Planning application
Site Adjacent To Velodrome Bounded By Springfield Road/ London Road Glasgow
Works: New dwelling
Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.
Proposal
Erection of residential development and commercial units with associated roads, parking, landscaping, services infrastructure and associated works.
As published by the council, reference 26/00688/FUL
Application record
- Reference
- 26/00688/FUL
- Type
- Full Planning Permission
- Status
- Pending - Consideration
- Received
- 1 Apr 2026
- Validated
- 6 May 2026
- Ward
- Calton
- Parish
- Bridgeton & Dalmarnock
Timeline
Dates from the published record
-
1 Apr 2026
Received by Glasgow City
-
6 May 2026
Validated
Checked as complete and ready for consideration.
-
28 Jul 2026
Added to PlanIndex
-
Decision
Awaiting decision
Decision expected by 1 July 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.
Glasgow City took a median of 77 days over the applications it decided in the last year.
Who's behind it
Company information only, from the register and Companies House
Montagu Evans LLP Agent, registered in London
Active · incorporated 2005 · London
1,330 applications on PlanIndex · across 128 councils · 97% granted
Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.
See their track recordWheatley Housing Group Limited Applicant, registered in Glasgow
Active · incorporated 2012 · Glasgow
1 application on PlanIndex
Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.
See their track recordDocuments
Plans, drawings, consultee responses and the officer's report
118 documents on file for this application
- REVISED SI REPORT PART 1
- REVISED SI REPORT PART 10
- REVISED SI REPORT PART 2
- REVISED SI REPORT PART 3
- REVISED SI REPORT PART 4
- REVISED SI REPORT PART 5
- REVISED SI REPORT PART 6
- REVISED SI REPORT PART 7
- REVISED SI REPORT PART 8
- REVISED SI REPORT PART 9
- PROP OVERLAND FLOOD ROUTING
- EVIDENCE OF PROFESSIONAL INDEMNITY INS-DRAINAGE STRATEGY
- PRIVATE BIO RETENTION SYSTEM DETAILS
- RESPONSE TO NRS FRM COMMENTS
- REVISED LEVELS LAYOUT
- COAL AUTHORITY
- REVISED PROPOSED SITE PLAN
- REVISED PROP SITE PLAN_PARKING STRATEGY
- REVISED PROP TYPICAL FLOOR_SITE PLAN
- REVISED PROP TYPICAL UPPER FLOOR_SITE PLAN
- SW
- LANDSCAPE MANAGEMENT AND MAINTENENCE SCHEDULE
- NOTIFICATION NEIGHBOURS LIST
- DRAINAGE IMPACT ASSESSMENT_PART3
- DRAINAGE IMPACT ASSESSMENT_PART4
- ARBORICULTURAL STATEMENT
- COVER LETTER
- DAYLIGHT AND SUNLIGHT IMPACT REPORT
- DAYLIGHT AND SUNLIGHT IMPACT REPORT_APPENDIX A_RESULTS
- DESIGN AND ACCESSS STATEMENT_PART1
- DESIGN AND ACCESSS STATEMENT_PART2
- DESIGN AND ACCESSS STATEMENT_PART3
- DESIGN AND ACCESSS STATEMENT_PART4
- DESIGN AND ACCESSS STATEMENT_PART5
- DESIGN AND ACCESSS STATEMENT_PART6
- DETENTION BASIN MAINTENANCE SCHEDULE GUIDANCE
- DRAINAGE IMPACT ASSESSMENT - ASSESSMENT COMPLIANCE CERTIFICATE
- DRAINAGE IMPACT ASSESSMENT - PROFESSIONAL INDEMNITY INSURANCE
- DRAINAGE IMPACT ASSESSMENT_PART1
- DRAINAGE IMPACT ASSESSMENT_PART2
- DRAINAGE IMPACT ASSESSMENT_PART3
- DRAINAGE IMPACT ASSESSMENT_PART4
- DRAINAGE IMPACT ASSESSMENT_PART5
- DRAINAGE STRATEGY - DRAINAGE LAYOUT
- DRAINAGE STRATEGY - LEVELS LAYOUT
- FLOOD RISK ASSESSMENT - COMPLIANCE CERTIFICATE
- FLOOD RISK ASSESSMENT
- FOOD RISK ASSESSMENT - INDEPENDENT CHECK CERTIFICATE
- INVASIVE WEEDS SURVEY
- A LOCATION PLAN
- NOISE IMPACT ASSESSMENT
- PLANNING STATEMENT
- APPLICATION PDF
- POROUS PAVING MAINTENANCE SCHEDULE GUIDANCE
- PRE APPLICATION CONSULTATION REPORT
- RAIN GARDEN MAINTENANCE SCHEDULE GUIDANCE
- SILT TRAP MAINTENANCE SCHEDULE GUIDANCE
- SITE INVESTIGATION REPORT_PART1
- SITE INVESTIGATION REPORT_PART2
- SITE INVESTIGATION REPORT_PART3
- SITE INVESTIGATION REPORT_PART4
- SITE INVESTIGATION REPORT_PART5
- SITE INVESTIGATION REPORT_PART6
- SITE INVESTIGATION REPORT_PART7
- SITE INVESTIGATION REPORT_PART8
- STATEMENT OF COMMUNITY BENEFIT
- STATEMENT ON ENERGY
- SURVEY PLAN
- TRANSPORT ASSESSMENT
- TREE SURVEY REPORT
- VORTEX FLOW CONTROL MAINTENANCE SCHEDULE GUIDANCE
- BLOCK A GA PLANS
- BLOCK A GROUND FLOOR
- BLOCK A ROOF PLAN
- BLOCK A TYPICAL FLOOR
- BLOCK A TYPICAL UPPER FLOOR
- BLOCK A_ELEVATIONS_FRONT ELEVATIONS
- BLOCK A_ELEVATIONS_REAR ELEVATIONS
- BLOCK A_PROPOSED AXONOMETRIC
- BLOCK A_SECTIONS
- BLOCK B AXONOMETRIC
- BLOCK B GA PLANS
- BLOCK B GROUND FLOOR
- BLOCK B ROOF PLAN
- BLOCK B TYPICAL FLOOR
- BLOCK B TYPICAL UPPER FLOOR
- BLOCK B_ELEVATIONS_LONDON ROAD
- BLOCK B_ELEVATIONS_REAR ELEVATION
- BLOCK B_ELEVATIONS_SPRINGFIELD ROAD
- BLOCK B_SECTIONS
- BLOCK C GA PLANS
- BLOCK C GROUND FLOOR
- BLOCK C ROOF PLAN
- BLOCK C TYPICAL FLOOR
- BLOCK C TYPICAL UPPER FLOOR
- BLOCK C_ ELEVATION_FRONT ELEVATIONS
- BLOCK C_ ELEVATION_GABLE ELEVATIONS
- BLOCK C_ ELEVATION_REAR ELEVATIONS
- BLOCK C_ GA SECTIONS
- BLOCK C_ PROPOSED AXONOMETRIC
- BLOCK D AND G GA ELEVATIONS
- BLOCK D AND G GA PLANS
- BLOCK E AND F GA ELEVATIONS
- BLOCK E AND F GA PLANS
- EXISTING SITE PLAN
- EXISTING SITE SECTIONS AND ELEVATIONS
- APPLICATION PDF
- PROPOSED ROOF SITE PLAN
- PROPOSED SITE AXONOMETRIC
- PROPOSED SITE ELEVATIONS AND SECTIONS - INTERIOR
- PROPOSED SITE ELEVATIONS AND SECTIONS - STREETS
- PROPOSED SITE PLAN
- PROPOSED SITE PLAN_CYCLE STORAGE
- PROPOSED SITE PLAN_FIRE STRATEGY
- PROPOSED SITE PLAN_PARKING STRATEGY
- PROPOSED SITE PLAN_REFUSE STRATEGY
- PROPOSED TYPICAL FLOOR 01 SITE PLAN
- PROPOSED TYPICAL UPPER FLOOR 05 SITE PLAN
Watch members (£5 a month) open the document list from here.
Open the documentsWhat happens while it is decided
This application is with Glasgow City for determination, against a statutory target of eight weeks. Over the last year Glasgow City decided full applications in a median of 93 days. More in our guide to how long planning decisions take.
About full applications
A full application seeks permission for a complete, detailed proposal in one go, with siting, design, access and landscaping all fixed at this stage. More in our guide to planning application types.
Other full applications
In Glasgow City
-
26/02254/FUL Awaiting decision
6 Cayton Gardens Glasgow G69 7LF
Erection of outbuilding to rear of dwellinghouse.
-
26/02233/FUL Awaiting decision
48 Kingslynn Drive Glasgow G44 4JA
Erection of two storey extension to side of dwellinghouse.
-
26/02210/FUL Awaiting decision
5 Aylmer Road Glasgow G43 2JN
Erection of outbuilding to rear and formation of French doors to rear of dwellinghouse
-
26/02209/FUL Awaiting decision
2 Penston Road Glasgow G33 4AG
Formation of hardstanding, installation of drainage infrastructure and external LED lighting and associated works.
-
26/02200/FUL Awaiting decision
22 Sandgate Avenue Glasgow G32 9PB
Alterations to roof of domestic garage associated with conversion to habitable accommodation