Planning application
DC/26/01343
The National Grid (Bramford To Twinstead Reinforcement) Order 2024
Proposal
Approval of details for Requirement 4(d) - Landscape and Ecological Management Plan - Stage 3.4 of the authorised development pursuant to The National Grid (Bramford to Twinstead Reinforcement) Order 2024
As published by the council, reference DC/26/01343
Timeline
Dates from the published record
-
27 Mar 2026
Received by Mid Suffolk
-
7 May 2026
Decision issued: Granted
-
24 Jul 2026
Added to PlanIndex
What a grant of permission means
The process from here
Permission has been granted, usually subject to conditions listed on the decision notice, some of which must be discharged before work starts. The decision notice on the council portal sets out exactly what was approved.
Work must normally begin within three years of the decision or the permission lapses. Neighbours cannot appeal a grant; challenging one means judicial review of how the decision was made, within tight time limits.
About conditions applications
How this application type works
This type of application deals with conditions attached to an existing permission, either by supplying the details a condition requires, called discharging it, or by asking to vary or remove one. It does not reopen the principle of the permission itself. Building often cannot lawfully start, or continue past a set stage, until the named conditions are discharged.
Nearby applications
Within 500 metres
-
DC/26/02061 Awaiting decision
The National Grid (Bramford To Twinstead Reinforcement) Order 2024
The National Grid (Bramford to Twinstead Reinforcement) Order 2024: Written notice of the commencement of construction of Stage 4.2 of the Authorised Development (Schedule 3, Requirement 3(4)) - commenced on 11 May 2026.
-
DC/26/01485 Decided
The National Grid (Bramford To Twinstead Reinforcement) Order 2024
The National Grid (Bramford to Twinstead Reinforcement) Order 2024: Notification of Pre commencement Operation - temporary access at locations, BM1 and BM2 , associated with Stage 4 of the Authorised Development - The anticipated programme for these pre commencement operations is from Tuesday 14 April 2026 to Friday 22 May 2026.
-
DC/26/02150 Awaiting decision
The National Grid (Bramford To Twinstead Reinforcement) Order 2024
Submission of details reserved by Requirements 6 Archaeology for Stages 3, 4.1 and 4.2 of the The National Grid (Bramford To Twinstead Reinforcement) Order 2024
-
DC/26/02513 Decided
The National Grid (Bramford To Twinstead Reinforcement) Order 2024
The National Grid (Bramford to Twinstead Reinforcement) Order 2024: Notification of Commencement of Stage 11.1 'Works at Bramford Substation' of the Authorised Development (Schedule 3, Requirement 3(4))
-
DC/26/01541 Granted
The National Grid (Bramford To Twinstead Reinforcement) Order 2024
Submission of details reserved by Requirements 6 [Archaeology] for Stage 1 of the authorised development pursuant to The National Grid (Bramford to Twinstead Reinforcement) Order 2024
-
DC/26/01542 Granted
The National Grid (Bramford To Twinstead Reinforcement) Order 2024
Submission of Details reserved by Schedule 3, Requirement 14-1 Soil Management Plan for Stage 1 of the authorised development pursuant to The National Grid (Bramford to Twinstead Reinforcement) Order 2024
Other conditions applications
In Mid Suffolk
-
DC/26/03296 Awaiting decision
22 King Street Sudbury Suffolk CO10 2EN
Discharge of Conditions Application for DC/26/01545 - Conditions 3 (Floor Finishes) and 4 (Lighting)
-
DC/26/02972 Granted
Acorn Place Saxham Street Stowupland Stowmarket Suffolk IP14 5DA
Discharge of Conditions Application for DC/26/01170 - Condition 3 (Biodiversity Enhancement)
-
DC/26/03290 Awaiting decision
Valley Farm Valley Lane Buxhall Stowmarket Suffolk IP14 3EB
Discharge of Conditions Application for DC/26/02091 - Condition 4 (Great Crested Newt Licence)
-
DC/26/03292 Awaiting decision
Hop Hall Somerton Road Hartest Bury St Edmunds Suffolk IP29 4NA
Discharge of Conditions Application for DC/23/04860 - 4 (External Facing And Roofing Materials), 5 (Landscaping), 6 (Surface Water), 8 (Access), 9 (Refuse and Recycling Bins) and 11 (Gradient of Access and Driveway)
-
DC/26/03277 Awaiting decision
The Hovell 25 High Street Thorndon Eye Suffolk IP23 7LX
Discharge of Conditions Application for DC/26/00006 - Conditions 3 (Construction Management Plan), 4 (Biodiversity Method Statement), 5 (Surface Water Discharge Prevention), 6 (Roofing Material), 8 (Biodiversity Enhancement Strategy), 9 (Wildlife Sensitive Lighting Design scheme) and 10 (Cycle Storage)