The Project comprises the following elements: - Construction of a 57km 400kV electricity transmission connection between Bridgwater in Somerset and Seabank, near Avonmouth, comprising: Installation of a 400kV overhead line (OHL). Installation of 400kV underground cables. - Modifications to existing OHLs at Hinkley Point, Somerset. - Construction of three 400kV Cable Sealing End (CSE) compounds along the route of the connection. - Construction of a 400/132kV substation at Sandford, North Somerset. - Extension of the existing 400kV substation at Seabank. - The removal of existing 132kV OHLs and the construction of replacement 132kV OHLs and 132kV underground cables. - Extensions/modifications to existing 132kV substations at Churchill, Portishead, Avonmouth and Seabank. - Associated works, for example, temporary access roads, highway works temporary construction compounds, scaffolds, work sites and ancillary works.
As published by the council, reference SCC/3699/2020
Application record
- Reference
- SCC/3699/2020
- Type
- Conditions
- Status
- Out to Consultation/ Decision Pending
- Received
- 10 Mar 2020
- Validated
- 10 Mar 2020
- Postcode
- TA5 1YA
Site history
Applications at this address on the Exmoor National Park register
This site has had 2 applications since 2020.
-
SCC/3696/2020 Awaiting decision
Hinkley C Connection Project Hinkley Point Road Stogursey Bridgwater TA5 1YA
The Project comprises the following elements: - Construction of a 57km 400kV electricity transmission connection between Bridgwater in Somerset and Seabank, near Avonmouth, comprising: Installation of a 400kV overhead line (OHL). Installation of 400kV underground cables. - Modifications to existing OHLs at Hinkley Point, Somerset. - Construction of three 400kV Cable Sealing End (CSE) compounds along the route of the connection. - Construction of a 400/132kV substation at Sandford, North Somerset. - Extension of the existing 400kV substation at Seabank. - The removal of existing 132kV OHLs and the construction of replacement 132kV OHLs and 132kV underground cables. - Extensions/modifications to existing 132kV substations at Churchill, Portishead, Avonmouth and Seabank. - Associated works, for example, temporary access roads, highway works temporary construction compounds, scaffolds, work sites and ancillary works.
Timeline
Dates from the published record
-
10 Mar 2020
Received by Exmoor National Park
-
12 Oct 2026
Added to PlanIndex
-
Decision
Awaiting decision
Decision expected by 5 May 2020, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.
Exmoor National Park took a median of 47 days over the applications it decided in the last year.
Documents
Plans, drawings, consultee responses and the officer's report
4 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Watch members (£5 a month) open the document list from here.
Open the documentsWhat happens while it is decided
This application is with Exmoor National Park for determination, against a statutory target of eight weeks. Over the last year Exmoor National Park decided condition discharge and variation applications in a median of 43 days. More in our guide to how long planning decisions take.
About condition discharge and variation applications
This application deals with conditions on an existing permission, supplying the details a condition requires or asking to vary or remove one, without reopening the permission itself. More in our guide to planning application types.
Nearby applications
Within 0.3 miles
-
Hinkley Point A- Encapsulation Plant Nr Bridgwater Somerset TA5 1YA
Application For Non-Material Amendment pursuant to Planning Permission 3/32/17/005 for the construction and operation of a Waste Encapsulation Plant
Granted Amendments -
Revetment, Hinkley Point A Site, Stogursey, TA5 1YA
Structural alterations to a revetment to include reprofiling of the bank
Granted Full applications 22 docs -
Hinkley Point C - Connection Project Hinkley Point Road Stogursey Bridgwater Somerset TA5 1YA
Details to satisfy Requirement 24 (1) - Scheme of marking The Project comprises the following elements: - Construction of a 57km 400kV electricity transmission connection between Bridgwater in Somerset and Seabank, near Avonmouth, comprising: Installation of a 400kV overhead line (OHL). Installation of 400kV underground cables. - Modifications to existing OHLs at Hinkley Point, Somerset. - Construction of three 400kV Cable Sealing End (CSE) compounds along the route of the connection. - Construction of a 400/132kV substation at Sandford, North Somerset. - Extension of the existing 400kV substation at Seabank. - The removal of existing 132kV OHLs and the construction of replacement 132kV OHLs and 132kV underground cables. - Extensions/modifications to existing 132kV substations at Churchill, Portishead, Avonmouth and Seabank. - Associated works, for example, temporary access roads, highway works temporary construction compounds, scaffolds, work sites and ancillary works.
Withdrawn Conditions Extension 5 docs -
Hinkley Point A, Hinkley Point Road, Stogursey, TA5 1YA
Installation of a ventilation discharge stack to the concrete box loading facility (Building 124) with associated concrete slab, shield wall and crash barrier
Granted Other 2 docs -
Hinkley C Connection Project Hinkley Point Road Stogursey Bridgwater TA5 1YA
95% historically approved · decision due ~22 Apr
The Project comprises the following elements: - Construction of a 57km 400kV electricity transmission connection between Bridgwater in Somerset and Seabank, near Avonmouth, comprising: Installation of a 400kV overhead line (OHL). Installation of 400kV underground cables. - Modifications to existing OHLs at Hinkley Point, Somerset. - Construction of three 400kV Cable Sealing End (CSE) compounds along the route of the connection. - Construction of a 400/132kV substation at Sandford, North Somerset. - Extension of the existing 400kV substation at Seabank. - The removal of existing 132kV OHLs and the construction of replacement 132kV OHLs and 132kV underground cables. - Extensions/modifications to existing 132kV substations at Churchill, Portishead, Avonmouth and Seabank. - Associated works, for example, temporary access roads, highway works temporary construction compounds, scaffolds, work sites and ancillary works.
Awaiting decision Conditions Extension 9 docs -
Hinkley Point C - Connection Project Hinkley Point Road Stogursey Bridgwater Somerset TA5 1YA
National Grid Hinkley Point C - connection Project The National Grid (Hinkley Point C Connection Project) Order 2016 (as amended) Planning Inspectorate Reference Number: EN020001 Discharge of Requirement 26 – Traffic Incident Management Plan for Stage 7.2 of the authorised development The Project comprises the following elements: - Construction of a 57km 400kV electricity transmission connection between Bridgwater in Somerset and Seabank, near Avonmouth, comprising: Installation of a 400kV overhead line (OHL). Installation of 400kV underground cables. - Modifications to existing OHLs at Hinkley Point, Somerset. - Construction of three 400kV Cable Sealing End (CSE) compounds along the route of the connection. - Construction of a 400/132kV substation at Sandford, North Somerset. - Extension of the existing 400kV substation at Seabank. - The removal of existing 132kV OHLs and the construction of replacement 132kV OHLs and 132kV underground cables. - Extensions/modifications to existing 132kV substations at Churchill, Portishead, Avonmouth and Seabank. - Associated works, for example, temporary access roads, highway works temporary construction compounds, scaffolds, work sites and ancillary works.
Withdrawn Conditions Extension 4 docs
Other condition discharge and variation applications
In Exmoor National Park
-
34/26/00005 Granted
Land to the East of, Back Lane, Middlezoy, Bridgwater, Somerset, TA7
Application for modification of Planning Obligation (Section 106 Agreement) dated 28/07/2023 relating to Planning Permission 34/21/00008 to vary the mortgagee exclusion clause (MEC) Schedule 3 Part 5 (Mortgagee and Exercise of Other Rights).
-
2026/1957/APP Awaiting decision
The Old Engine Shed Upper Vobster Road Vobster Frome Somerset BA3 5SD
Approval of details reserved by condition 8 (Contaminated Land Verification Report) on planning consent 2024/1135/FUL (Change use from commercial storage (B8) to residential (Use Class C3). Single storey extension & erection of garage)
-
2026/1570/APP Granted
Land East Of Norton Hall Beauchamps Drive Stratton On The Fosse Shepton Mallet Somerset
Approval of details reserved by condition 26 (arboricultural method statement) on consent 2021/0157/OTS.
-
2026/1962/APP Awaiting decision
The Old Inn Roemead Road Green Ore Wells Somerset BA5 3ES
Approval of details reserved by condition 3 (Method of Attachment - Submission of details) 4 (Opening Up Works - Method Statement and Schedule) 5 (Re-pointing - Submission of details) 6 (Rendering - Submission of details) 7 (Joinery Details) 8 (Ducts, Pipes, Rainwater Goods etc - Submission of Details) on listed building consent 2025/0745/LBC
-
2026/1951/APP Awaiting decision
The Old Inn Roemead Road Green Ore Wells Somerset BA5 3ES
Approval of details reserved by condition 3 (Method of Attachment - Submission of details) 4 (Opening Up Works - Method Statement and Schedule) 5 (Re-pointing - Submission of details) 6 (Rendering - Submission of details) 7 (Joinery Details) 8 (Ducts, Pipes, Rainwater Goods etc - Submission of Details) on planning consent 2025/0744/HSE