Planning application
The Hall Hall Road Lavenham Sudbury Suffolk CO10 9QX
Relates to DC/25/04034
Permission granted. Work must normally begin within three years of the decision or the permission lapses.
Proposal
Discharge of Conditions Application for DC/25/04034 - Condition 2 (Materials and Finishes)
As published by the council, reference DC/26/01627
Application record
- Reference
- DC/26/01627
- Type
- Discharge of Condition(s)
- Status
- Granted
- Decision
- Granted
- Received
- 16 Apr 2026
- Validated
- 16 Apr 2026
- Decided
- 20 May 2026
- Ward
- Lavenham
- Parish
- Lavenham
- Decision by
- Delegated Decision
- Postcode
- CO10 9QX
Site history
Applications at this address on the Mid Suffolk register
This site has had 5 applications since 2025: 3 approved, 1 refused.
-
DC/26/03725 Awaiting decision
The Hall Hall Road Lavenham Sudbury Suffolk CO10 9QX
Application for works to trees in a Conservation Area - 2 x Black Poplar (T1 and T2 on sketch plan) - overall crown reduction by 5 metres
-
DC/26/01662 Granted
The Hall Hall Road Lavenham Sudbury Suffolk CO10 9QX
Application for a Non-Material Amendment relating to DC/25/04033 (subsequenlty approved under Appeal A ref 6004166)- Request for approval to move the gates further away from the carriageway (Hall Road, previously Potland Lane), to include a post and parcel box located in front of a new brick wall constructed using Camtech Anglian Red handmade bricks as previously approved and used for the wall dividing the original yard at the Hall and elsewhere in many other parts of the development. The provision of a small pedestrian gate using materials to match the main gates between the existing wall at the south end of the gates and the proposed location of the southern gate post.
-
DC/25/04034 Refused
The Hall Hall Road Lavenham Sudbury Suffolk CO10 9QX
Application for Listed Building Consent - Proposed replacement entrance gates
-
DC/25/03663 Granted
The Hall Hall Road Lavenham Sudbury Suffolk CO10 9QX
Discharge of Conditions Application for DC/24/03084 - Conditions 5 (Wall and Roof Materials) and 7 (Hard Surfacing Materials)
Timeline
Dates from the published record
-
16 Apr 2026
Received by Mid Suffolk
-
20 May 2026
Decision issued: Granted
-
24 Jul 2026
Added to PlanIndex
Related applications
Cases linked to this one on the register
-
DC/25/04034 Refused
The Hall Hall Road Lavenham Sudbury Suffolk CO10 9QX
Application for Listed Building Consent - Proposed replacement entrance gates
Who's behind it
Company information only, from the register and Companies House
Project 5 Architecture LLP Agent, an architecture practice registered in Royston
Active · incorporated 2007 · Royston
18 applications on PlanIndex · across 7 councils · 73% granted
Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.
See their track recordDocuments
Plans, drawings, consultee responses and the officer's report
4 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Watch members (£5 a month) open the document list from here.
Open the documentsWhat this grant of permission means
Mid Suffolk granted permission on 20 May 2026, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.
About condition discharge and variation applications
This application deals with conditions on an existing permission, supplying the details a condition requires or asking to vary or remove one, without reopening the permission itself. More in our guide to planning application types.
Nearby applications
Within 500 metres
-
The Hall Hall Road Lavenham Sudbury Suffolk CO10 9QX
99% historically approved · decision due ~23 Oct
Application for works to trees in a Conservation Area - 2 x Black Poplar (T1 and T2 on sketch plan) - overall crown reduction by 5 metres
Awaiting decision Trees 2 docs -
The Hall Hall Road Lavenham Sudbury Suffolk CO10 9QX
99% historically approved · decision due ~23 Oct
Application for works to trees in a Conservation Area - 2 x Black Poplar (T1 and T2 on sketch plan) - overall crown reduction by 5 metres
Awaiting decision Trees 2 docs -
The Hall Hall Road Lavenham Sudbury Suffolk CO10 9QX
Discharge of Conditions Application for DC/25/04034 - Condition 2 (Materials and Finishes)
Granted Conditions 4 docs -
The Hall Hall Road Lavenham Sudbury Suffolk CO10 9QX
Discharge of Conditions Application for DC/24/03084 - Conditions 5 (Wall and Roof Materials) and 7 (Hard Surfacing Materials)
Granted Conditions 6 docs -
The Hall Hall Road Lavenham Sudbury Suffolk CO10 9QX
Discharge of Conditions Application for DC/24/03084 - Conditions 5 (Wall and Roof Materials) and 7 (Hard Surfacing Materials)
Granted Conditions 6 docs -
The Hall Hall Road Lavenham CO10 9QX
Application for Listed Building Consent - Installation of new gates (as approved under Non-material Amendment DC/26/01662).
Granted Heritage and listed buildings 7 docs
Other condition discharge and variation applications
In Mid Suffolk
-
DC/26/03961 Awaiting decision
Wingfield College Church Road Wingfield Diss Suffolk IP21 5RA
Discharge of Conditions Application for DC/25/03300 - Condition 4 (Archaeological Post-Investigation) and 7 (Wildlife Enhancements)
-
DC/26/03962 Awaiting decision
Climax Molybdenum Uk Ltd Needham Road Stowmarket Suffolk IP14 2AE
Discharge of Conditions Application for DC/26/01041 - Condition 4 (Wildlife Enhancement Layout)
-
DC/26/03973 Awaiting decision
Grove Farm Queen Street Stradbroke Eye Suffolk IP21 5HH
Discharge of Conditions Application for DC/25/04640 - 6 (Roof Coverings)
-
DC/26/02777 Granted
24 Bolton Street Lavenham Sudbury Suffolk CO10 9RG
Discharge of Conditions Application for DC/24/00688 - Condition 3 (Biodiversity Enhancement)
-
DC/26/03937 Awaiting decision
The Nutshell Milton Road South Stowmarket Suffolk IP14 1EZ
Discharge of Conditions Application for DC/26/00753 - Conditions 3 (Materials), 5 (Biodiversity Enhancement Strategy) and 8 (Construction Management Plan)