Planning application
Runcorn Carbon Dioxide Spur Pipeline
Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.
Proposal
Proposed construction of a new carbon dioxide spur pipeline, an Above Ground Installation (AGI), plus ancillary works and equipment to serve Viridor Energy from Waste (EfW) Facility Carbon Capture Plant at
As published by the council, reference 25/00293/FULEIA
Application record
- Reference
- 25/00293/FULEIA
- Type
- Other
- Status
- Registered
- Received
- 4 Jul 2025
- Validated
- 8 Jul 2025
- Ward
- Mersey & Weston
- Parish
- No Parish
Timeline
Dates from the published record
-
4 Jul 2025
Received by Halton
-
8 Jul 2025
Validated
Checked as complete and ready for consideration.
-
21 Jul 2026
Added to PlanIndex
-
Decision
Awaiting decision
Decision expected by 2 September 2025, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.
Halton took a median of 62 days over the applications it decided in the last year.
Who's behind it
Company information only, from the register and Companies House
WSP Ltd Agent, registered in Cobham
Active · incorporated 2001 · Cobham
735 applications on PlanIndex · across 136 councils · 96% granted
Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.
See their track recordDocuments
Plans, drawings, consultee responses and the officer's report
162 documents on file for this application
- RU.4.4 RUNCORN SPUR PIPELINE HABITAT REGULATIONS ASSESSMENT REV B
- TECHNICAL NOTE NATIONAL HIGHWAYS
- LBCCS SOIL STABILISATION CLARIFICATION
- RU.3.3.9.2 RUNCORN SPUR PIPELINE ES APPENDIX 9.2 - PRELIMINARY ECOLOGICAL ASSESS
- RU.3.3.9.2 RUNCORN SPUR PIPELINE ES APPENDIX 9.2 - PRELIMINARY ECOLOGICAL ASSESS
- APPLICATION FORM REDACTED
- RU.4.3 RUNCORN SPUR PIPELINE ANNEX D - STATUTORY_BIODIVERSITY_METRIC_CALCULATION
- RU.4.3 RUNCORN SPUR PIPELINE BIODIVERSITY NET GAIN ASSESSMENT REV B
- RU.2.3 RUNCRON SPUR PIPELINE - PLANNING DESIGN AND ACCESS STATEMENT REV B
- 70116228-RU.2.2.9-PLN-SHEET1 - ABOVE-GROUND PIPELINE SECTION - RUNCORN NORTH BRI
- 70116228-RU.2.2.8-PLN-SHEET1 - ABOVE-GROUND PIPELINE SECTION - TYPICAL PIPELINE
- 70116228-RU.2.2.7-EL-SHEET1 - INCE AGI EXISTING AND PROPOSED ELEVATIONS
- 70116228-RU.2.2.6-LAY-SHEET1 - INCE AGI EXISTING AND PROPOSED LAYOUT
- 70116228-RU.2.2.5-LAY-SHEET1 - RUNCORN AGI SITE PREPARATION LAYOUT
- 70116228-RU.2.2.4-EL-SHEET1 - RUNCORN AGI PROPOSED ELEVATIONS
- 70116228-RU.2.2.3-LAY-SHEET1 - RUNCORN AGI PROPOSED LAYOUT
- 70116228-RU.2.2.2-LAY-SHEET15 - PROPOSED SITE LAYOUT PLAN SHEET 15 OF 15
- 70116228-RU.2.2.2-LAY-SHEET14 - PROPOSED SITE LAYOUT PLAN SHEET 14 OF 15
- 70116228-RU.2.2.2-LAY-SHEET13 - PROPOSED SITE LAYOUT PLAN SHEET 13 OF 15
- 70116228-RU.2.2.2-LAY-SHEET12 - PROPOSED SITE LAYOUT PLAN SHEET 12 OF 15
- 70116228-RU.2.2.2-LAY-SHEET11 - PROPOSED SITE LAYOUT PLAN SHEET 11 OF 15
- 70116228-RU.2.2.2-LAY-SHEET10 - PROPOSED SITE LAYOUT PLAN SHEET 10 OF 15
- 70116228-RU.2.2.2-LAY-SHEET09 - PROPOSED SITE LAYOUT PLAN SHEET 09 OF 15
- 70116228-RU.2.2.2-LAY-SHEET08 - PROPOSED SITE LAYOUT PLAN SHEET 08 OF 15
- 70116228-RU.2.2.2-LAY-SHEET07 - PROPOSED SITE LAYOUT PLAN SHEET 07 OF 15
- 70116228-RU.2.2.2-LAY-SHEET06 - PROPOSED SITE LAYOUT PLAN SHEET 06 OF 15
- 70116228-RU.2.2.2-LAY-SHEET05 - PROPOSED SITE LAYOUT PLAN SHEET 05 OF 15
- 70116228-RU.2.2.2-LAY-SHEET04 - PROPOSED SITE LAYOUT PLAN SHEET 04 OF 15
- 70116228-RU.2.2.2-LAY-SHEET03 - PROPOSED SITE LAYOUT PLAN SHEET 03 OF 15
- 70116228-RU.2.2.2-LAY-SHEET02 - PROPOSED SITE LAYOUT PLAN SHEET 02 OF 15
- 70116228-RU.2.2.2-LAY-SHEET01 - PROPOSED SITE LAYOUT PLAN SHEET 01 OF 15
- 70116228-RU.2.2.13-LAY-SHEET1 - RUNCORN SPUR PIPELINE PROPOSED DEVELOPMENT AND T
- 70116228-RU.2.2.12-CX-SHEET1 - TYPICAL TRENCH CROSS SECTION
- 70116228-RU.2.2.11-PLN-SHEET1- GENERAL TYPICAL VERTICAL PIPELINE EXPANSION LOOP
- 70116228-RU.2.2.10-PLN-SHEET1 - ABOVE-GROUND PIPELINE SECTION - RUNCORN AND WEST
- 70116228-RU.2.2.1-SLP-SHEET1 - SITE LOCATION PLAN
- RU.4.2 RUNCORN SPUR PIPELINE OUTLINE CONSTRUCTION TRAFFIC MANAGEMENT PLAN
- RU.4.1 RUNCORN SPUR PIPELINE OUTLINE ENVIRONMENTAL MANAGEMENT PLAN
- RU.3.4.9.7 RUNCORN SPUR PIPELINE ES FIGURE 9.7 - CONSTRAINTS MAP REDACTED
- RU.3.4.9.6 RUNCORN SPUR PIPELINE ES FIGURE 9.6 - UKHAB CLASSIFICATION MAP
- RU.3.4.9.5 RUNCORN SPUR PIPELINE ES FIGURE 9.5 - OTHER AREAS OF CONSERVATION IMP
- RU.3.4.9.4 RUNCORN SPUR PIPELINE ES FIGURE 9.4 - NON-STATUTORY DESIGNATED SITES
- RU.3.4.9.3 RUNCORN SPUR PIPELINE ES FIGURE 9.3 - NATIONAL STATUTORY DESIGNATED S
- RU.3.4.9.2 RUNCORN SPUR PIPELINE ES FIGURE 9.2 - INTERNATIONAL STATUTORY DESIGNA
- RU.3.4.9.1 RUNCORN SPUR PIPELINE ES FIGURE 9.1 - SITE BOUNDARY
- RU.3.4.8.1 RUNCORN SPUR PIPELINE ES FIGURE 8.1 - KNOWN HERITAGE ASSETS
- RU.3.4.4.7 RUNCORN SPUR PIPELINE ES FIGURE 4.7 - DESIGN FREEZE 2 NORTH
- RU.3.4.4.6 RUNCORN SPUR PIPELINE ES FIGURE 4.6 - DESIGN FREEZE 1B AND NORTHERN R
- RU.3.4.4.5 RUNCORN SPUR PIPELINE ES FIGURE 4.5 - DESIGN FREEZE 1 RED LINE BOUNDA
- RU.3.4.4.4 RUNCORN SPUR PIPELINE ES FIGURE 4.4 - GOLDSET RESULTS
- RU.3.4.4.3 RUNCORN SPUR PIPELINE ES FIGURE 4.3 - ROUTE OPTIONS
- RU.3.4.4.2 RUNCORN SPUR PIPELINE ES FIGURE 4.2 - STRATEGIC CORRIDOR
- RU.3.4.4.1 RUNCORN SPUR PIPELINE ES FIGURE 4.1 - STUDY AREA
- RU.3.4.3.4 RUNCORN SPUR PIPELINE ES FIGURE 3.4 - MANCHESTER SHIP CANAL DEPOSIT G
- RU.3.4.3.3 RUNCORN SPUR PIPELINE ES FIGURE 3.3 - RUNCORN SPUR PIPELINE PROPOSED
- RU.3.4.3.2 RUNCORN SPUR PIPELINE ES FIGURE 3.2 - RUNCORN SPUR PIPELINE PROPOSED
- RU.3.4.3.1 RUNCORN SPUR PIPELINE ES FIGURE 3.1 - RED LINE BOUNDARY
- RU.3.4.18.1 RUNCORN SPUR PIPELINE ES FIGURE 18.1 - SHORT LIST OF OTHER DEVELOPME
- RU.3.4.17.3 RUNCORN SPUR PIPELINE ES FIGURE 17.3 - INDICATIVE DRAINAGE DESIGN
- RU.3.4.17.2 RUNCORN SPUR PIPELINE ES FIGURE 17.2 - PROTECTED AREAS
- RU.3.4.17.1 RUNCORN SPUR PIPELINE FIGURE 17.1 - WATERCOURSES (WITH CROSSINGS)
- RU.3.4.16.5 RUNCORN SPUR PIPELINE ES FIGURE 16.5 - PUBLIC RIGHTS OF WAY (PROW) D
- RU.3.4.16.4 RUNCORN SPUR PIPELINE ES FIGURE 16.4 - ACCESS LOCATIONS
- RU.3.4.16.3 RUNCORN SPUR PIPELINE ES FIGURE 16.3 - CONSTRUCTION TRAFFIC ROUTES
- RU.3.4.16.2 RUNCORN SPUR PIPELINE ES FIGURE 16.2 - PERSONAL INJURY ACCIDENT LOCA
- RU.3.4.16.1 RUNCORN SPUR PIPELINE ES FIGURE 16.1 - TRAFFIC AND TRANSPORT ZONE OF
- RU.3.4.15.2 RUNCORN SPUR PIPELINE ES FIGURE 15.2 - PUBLIC RIGHTS OF WAY (PROW)
- RU.3.4.15.1 RUNCORN SPUR PIPELINE ES FIGURE 15.1 - POPULATION AND HUMAN HEALTH S
- RU.3.4.14.2 RUNCORN SPUR PIPELINE ES FIGURE 14.2 - MAGNITUDE OF IMPACT, DAYTIME
- RU.3.4.14.1 RUNCORN SPUR PIPELINE ES FIGURE 14.1 - NOISE MONITORING LOCATIONS &
- RU.3.4.12.4 RUNCORN SPUR PIPELINE ES FIGURE 12.4 - VIEWPOINT LOCATION PLAN
- RU.3.4.12.3 RUNCORN SPUR PIPELINE ES FIGURE 12.3 - VIEWPOINT PHOTOGRAPHY (PART 4
- RU.3.4.12.3 RUNCORN SPUR PIPELINE ES FIGURE 12.3 - VIEWPOINT PHOTOGRAPHY (PART 3
- RU.3.4.12.3 RUNCORN SPUR PIPELINE ES FIGURE 12.3 - VIEWPOINT PHOTOGRAPHY (PART 2
- RU.3.4.12.3 RUNCORN SPUR PIPELINE ES FIGURE 12.3 - VIEWPOINT PHOTOGRAPHY (PART 1
- RU.3.4.12.2 RUNCORN SPUR PIPELINE ES FIGURE 12.2 - LANDSCAPE CHARACTER PLAN
- RU.3.4.12.1 RUNCORN SPUR PIPELINE ES FIGURE 12.1 - ZONE OF THEORETICAL VISIBILIT
- RU.3.3.9.9 RUNCORN SPUR PIPELINE ES APPENDIX 9.9 - AQUATIC MACROINVERTEBRATE AND
- RU.3.3.9.8 RUNCORN SPUR PIPELINE ES APPENDIX 9.8 - PRELIMINARY AQUATIC ECOLOGY A
- RU.3.3.9.7 RUNCORN SPUR PIPELINE ES APPENDIX 9.7 - RIPARIAN MAMMAL REPORT
- RU.3.3.9.5 RUNCORN SPUR PIPELINE ES APPENDIX 9.5 - GREAT CRESTED NEWT HSI AND ED
- RU.3.3.9.3 RUNCORN SPUR PIPELINE ES APPENDIX 9.3 - WINTERING BIRDS SURVEY REPORT
- RU.2.1.10 RUNCORN SPUR PIPELINE - SUSTAINABLE CONSTRUCTION CHECKLIST
- RU.2.1.2 RUNCORN SPUR PIPELINE - COVER LETTER CWCC
- RU.2.1.3 RUNCORN SPUR PIPELINE - COVER LETTER HBC
- RU.3.3.9.3 RUNCORN SPUR PIPELINE ES APPENDIX 9.3 - WINTERING BIRDS SURVEY REPORT
- RU.3.3.9.1 RUNCORN SPUR PIPELINE ES APPENDIX 9.1 - ARBORICULTURAL IMPACT ASSESSM
- RU.3.3.8.4 RUNCORN SPUR PIPELINE ES APPENDIX 8.4 - GEOARCHAEOLOGICAL DESK-BASED
- RU.3.3.8.3 RUNCORN SPUR PIPELINE ES APPENDIX 8.3 - GEOPHYSICAL SURVEY REPORT
- RU.3.3.8.2 RUNCORN SPUR PIPELINE ES APPENDIX 8.2 - CULTURAL HERITAGE IMPACT ASSE
- RU.3.3.8.1 RUNCORN SPUR PIPELINE ES APPENDIX 8.1 - CULTURAL HERITAGE BASELINE RE
- RU.3.3.6.2 RUNCORN SPUR PIPELINE ES APPENDIX 6.2 - AQ OPERATIONAL MODELLING
- RU.3.3.6.1 RUNCORN SPUR PIPELINE ES APPENDIX 6.1 - CONSTRUCTION DUST METHODOLOGY
- RU.3.3.5.1 RUNCORN SPUR PIPELINE ES APPENDIX 5.1 - TABLE OF RELEVANT EXPERTISE A
- RU.3.3.4.2 RUNCORN SPUR PIPELINE ES APPENDIX 4.2 - ALTERNATIVE ROUTE FEASIBILITY
- RU.3.3.4.1 RUNCORN SPUR PIPELINE ES APPENDIX 4.1 - GOLDSET WEIGHTING
- RU.3.3.18.2 RUNCORN SPUR PIPELINE ES APPENDIX 18.2 - INTRA-PROJECT EFFECTS ASSES
- RU.3.3.18.1 RUNCORN SPUR PIPELINE ES APPENDIX 18.1 - INTER-PROJECT EFFECTS ASSES
- RU.3.3.17.4 RUNCORN SPUR PIPELINE ES APPENDIX 17.4 - ASSESSMENT OF EFFECTS
- RU.3.3.17.3 RUNCORN SPUR PIPELINE ES APPENDIX 17.3 - WATER FRAMEWORK DIRECTIVE A
- RU.3.3.17.2 RUNCORN SPUR PIPELINE ES APPENDIX 17.2 - FLOOD RISK ASSESSMENT (PART
- RU.3.3.17.2 RUNCORN SPUR PIPELINE ES APPENDIX 17.2 - FLOOD RISK ASSESSMENT (PART
- RU.3.3.17.2 RUNCORN SPUR PIPELINE ES APPENDIX 17.2 - FLOOD RISK ASSESSMENT (PART
- RU.3.3.17.1 RUNCORN SPUR PIPELINE ES APPENDIX 17.1 - BASELINE INFORMATION
- RU.3.3.16.6 RUNCORN SPUR PIPELINE ES APPENDIX 16.6 - OUTLINE PUBLIC RIGHTS OF WA
- RU.3.3.16.5 RUNCORN SPUR PIPELINE ES APPENDIX 16.5 - FUTURE YEAR TRAFFIC DATA
- RU.3.3.16.4 RUNCORN SPUR PIPELINE ES APPENDIX 16.4 - BASELINE TRAFFIC DATA
- RU.3.3.16.3 RUNCORN SPUR PIPELINE ES APPENDIX 16.3 - INTERIM WORKER TRAVEL PLAN
- RU.3.3.16.2 RUNCORN SPUR PIPELINE ES APPENDIX 16.2 - TRANSPORT ASSESSMENT
- RU.3.3.16.1 RUNCORN SPUR PIPELINE ES APPENDIX 16.1 - METHODOLOGY.
- RU.3.3.14.3 RUNCORN SPUR PIPELINE ES APPENDIX 14.3 - NOISE AND VIBRATION ASSESSM
- RU.3.3.14.2 RUNCORN SPUR PIPELINE ES APPENDIX 14.2 - NOISE AND VIBRATION ASSESSM
- RU.3.3.14.1 RUNCORN SPUR PIPELINE ES APPENDIX 14.1 - BASELINE NOISE MONITORING D
- RU.3.3.13.3 RUNCORN SPUR PIPELINE ES APPENDIX 13.3 - MA&D IMPACT ASSESSMENT METH
- RU.3.3.13.2 RUNCORN SPUR PIPELINE ES APPENDIX 13.2 - ES RISK RECORD
- RU.3.3.13.1 RUNCORN SPUR PIPELINE ES APPENDIX 13.1 - MAJOR ACCIDENTS AND DISASTE
- RU.3.3.12.3 RUNCORN SPUR PIPELINE ES APPENDIX 12.3 - VISUAL ANALYSIS
- RU.3.3.12.2 RUNCORN SPUR PIPELINE ES APPENDIX 12.2 - LANDSCAPE ANALYSIS
- RU.3.3.12.1 RUNCORN SPUR PIPELINE ES APPENDIX 12.1 - LANDSCAPE AND VISUAL METHOD
- RU.3.3.11.2 LEACHATE SAMPLES ES APPENDIX 11.2 - PHASE 2 GEOENVIRONMENTAL 4 OF 4
- RU.3.3.11.2 SOIL VOC/SVOC SAMPLES ES APPENDIX 11.2 - PHASE 2 GEOENVIRONMENTAL 3
- RU.3.3.11.2 ANALYTICAL RESULTS ES APPENDIX 11.2 - PHASE 2 GEOENVIRONMENTAL 2 OF
- RU.3.3.11.2 ES APPENDIX 11.2 - PHASE 2 GEOENVIRONMENTAL 1 OF 4
- RU.3.3.11.1 RUNCORN SPUR PIPELINE ES APPENDIX 11.1 - PRELIMINARY RISK ASSESSMENT
- RU.3.3.11.1 RUNCORN SPUR PIPELINE ES APPENDIX 11.1 - PRELIMINARY RISK ASSESSMENT
- RU.3.3.11.1 RUNCORN SPUR PIPELINE ES APPENDIX 11.1 - PRELIMINARY RISK ASSESSMENT
- RU.3.3.11.1 RUNCORN SPUR PIPELINE ES APPENDIX 11.1 - PRELIMINARY RISK ASSESSMENT
- RU.3.3.11.1 RUNCORN SPUR PIPELINE ES APPENDIX 11.1 - PRELIMINARY RISK ASSESSMENT
- RU.3.3.1.3 RUNCORN SPUR PIPELINE ES APPENDIX 1.3 - SCOPING OPINION RESPONSES
- RU.3.3.1.2 RUNCORN SPUR PIPELINE ES APPENDIX 1.2 - SCOPING OPINION
- RU.3.3.1.1 RUNCORN SPUR PIPELINE ES APPENDIX 1.1 - SCOPING REPORT
- RU.3.2.9 RUNCORN SPUR PIPELINE ES CHAPTER 9 - BIODIVERSITY
- RU.3.2.8 RUNCORN SPUR PIPELINE ES CHAPTER 8 - CULTURAL HERITAGE
- RU.3.2.7 RUNCORN SPUR PIPELINE ES CHAPTER 7 - CLIMATE RESILIENCE
- RU.3.2.6 RUNCORN SPUR PIPELINE ES CHAPTER 6 - AIR QUALITY
- RU.3.2.5 RUNCORN SPUR PIPELINE ES CHAPTER 5 - EIA METHODOLOGY
- RU.3.2.4 RUNCORN SPUR PIPELINE ES CHAPTER 4 - CONSIDERATION OF ALTERNATIVES
- RU.3.2.3 RUNCORN SPUR PIPELINE ES CHAPTER 3 - DESCRIPTION OF THE RUNCORN SPUR PI
- RU.3.2.20 RUNCORN SPUR PIPELINE ES CHAPTER 20 - GLOSSARY AND ABBREVIATIONS
- RU.3.2.2 RUNCORN SPUR PIPELINE ES CHAPTER 2 - THE PROJECT
- RU.3.2.19 RUNCORN SPUR PIPELINE ES CHAPTER 19 - SUMMARY OF SIGNIFICANT EFFECTS
- RU.3.2.18 RUNCORN SPUR PIPELINE ES CHAPTER 18 - CUMULATIVE EFFECTS ASSESSMENT
- RU.3.2.17 RUNCORN SPUR PIPELINE ES CHAPTER 17 - WATER RESOURCES AND FLOOD RISK
- RU.3.2.16 RUNCORN SPUR PIPELINE ES CHAPTER 16 - TRAFFIC AND TRANSPORT
- RU.3.2.15 RUNCORN SPUR PIPELINE ES CHAPTER 15 - POPULATION AND HUMAN HEALTH
- RU.3.2.15 RUNCORN SPUR PIPELINE ES APPENDIX 15.1 - LAND USE ASSETS AND ACCESSIBI
- RU.3.2.14 RUNCORN SPUR PIPELINE ES CHAPTER 14 - NOISE AND VIBRATION
- RU.3.2.13 RUNCORN SPUR PIPELINE ES CHAPTER 13 - MAJOR ACCIDENTS AND DISASTERS
- RU.3.2.12 RUNCORN SPUR PIPELINE ES CHAPTER 12 - LANDSCAPE AND VISUAL
- RU.3.2.11 RUNCORN SPUR PIPELINE ES CHAPTER 11 - LAND AND SOILS
- RU.3.2.1 RUNCORN SPUR PIPELINE ES CHAPTER 1 - INTRODUCTION
- RU.3.1 RUNCORN SPUR PIPELINE ES NON-TECHNICAL SUMMARY
- RU.2.4 RUNCORN SPUR PIPELINE - STATEMENT OF COMMUNITY INVOLVEMENT (PART 3 OF 3)
- RU.2.4 RUNCORN SPUR PIPELINE - STATEMENT OF COMMUNITY INVOLVEMENT (PART 2 OF 3)
- RU.2.4 RUNCORN SPUR PIPELINE - STATEMENT OF COMMUNITY INVOLVEMENT (PART 1 OF 3)
- RU.2.1.9 RUNCORN SPUR PIPELINE - HEALTH IMPACT STATEMENT
- RU.2.1.8 RUNCORN SPUR PIPELINE - CIL FORM
- RU.2.1.7 RUNCORN SPUR PIPELINE - ARTICLE 13 NOTICE 2 PRESS NOTICE EXCERPT 2
- RU.2.1.6 RUNCORN SPUR PIPELINE - ARTICLE 13 NOTICE 2 PRESS NOTICE EXCERPT 1
- RU.2.1.5 RUNCORN SPUR PIPELINE - ARTICLE 13 LETTER
- RU.2.1.4 RUNCORN SPUR PIPELINE - ARTICLE 13 NOTICE 1
- RU.3.2.10 RUNCORN SPUR PIPELINE ES CHAPTER 10 - GREENHOUSE GAS
Watch members (£5 a month) open the document list from here.
Open the documentsWhat happens while it is decided
This application is with Halton for determination, against a statutory target of eight weeks. Over the last year Halton's median decision took 62 days. More in our guide to how long planning decisions take.
About less common application types
This application sits outside the common categories, and the council record linked on this page sets out the specific procedure that applies. More in our guide to planning application types.
Nearby applications
Within 0.3 miles
-
Land At Cross Lane Frodsham
94% historically approved · decision due ~10 Oct
Construction of a new Carbon Dioxide Spur Pipeline and Above Ground Installation (AGI) and ancillary equipment to serve the Viridor Energy from Waste (Efw) Facility Carbon Capture Plant
Awaiting decision Full applications 177 docs
Other less common application types
In Halton
-
26/00122/DEM Withdrawn
Colin Myers Timber And Sawmill Hale Road Widnes Cheshire WA8 8PX
Prior notification of proposed demolition of existing traditional construction (brick / blockwork) single-storey building and part demolition of existing portal frame building at
-
26/00118/HBCDEM Granted
Golden Triangle Industrial Estate Harrison Street Widnes Cheshire WA8 8TN
Prior notification of proposed demolition of buildings at
-
26/00135/HSC Awaiting decision
Univar Solutions CD&S UK Limited Hale Road Industrial Estate Pickerings Road Widnes WA8 8XW
Application for Hazardous Substances Consent at
-
23/00063/DEM Granted
Low Wood Keckwick Lane Daresbury Warrington Cheshire WA4 4AB
Prior notification of proposed demolition of bungalow at
-
23/00034/HBCDEM Granted
Wigg Island Visitor Centre Wigg Island Runcorn WA7 1PJ
Prior notification of proposed demolition of disused visitor centre at