Fulham Gas Works Imperial Road London

Granted Hammersmith and Fulham 2017/04956/DET Details to Meet Conditions Full/Outline

Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

Details of construction management plan, in compliance with condition 10 of planning permission (Ref.2016/02697/FUL) dated 2nd December 2016.

As published by the council, reference 2017/04956/DET

Application record

Reference
2017/04956/DET
Type
Details to Meet Conditions Full/Outline
Status
Application Approved
Decision
Granted As published: Application Approved
Received
27 Dec 2017
Validated
27 Dec 2017
Decided
7 Mar 2018
Ward
Parsons Green And Walham
Decision by
Delegated Decision

Site history

Applications at this address on the Hammersmith and Fulham register

This site has had 118 applications since 2017: 39 approved, 0 refused.

  • P/2026/02356/NMAT Awaiting decision

    Fulham Gas Works Imperial Road London

    Non-Material Amendment to Planning Permission (ref: 2018/02100/COMB) dated 8 February 2019 (as amended by ref: 2024/00961/VAR dated 3 December 2024), in respect of the description of development to change it from "Planning Application (part-detailed, part-outline) for demolition of existing buildings and structures (excl. No.2 Gasholder, 1856 Chief Engineer's Office, 1927 Research Laboratory, 1920 WWI War Memorial and WW2 War Memorial) and redevelopment to provide a residential-led mixed use development comprising the erection of new buildings" to "Planning Application (part-detailed, part-outline) for demolition of selected existing buildings and structures and redevelopment to provide a residential-led mixed use development comprising the erection of new buildings", specifically allowing the insertion of "selected" and the deletion of "(excl. No.2 Gasholder, 1856 Chief Engineer's Office, 1927 Research Laboratory, 1920 WWI War Memorial and WW2 War Memorial)"

    Submitted 11 Sep 2026 Amendments
  • P/2026/02015/DET Awaiting decision

    Fulham Gas Works Imperial Road London

    Details to discharge Condition 62 (Road Safety Audit) for Plot H1 (Phase 4b) pursuant to Planning Permission (ref: 2018/02100/COMB) dated 8 February 2019 as varied by (ref: 2024/00961/VAR dated 23 December 2024).

    Submitted 5 Aug 2026 Conditions
  • P/2026/01772/NMAT Awaiting decision

    Fulham Gas Works,Imperial Road,London

    Non-Material Amendment to Planning Permission (ref: 2018/02100/COMB ) dated 8 February 2019 (as amended by ref: 2024/00961/VAR dated 3 December 2024), in respect of Condition 73 (details and materials). The proposed amendment being the requirement of a mock up to be provided remotely for review by officers rather than on site.

    Submitted 13 Jul 2026 Amendments
  • Fulham Gas Works Imperial Road London

    Details of paint finishes, in compliance with Condition 3 of Listed Building Consent (ref: 2025/00568/LBC) dated 23 July 2026.

    Decided 17 Sep 2026 Conditions
  • Fulham Gas Works Imperial Road London

    Details to discharge Condition 20 (Verification Report) for Phases 3b, 3c and 3d (Development Plots E1 and E2) pursuant to Planning Permission (ref: 2018/02100/COMB) dated 8 February 2019 as varied by (ref: 2024/00961/VAR dated 23 December 2024).

    Decided 21 Jul 2026 Conditions
  • P/2026/01890/VAR Awaiting decision

    Fulham Gas Works Imperial Road London

    Variation of Condition 1 (Drawings) of reserved matters details relating to the approval of access; appearance; landscaping; layout and scale in respect of Phases 4b, 4c and 4d (Development Plots H1 and H2); for the erection of two buildings comprising residential and non-residential floorspace with associated landscaping approved under 2024/01420/RES granted 17 January 2025 of planning permission 2018/02100/COMB granted 8 February 2019 (as amended by refs 2020/01088/NMAT and 2024/00818/NMAT). As varied by 2024/00961/VAR variation of Condition 4 (Drawings) and Condition 5 (Design Codes and Parameter Plans) of planning permission 2018/02100/COMB granted 8 Feb 2019 (as amended by refs 2020/01088/NMAT and 2024/00818/NMAT). The proposed amendments to Phase 4b Development Plot H1 comprise: (a) revisions to tower and shoulder terrace heights within consented maximum parameter heights (comprising an increase in shoulder height and reduction in tower height); (b) changes to the arrangemen... read more

    Submitted 15 May 2026 Amendments
  • P/2026/01214/DET Awaiting decision

    Fulham Gas Works Imperial Road London

    Details to discharge Condition 16 (Preliminary Risk Assessment) for Development Phases 3a, 4a, 5a, 5b and 6 pursuant to Planning Permission (ref: 2018/02100/COMB) dated 8 February 2019 as varied by (ref: 2024/00961/VAR dated 23 December 2024).

    Submitted 6 May 2026 Conditions
  • Fulham Gas Works Imperial Road London

    Display of 1no. internally illuminated fascia sign and 2no. non-illuminated projecting signs to Unit 4a, phase 1

    Decided 3 Jul 2026 Advertising
  • P/2026/01024/DET Awaiting decision

    Fulham Gas Works Imperial Road London

    Details to discharge Condition 87 (Materials) for development Development Plot H1 (Phase 4b) pursuant to Planning Permission (ref: 2018/02100/COMB) dated 8 February 2019 as varied by (ref: 2024/00961/VAR dated 23 December 2024).

    Submitted 16 Apr 2026 Conditions
  • P/2026/01008/DET Awaiting decision

    Fulham Gas Works,Imperial Road,London

    Details to discharge Condition 74 (1:20 details) for development Development Plot H1 (Phase 4b) pursuant to Planning Permission (ref: 2018/02100/COMB) dated 8 February 2019 as varied by (ref: 2024/00961/VAR dated 23 December 2024)

    Submitted 14 Apr 2026 Conditions

Timeline

Dates from the published record

  1. 27 Dec 2017

    Received by Hammersmith and Fulham

  2. 7 Mar 2018

    Decision issued: Application Approved

  3. 9 Oct 2026

    Added to PlanIndex

Who's behind it

Company information only, from the register and Companies House

Deloitte Real Estate LLP Agent

175 applications on PlanIndex · across 9 councils · 100% granted

Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.

See their track record

Documents

Plans, drawings, consultee responses and the officer's report

7 documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Watch members (£5 a month) open the document list from here.

Open the documents

What this grant of permission means

Hammersmith and Fulham granted permission on 7 March 2018, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About condition discharge and variation applications

This application deals with conditions on an existing permission, supplying the details a condition requires or asking to vary or remove one, without reopening the permission itself. More in our guide to planning application types.

Nearby applications

Within 0.3 miles

  • Fulham Gas Works Imperial Road London SW6

    2018/03801/DET Submitted 21 Nov 2018 50 yards away

    Details of remediation method statement, in compliance with condition 7; details of verification report, in compliance with condition 8; details of long term monitoring methodology report, in compliance with condition 9 of planning permission 2016/02697/FUL dated 2nd December 2016.

    Granted Conditions 34 docs
  • Chelsea Creek Highways Depot Lots Road London SW10 0RN

    2025/00975/SCREIA Submitted 2 Apr 2025 50 yards away

    96% historically approved · decision due ~29 May

    Environmental Impact Assessment (EIA) request for a Screening Opinion made pursuant to Regulation 6(1) of the Town and Country Planning (EIA) Regulations 2017 (as amended) relating to a proposed development comprising a) the demolition of the existing buildings on the site; b) erection of three buildings comprising five blocks of up to 13 storeys plus basement, providing approximately 280 dwellings (including affordable extra care housing, affordable general needs housing and market housing) (Use Class C3) and approximately 2,100m2 commercial floor space (Use Classes E, F2 and Sui Generis) together with associated servicing, blue badge parking, bicycle storage and public realm; and c) works to the Chelsea Creek wall including construction of a new retaining wall, raising of the river defences to a height of up to 6.4m AOD and the provision of associated landscaping within Chelsea Creek.

    Decided Outline Demolition
    Major scheme
  • Fulham Gas Works Imperial Road London

    2018/03456/DET Submitted 22 Oct 2018 100 yards away

    Details of surface treatments and landscaping including details of planting, paving, boundary treatment and gates for the Pressure Reduction System (PRS), to discharge Condition 16 of planning permission 2015/04762/FUL dated 17th August 2016.

    Granted Conditions 17 docs
  • Fulham Gas Works Imperial Road London

    2018/01155/DET Submitted 5 Apr 2018 100 yards away

    Details of Surface Treatments and Landscaping, in compliance with condition 16 of planning permission 2015/04762/FUL dated 17th August 2016.

    Granted Conditions 13 docs
  • Fulham Gas Works Imperial Road London

    2018/03597/NMAT Submitted 5 Nov 2018 100 yards away

    Non Material Amendment to application ref 2015/04762/FUL dated 17th August 2016 for minor changes to the design of the approved wall.

    Withdrawn Amendments 11 docs
  • Fulham Gas Works Imperial Road London SW6

    2018/03808/DET Submitted 22 Nov 2018 100 yards away

    Details of remediation method statement, in compliance with condition 6 of planning permission 2015/04762/FUL dated 17th August 2016.

    Granted Conditions 164 docs

In Hammersmith and Fulham

  • 50 Brook Green, London, W6 7BJ

    Submission of a Demolition Logistics Plan, pursuant to Condition 4; a Construction Logistics Plan, pursuant to Condition 5; an updated Arboricultural Impact Assessment and Tree Protection Plan, pursuant to Condition 17; details of accessible units, pursuant to Condition 23; and details of Air Quality Emissions Control of Non-Road Mobile Machinery (NRMM), pursuant to Conditions 35 and 36 of the planning permission reference: 2025/00492/VAR dated 5th May 2026.

    Received 21 May, published by the council 24 Jul 2026 Conditions
  • 574 - 580 King's Road, London, SW6 2DY

    Submission of details of a Ventilation Strategy Report, pursuant to Condition 16 of the planning permission reference: 2025/01090/FUL dated 27th November 2025.

    Received 28 May, published by the council 24 Jul 2026 Conditions
  • P/2026/02566/DET Awaiting decision

    Former Dairy Crest Site,Land Beneath And Bounded By Westway And,West London Railway Line And Adjoining,58 Wood Lane,London W12

    Details to discharge Condition 12 (temporary fencing and/or enclosure) relating to Development Zone 3 ('DZ3') of planning planning permission 2025/02724/VAR dated 9 September 2026.

    Received 6 Oct, published by the council 9 Oct 2026 Conditions
  • P/2026/02562/DET Awaiting decision

    Former Dairy Crest Site,Land Beneath And Bounded By Westway And,West London Railway Line And Adjoining,58 Wood Lane,London W12

    Details to discharge Condition 21 (Piling Method Statement) relating to Development Zone 3 ('DZ3') of planning planning permission 2025/02724/VAR dated 9 September 2026.

    Received 6 Oct, published by the council 9 Oct 2026 Conditions
  • P/2026/02563/DET Awaiting decision

    Former Dairy Crest Site,Land Beneath And Bounded By Westway And,West London Railway Line And Adjoining,58 Wood Lane,London W12

    Details to discharge Condition 10 (Construction Management Plan (CMP)) of planning planning permission 2025/02724/VAR dated 9 September 2026.

    Received 6 Oct, published by the council 9 Oct 2026 Conditions