Planning application
The National Grid (Bramford To Twinstead Reinforcement) Order 2024
Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.
Proposal
Submission of details reserved by Requirement 4(1)(d) Landscape and Ecological Management Plan for Stage 6 of the authorised development pursuant to The National Grid (Bramford to Twinstead Reinforcement) Order 2024
As published by the council, reference DC/26/03850
Application record
- Reference
- DC/26/03850
- Type
- Discharge of Requirement
- Status
- Awaiting decision
- Received
- 4 Sep 2026
- Validated
- 4 Sep 2026
- Ward
- Assington
- Parish
- Assington
Comment by 25 September 2026
The council is taking comments on this application until then. Have your say on Mid Suffolk's portal.
Timeline
Dates from the published record
-
4 Sep 2026
Received by Mid Suffolk
-
7 Sep 2026
Added to PlanIndex
-
Decision
Awaiting decision
Decision expected by 30 October 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.
Mid Suffolk took a median of 48 days over the applications it decided in the last year.
What happens while it is decided
The process from here
This application is with Mid Suffolk for determination. The council publicises it, consults neighbours and technical bodies where required, and weighs the responses against local and national planning policy.
The statutory target is eight weeks for most applications and thirteen for major development, though extensions of time are common. Comments carry most weight while the case is undecided, so check the council portal for the deadline if you want to respond.
About conditions applications
How this application type works
This type of application deals with conditions attached to an existing permission, either by supplying the details a condition requires, called discharging it, or by asking to vary or remove one. It does not reopen the principle of the permission itself. Building often cannot lawfully start, or continue past a set stage, until the named conditions are discharged.
Nearby applications
Within 500 metres
-
The National Grid (Bramford To Twinstead Reinforcement) Order 2024
95% historically approved · decision due ~9 Jul
The National Grid (Bramford to Twinstead Reinforcement) Order 2024: Written notice of the commencement of construction of Stage 4.2 of the Authorised Development (Schedule 3, Requirement 3(4)) - commenced on 11 May 2026.
Awaiting decision Conditions -
The National Grid (Bramford To Twinstead Reinforcement) Order 2024
95% historically approved · decision due ~29 Oct
Submission of Details reserved by Requirement 4(a) - Construction Environmental Management Plan for Stages 6-8 of the authorised development pursuant to the The National Grid (Bramford to Twinstead Reinforcement) Order 2024
Awaiting decision Conditions -
The National Grid (Bramford To Twinstead Reinforcement) Order 2024
Submission of Details reserved by Requirement 6 - Detailed Written Scheme of Investigation (DWSI) for Stage 3 - pursuant to The National Grid (Bramford To Twinstead Reinforcement) Order 2024 to approve area(s) where no further archaeological investigation is required at land in vicinity of Polstead Heath, Holt Road and B1068, Leavenheath.
Granted Conditions 5 docs -
The National Grid (Bramford To Twinstead Reinforcement) Order 2024
Approval of Details reserved by Schedule 3, Requirement 3(1) - Notification of Pre-commencement Operations
Decided Conditions 1 doc -
The National Grid (Bramford To Twinstead Reinforcement) Order 2024
The National Grid (Bramford to Twinstead Reinforcement) Order 2024: Notification of Pre commencement Operation - temporary access at locations, BM1 and BM2 , associated with Stage 4 of the Authorised Development - The anticipated programme for these pre commencement operations is from Tuesday 14 April 2026 to Friday 22 May 2026.
Decided Conditions 2 docs -
The National Grid (Bramford To Twinstead Reinforcement) Order 2024
95% historically approved · decision due ~28 Oct
Submission of Details reserved by Requirement 6 - Detailed Written Scheme of Investigation (DWSI) for Stage 3 - pursuant to The National Grid (Bramford To Twinstead Reinforcement) Order 2024 to approve area(s) - where no further archaeological investigation is required at land in the vicinity of Trenches 359-366 - as marked on the attached plans.
Awaiting decision Conditions 1 doc
Other conditions applications
In Mid Suffolk
-
DC/26/03834 Awaiting decision
Land East And West Of Aubrey Drive Sudbury Part In The Parish Of Chilton
Discharge of Conditions Application for DC/21/06676 - 3 (Surface Water Managemet Strategy), 4 (Surface Water Management Strategy - Implementation and maintenance), 6 (Construction Surface Water Management Plan), 8 (Biodiversity Enhancement Strategy), 10 (Archaeological Works), 13 (Construction Management - Environmental protection), 14 (Construction Management - Highway Safety) and 15 (Landscaping Scheme)
-
DC/26/03842 Awaiting decision
The National Grid (Bramford To Twinstead Reinforcement) Order 2024
Submission of Details reserved by Requirement 4(a) - Construction Environmental Management Plan for Stages 6-8 of the authorised development pursuant to the The National Grid (Bramford to Twinstead Reinforcement) Order 2024
-
DC/26/03798 Awaiting decision
Land To The East Of Ely Road Barham Suffolk
Discharge of Conditions Application for DC/22/06117 - Discharge of Conditions 5 (Advance Planting), 6 (Landscape Management), 7 (Hard and Soft Landscaping), 9 (Open Space and Play Space), 19 (Fire Hydrants), 28 (Ecology Mitigation and Enhancement Measures), 30 (Landscape and Ecological Management Plan), 31 (Lighting Design Scheme for Biodiversity) and 32 (SPA and Ramsar Site)
-
DC/26/03802 Awaiting decision
The National Grid (Bramford To Twinstead Reinforcement) Order 2024
Submission of Details reserved by Requirement 6 - Detailed Written Scheme of Investigation (DWSI) for Stage 3 - pursuant to The National Grid (Bramford To Twinstead Reinforcement) Order 2024 to approve area(s) - where no further archaeological investigation is required at land in the vicinity of Trenches 359-366 - as marked on the attached plans.
-
DC/26/03799 Awaiting decision
1 Maple Close Stradbrooke IP21 5LZ
Discharge of Conditions Application for 0068/16 - Condition 6 (Materials)