The National Grid (Bramford To Twinstead Reinforcement) Order 2024

Awaiting decision Mid Suffolk DC/26/02061 Discharge of Requirement

Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.

Proposal

The National Grid (Bramford to Twinstead Reinforcement) Order 2024: Written notice of the commencement of construction of Stage 4.2 of the Authorised Development (Schedule 3, Requirement 3(4)) - commenced on 11 May 2026.

As published by the council, reference DC/26/02061

Application record

Reference
DC/26/02061
Type
Discharge of Requirement
Status
Awaiting decision
Received
14 May 2026
Validated
14 May 2026
Ward
Assington
Parish
Assington

Site history

Applications at this address on the Mid Suffolk register

This site has had 64 applications since 2025: 33 approved, 1 refused.

  • DC/26/03858 Awaiting decision

    The National Grid (Bramford To Twinstead Reinforcement) Order 2024

    Submission of Detials reserved by Requirement 4(1)(d) Landscape and Ecological Management Plan for Stage 4.2 of the authorised development pursuant to The National Grid (Bramford To Twinstead Reinforcement) Order 2024

    Submitted 4 Sep 2026 Conditions
  • DC/26/03850 Awaiting decision

    The National Grid (Bramford To Twinstead Reinforcement) Order 2024

    Submission of details reserved by Requirement 4(1)(d) Landscape and Ecological Management Plan for Stage 6 of the authorised development pursuant to The National Grid (Bramford to Twinstead Reinforcement) Order 2024

    Submitted 4 Sep 2026 Conditions
  • DC/26/03842 Awaiting decision

    The National Grid (Bramford To Twinstead Reinforcement) Order 2024

    Submission of Details reserved by Requirement 4(a) - Construction Environmental Management Plan for Stages 6-8 of the authorised development pursuant to the The National Grid (Bramford to Twinstead Reinforcement) Order 2024

    Submitted 3 Sep 2026 Conditions
  • DC/26/03802 Awaiting decision

    The National Grid (Bramford To Twinstead Reinforcement) Order 2024

    Submission of Details reserved by Requirement 6 - Detailed Written Scheme of Investigation (DWSI) for Stage 3 - pursuant to The National Grid (Bramford To Twinstead Reinforcement) Order 2024 to approve area(s) - where no further archaeological investigation is required at land in the vicinity of Trenches 359-366 - as marked on the attached plans.

    Submitted 2 Sep 2026 Conditions
  • DC/26/03637 Awaiting decision

    The National Grid (Bramford To Twinstead Reinforcement) Order 2024

    Submission of Details reserved by Requirement 6 - Detailed Written Scheme of Investigation (DWSI) for Stage 3 - pursuant to The National Grid (Bramford To Twinstead Reinforcement) Order 2024 to approve area(s) - where no further archaeological investigation is required at land in the vicinity of Chestnut Grove.

    Submitted 20 Aug 2026 Conditions
  • DC/26/03648 Awaiting decision

    The National Grid (Bramford To Twinstead Reinforcement) Order 2024

    Submission of Details reserved by Requirement 6 - Detailed Written Scheme of Investigation (DWSI) for Stage 3 - pursuant to The National Grid (Bramford To Twinstead Reinforcement) Order 2024 to approve area(s) - where no further archaeological investigation is required at land in the vicinity of Bush Hill Grove / Leadenhall Wood.

    Submitted 20 Aug 2026 Conditions
  • DC/26/03646 Awaiting decision

    The National Grid (Bramford To Twinstead Reinforcement) Order 2024

    Submission of Details reserved by Requirement 6 - Detailed Written Scheme of Investigation (DWSI) for Stage 3 - pursuant to The National Grid (Bramford To Twinstead Reinforcement) Order 2024 to approve area(s) - where no further archaeological investigation is required at land in the vicinity of Pond Hall.

    Submitted 20 Aug 2026 Conditions
  • DC/26/03530 Awaiting decision

    The National Grid (Bramford To Twinstead Reinforcement) Order 2024

    Submission of Details reserved by Requirement 6 -Detailed Written Scheme of Investigation (DWSI) for Stage 3 pursuant to the The National Grid (Bramford To Twinstead Reinforcement) Order 2024 to approve that no further archaeological investigation is required in the areas marked on the attached plans at land near to Burstall Hill.

    Submitted 14 Aug 2026 Conditions
  • DC/26/03550 Granted

    The National Grid (Bramford To Twinstead Reinforcement) Order 2024

    Submission of Details reserved by Requirement 6 - Detailed Written Scheme of Investigation (DWSI) for Stage 3 - pursuant to The National Grid (Bramford To Twinstead Reinforcement) Order 2024 to approve area(s) where no further archaeological investigation is required at land in the vicinity of Burstall Hill.

    Decided 28 Aug 2026 Conditions
  • DC/26/03335 Awaiting decision

    The National Grid (Bramford To Twinstead Reinforcement) Order 2024

    Submission of Details reserved by Requirement 6 of the Detailed Written Scheme of Investigation (DWSI) for Stage 3- Trenches 371-379- pursuant to The National Grid (Bramford To Twinstead Reinforcement) Order 2024

    Submitted 3 Aug 2026 Conditions

Timeline

Dates from the published record

  1. 14 May 2026

    Received by Mid Suffolk

  2. 24 Jul 2026

    Added to PlanIndex

  3. Decision

    Awaiting decision

    Decision expected by 9 July 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.

    Mid Suffolk took a median of 49 days over the applications it decided in the last year.

What happens while it is decided

This application is with Mid Suffolk for determination, against a statutory target of eight weeks. Over the last year Mid Suffolk decided condition discharge and variation applications in a median of 46 days. More in our guide to how long planning decisions take.

About condition discharge and variation applications

This application deals with conditions on an existing permission, supplying the details a condition requires or asking to vary or remove one, without reopening the permission itself. More in our guide to planning application types.

Nearby applications

Within 500 metres

  • The National Grid (Bramford To Twinstead Reinforcement) Order 2024

    DC/26/03850 Submitted 4 Sep 2026 0m away

    95% historically approved · decision due ~30 Oct

    Submission of details reserved by Requirement 4(1)(d) Landscape and Ecological Management Plan for Stage 6 of the authorised development pursuant to The National Grid (Bramford to Twinstead Reinforcement) Order 2024

    Awaiting decision Conditions
  • The National Grid (Bramford To Twinstead Reinforcement) Order 2024

    DC/26/03842 Submitted 3 Sep 2026 0m away

    95% historically approved · decision due ~29 Oct

    Submission of Details reserved by Requirement 4(a) - Construction Environmental Management Plan for Stages 6-8 of the authorised development pursuant to the The National Grid (Bramford to Twinstead Reinforcement) Order 2024

    Awaiting decision Conditions
  • The National Grid (Bramford To Twinstead Reinforcement) Order 2024

    DC/26/03080 Submitted 16 Jul 2026 0m away

    Submission of Details reserved by Requirement 6 - Detailed Written Scheme of Investigation (DWSI) for Stage 3 - pursuant to The National Grid (Bramford To Twinstead Reinforcement) Order 2024 to approve area(s) where no further archaeological investigation is required at land in vicinity of Polstead Heath, Holt Road and B1068, Leavenheath.

    Granted Conditions 5 docs
  • The National Grid (Bramford To Twinstead Reinforcement) Order 2024

    DC/25/04004 Submitted 9 Sep 2025 0m away

    Approval of Details reserved by Schedule 3, Requirement 3(1) - Notification of Pre-commencement Operations

    Decided Conditions 1 doc
  • The National Grid (Bramford To Twinstead Reinforcement) Order 2024

    DC/26/03856 Submitted 4 Sep 2026 0m away

    95% historically approved · decision due ~30 Oct

    Submission of Details reserved by Requirement 8 Retention and Removal of Trees, Woodlands and Hedgerows Plan for Stage 4.2 of the authorised development pursuant to The National Grid (Bramford To Twinstead Reinforcement) Order 2024

    Awaiting decision Conditions Trees 6 docs
  • The National Grid (Bramford To Twinstead Reinforcement) Order 2024

    DC/26/01485 Submitted 7 Apr 2026 0m away

    The National Grid (Bramford to Twinstead Reinforcement) Order 2024: Notification of Pre commencement Operation - temporary access at locations, BM1 and BM2 , associated with Stage 4 of the Authorised Development - The anticipated programme for these pre commencement operations is from Tuesday 14 April 2026 to Friday 22 May 2026.

    Decided Conditions 2 docs

In Mid Suffolk

  • DC/26/03961 Awaiting decision

    Wingfield College Church Road Wingfield Diss Suffolk IP21 5RA

    Discharge of Conditions Application for DC/25/03300 - Condition 4 (Archaeological Post-Investigation) and 7 (Wildlife Enhancements)

    11 Sep 2026 Conditions
  • DC/26/03962 Awaiting decision

    Climax Molybdenum Uk Ltd Needham Road Stowmarket Suffolk IP14 2AE

    Discharge of Conditions Application for DC/26/01041 - Condition 4 (Wildlife Enhancement Layout)

    11 Sep 2026 Conditions
  • DC/26/03973 Awaiting decision

    Grove Farm Queen Street Stradbroke Eye Suffolk IP21 5HH

    Discharge of Conditions Application for DC/25/04640 - 6 (Roof Coverings)

    11 Sep 2026 Conditions
  • DC/26/02777 Granted

    24 Bolton Street Lavenham Sudbury Suffolk CO10 9RG

    Discharge of Conditions Application for DC/24/00688 - Condition 3 (Biodiversity Enhancement)

    29 Jun 2026 Conditions
  • DC/26/03937 Awaiting decision

    The Nutshell Milton Road South Stowmarket Suffolk IP14 1EZ

    Discharge of Conditions Application for DC/26/00753 - Conditions 3 (Materials), 5 (Biodiversity Enhancement Strategy) and 8 (Construction Management Plan)

    10 Sep 2026 Conditions