Skip to content
PlanIndex Get alerts
Menu

Planning application

Land North Of Tye Lane Bramford Suffolk

Awaiting decision Mid Suffolk DC/26/03359 Discharge of Condition(s)

Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.

Proposal

Discharge of Conditions Application for DC/21/04711 - Condition 25 (Archaeological Works)

As published by the council, reference DC/26/03359

Application record

Reference
DC/26/03359
Type
Discharge of Condition(s)
Status
Awaiting decision
Received
5 Aug 2026
Validated
5 Aug 2026
Ward
Bramford & Blakenham
Parish
Bramford

Site history

Applications at this address on the Mid Suffolk register

This site has had 6 applications since 2024: 3 approved, 0 refused.

  • DC/26/02819 Granted

    Land North Of Tye Lane Bramford Suffolk

    Discharge of Conditions Application for DC/21/04711 - Condition 21 (Highway Condition Survey And Damage Repairs)

    Decided 10 Aug 2026 Conditions
  • DC/26/01693 Split decision

    Land North Of Tye Lane Bramford Suffolk

    Discharge of Conditions Application for DC/21/04711 - Condition 4 (Temporary Permission And Reinstatement Scheme)

    Decided 22 Apr 2026 Conditions
  • DC/25/04679 Granted

    Land North Of Tye Lane Bramford Suffolk

    Discharge of Conditions Application for DC/21/04711 - Condition 6 (Information Board Strategy)

    Decided 14 Nov 2025 Conditions
  • DC/24/02453 Split decision

    Land North Of Tye Lane Bramford Suffolk

    Discharge of Conditions Application for DC/21/04711 - Conditions 11 (Surface Water Discharge Strategy) and 13 (Landscaping)

    Decided 18 Jul 2024 Conditions
  • DC/24/02418 Granted

    Land North Of Tye Lane Bramford Suffolk

    Discharge of Conditions Application for DC/21/04711 - Condition 8 (Wildlife Sensitive Lighting Design Scheme), Condition 10 (Construction Management Plan), Condition 19 (Visibility Splays) and Condition 22 (Emergency Response Plan)

    Decided 18 Jul 2024 Conditions

Timeline

Dates from the published record

  1. 5 Aug 2026

    Received by Mid Suffolk

  2. 9 Aug 2026

    Added to PlanIndex

  3. Decision

    Awaiting decision

    Decision expected by 30 September 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.

    Mid Suffolk took a median of 48 days over the applications it decided in the last year.

Documents

Plans, drawings, consultee responses and the officer's report

4 documents on file for this application

  • DC/21/04711 DECISION NOTICE Additional Information · 05 Aug 2026
  • APPLICATION FORM Application Form · 05 Aug 2026
  • COVER LETTER Additional Information · 05 Aug 2026
  • PROGRAM OF ARCHAEOLOGICAL MITIGATION, EXCAVATIONS, MONITORING Report · 05 Aug 2026

Trade members open them from here.

Open the documents

What happens while it is decided

This application is with Mid Suffolk for determination, against a statutory target of eight weeks. Over the last year Mid Suffolk decided condition discharge and variation applications in a median of 46 days. More in our guide to how long planning decisions take.

About condition discharge and variation applications

This application deals with conditions on an existing permission, supplying the details a condition requires or asking to vary or remove one, without reopening the permission itself. More in our guide to planning application types.

Nearby applications

Within 500 metres

  • Land North Of Tye Lane Bramford Suffolk

    DC/24/02453 Submitted 29 May 2024 0m away

    Discharge of Conditions Application for DC/21/04711 - Conditions 11 (Surface Water Discharge Strategy) and 13 (Landscaping)

    Split decision Conditions 15 docs
  • Land North Of Tye Lane Bramford Suffolk

    DC/25/04679 Submitted 21 Oct 2025 0m away

    Discharge of Conditions Application for DC/21/04711 - Condition 6 (Information Board Strategy)

    Granted Conditions 5 docs
  • Land North Of Tye Lane Bramford Suffolk

    DC/26/01693 Submitted 21 Apr 2026 0m away

    Discharge of Conditions Application for DC/21/04711 - Condition 4 (Temporary Permission And Reinstatement Scheme)

    Split decision Conditions 3 docs
  • Land North Of Tye Lane Bramford Suffolk

    DC/26/03359 Submitted 5 Aug 2026 0m away

    95% historically approved · decision due ~30 Sep

    Discharge of Conditions Application for DC/21/04711 - Condition 25 (Archaeological Works)

    Awaiting decision Conditions 4 docs
  • Land North Of Tye Lane Tye Lane Bramford Suffolk

    DC/25/03911 Submitted 3 Sep 2025 0m away

    Application for a Non-material amendment relating to DC/21/04711 dated 18/12/2023 - amendment to details approved pursuant to condition 13 (Landscaping scheme) to retain sections of internal access track comprised of temporary tarmac, surfacing and temporary rope wire fencing within the site.

    Granted Amendments 8 docs
  • Land North Of Tye Lane Bramford Suffolk

    DC/24/02453 Submitted 29 May 2024 0m away

    Discharge of Conditions Application for DC/21/04711 - Conditions 11 (Surface Water Discharge Strategy) and 13 (Landscaping)

    Split decision Conditions 15 docs

In Mid Suffolk

  • DC/26/03850 Awaiting decision

    The National Grid (Bramford To Twinstead Reinforcement) Order 2024

    Submission of details reserved by Requirement 4(1)(d) Landscape and Ecological Management Plan for Stage 6 of the authorised development pursuant to The National Grid (Bramford to Twinstead Reinforcement) Order 2024

    4 Sep 2026 Conditions
  • DC/26/03834 Awaiting decision

    Land East And West Of Aubrey Drive Sudbury Part In The Parish Of Chilton

    Discharge of Conditions Application for DC/21/06676 - 3 (Surface Water Managemet Strategy), 4 (Surface Water Management Strategy - Implementation and maintenance), 6 (Construction Surface Water Management Plan), 8 (Biodiversity Enhancement Strategy), 10 (Archaeological Works), 13 (Construction Management - Environmental protection), 14 (Construction Management - Highway Safety) and 15 (Landscaping Scheme)

    3 Sep 2026 Conditions
  • DC/26/03842 Awaiting decision

    The National Grid (Bramford To Twinstead Reinforcement) Order 2024

    Submission of Details reserved by Requirement 4(a) - Construction Environmental Management Plan for Stages 6-8 of the authorised development pursuant to the The National Grid (Bramford to Twinstead Reinforcement) Order 2024

    3 Sep 2026 Conditions
  • DC/26/03798 Awaiting decision

    Land To The East Of Ely Road Barham Suffolk

    Discharge of Conditions Application for DC/22/06117 - Discharge of Conditions 5 (Advance Planting), 6 (Landscape Management), 7 (Hard and Soft Landscaping), 9 (Open Space and Play Space), 19 (Fire Hydrants), 28 (Ecology Mitigation and Enhancement Measures), 30 (Landscape and Ecological Management Plan), 31 (Lighting Design Scheme for Biodiversity) and 32 (SPA and Ramsar Site)

    2 Sep 2026 Conditions
  • DC/26/03802 Awaiting decision

    The National Grid (Bramford To Twinstead Reinforcement) Order 2024

    Submission of Details reserved by Requirement 6 - Detailed Written Scheme of Investigation (DWSI) for Stage 3 - pursuant to The National Grid (Bramford To Twinstead Reinforcement) Order 2024 to approve area(s) - where no further archaeological investigation is required at land in the vicinity of Trenches 359-366 - as marked on the attached plans.

    2 Sep 2026 Conditions