 11 of planning consent 03/01286/MIN to extend the operational life of the existing permitted site until 31st October 2040 and to provide for working to take place in accordance with the proposed amended site design

    Granted Full applications 11 docs
  • Blackhillock Electricity Substation Keith Moray

    24/00986/APP Submitted 17 Jun 2024 250 yards away

    Variation of conditions 6, 13, 15 and 18 imposed on 22/00067/S36 due to the change in bund dimensions at

    Granted Full applications 20 docs
  • Blackhillock Electricity Substation Keith Moray

    22/00067/S36 Submitted 17 Jan 2022 250 yards away

    Install a battery energy storage system (BESS) with associated infrastucture at

    Granted 78 docs
  • Land South Of Blackhillock Substation Keith Moray

    20/01776/APP Submitted 24 Dec 2020 400 yards away

    Installation of a synchronous compensator and ancillary infrastructure on

    Withdrawn Full applications

In Moray

  • 26/01247/PPP Awaiting decision

    Garden Ground Of West Park House Nairn Road Forres Moray

    Form 2no dwellinghouse plots in garden ground of

    Received 29 Sep, published by the council 5 Oct 2026 Outline
  • 26/01191/SCO Awaiting decision

    Parkmore Lime Quarry Dufftown Keith Moray AB55 4DL

    EIA scoping report related to a proposed planning application for Parkmore Quarry. The proposed development involves a limited lateral extension to the quarry together with deepening of the quarry within the existing extraction footprint and is aimed at optimising the extraction of the high quality limestone reserves at the quarry. The quarry operates under Planning Permission 05/00413/MIN which expires on 21st February 2042.

    Received 17 Sep, published by the council 24 Sep 2026 Outline
  • 26/01191/SCN Awaiting decision

    Parkmore Lime Quarry Dufftown Keith Moray AB55 4DL

    EIA scoping report related to a proposed planning application for Parkmore Quarry. The proposed development involves a limited lateral extension to the quarry together with deepening of the quarry within the existing extraction footprint and is aimed at optimising the extraction of the high quality limestone reserves at the quarry. The quarry operates under Planning Permission 05/00413/MIN which expires on 21st February 2042.

    Received 17 Sep, published by the council 19 Sep 2026 Outline
  • 25/01648/PPP Withdrawn

    Land Between Brae Croft And Gillymule Farm Grange Keith AB55 6TJ

    Erect a dwelling and detached garage on

    Received 15 Dec, published by the council 27 Jul 2026 Outline
  • 26/01133/PPP Awaiting decision

    Site Adjacent To Westerton Croft Grange Keith Moray

    Erect dwellinghouse and detached garage/carport on