Change of use from BT Standard KX100 Series public telephone kiosk to a Standard KX100 Series with new antenna containing small cell equipment and fan vent, and removal of one kiosk.

As published by the council, reference 2020/4874/P

Timeline

Dates from the published record

  1. 9 Feb 2022

    Decision issued: Refused

  2. 22 Jul 2026

    Added to PlanIndex

What refusal means

The process from here

The council refused this application for the reasons set out on the decision notice, which the council portal holds in full. Only the applicant can appeal a refusal; the time limit runs from the decision date and is shorter for householder schemes.

Refusal does not prevent a fresh attempt. Applicants often address the reasons for refusal and resubmit, so a refused scheme is not necessarily the end of proposals for the site.

About full applications applications

How this application type works

A full application seeks permission for a complete, detailed proposal in one go: siting, design, access and landscaping are all fixed at this stage. It is the standard route for new buildings, conversions and changes of use. The statutory target is eight weeks for smaller schemes and thirteen weeks for major development, though complex cases often take longer by agreement.

More on full applications applications in our guide

Nearby applications

Within 500 metres

  • 2016/4926/L Granted

    UCL Cruciform Building Gower Street London WC1E 6AE

    The works involve replacing the existing heating, steam and condensate pipework that are currently in a sub-basement duct which runs between the adjacent Rockefeller Building and The Cruciform Building. The route of the new pipework runs at basement level via the link tunnel between the two buildings and vaults adjacent to The Cruciform Building. As part of the re-routing the pipework will need to leave the vaults, cross the lightwell and enter The Cruciform Building basement plantroom via new core drilled holes. The reason for the re-routing is that the structural condition and presence of asbestos would entail a prolonged shutdown of the existing services .

    13 Dec 2016 0m away Heritage and listed buildings
  • 2015/3519/L Granted

    Ucl Cruciform Building Gower Street London WC1E 6AU

    Approval of condition 5b (2012/6522/L) For: The erection of a glazed extension at ground floor level to provide entrance and 2x roof lights at ground level on the Gower street elevation, opening up of blocked up windows at lower ground floor level along Gower Street elevation and installation of new windows to match existing and associated internal alterations at lower ground level all in connection with existing educational facility (Class D1)

    23 Nov 2015 0m away Heritage and listed buildings
  • 2013/7657/L Granted

    UCL Cruciform Building Gower Street London WC1E 6AU

    Condition 5 a) Details of lighting design; part 5 b) Stair door, moulding & architrave; part 5 c) New joinery details; 5 d) Sample of roofing material, of listed building consent (2012/6522/L) dated 11/02/2013 for the erection of glazed extension entrance at ground floor level and various alterations.

    24 Jan 2014 0m away Heritage and listed buildings
  • 2016/2168/L Granted

    UCL Cruciform Building Gower Street London WC1E 6AE

    Refurbishment of existing laboratory at Wing 2.1 on second floor.

    5 Aug 2016 0m away Heritage and listed buildings
  • 2026/2863/L Awaiting decision

    UCL Cruciform Building Gower Street London WC1E 6BT

    Replacement of existing chiller units at Level 01 roof level with 4no. heat pump cabinets and 4no. flatbed dry air coolers; reconfiguration of plant screen; installation of an access ladder, alongside associated works.

    3 Jul 2026 0m away Heritage and listed buildings
  • 2026/2804/P Awaiting decision

    UCL Cruciform Building Gower Street London WC1E 6BT

    Replacement of existing chiller units at Level 01 roof level with 4no. heat pump cabinets and 4no. flatbed dry air coolers; reconfiguration of plant screen; installation of an access ladder, alongside associated works.

    3 Jul 2026 0m away Full applications

In Camden

  • 2026/0743/P Granted

    34-42 Middlesex House Cleveland Street London W1T 4JE

    Details pursuant to Condition 6 (Living Roof) of planning permission 2024/2020/P granted on 12/09/2024 "(Minor refurbishment and rooftop works including: upgraded entrance and reception area; new cycle storage and associated end of trip facilities; new/replaced rooftop plant and plant enclosures; creation of a rooftop amenity area with pavilion structure; hard and soft rooftop landscaping; and all associated and ancillary works)."

    25 Feb 2026 Full applications
  • 2026/3202/P Awaiting decision

    Flat 1 94 Goldhurst Terrace London NW6 3HS

    Erection of a single storey rear extension.

    30 Jul 2026 Full applications
  • 2026/0335/P Granted

    216A West End Lane London NW6 1UX

    Conversion of 1 x 7 bedroom flat (C3) and 1 x 2 bedroom flat (C3) to 1 x 7 bedroom House in Multiple Occupation (Sui-generis) and 1 x 1 bedroom flat (C3) and installation of four rooflights

    28 Jan 2026 Full applications
  • 2026/3229/P Awaiting decision

    52 Neal Street London WC2H 9PA

    Alterations to the shopfront and installation of awnings.

    29 Jul 2026 Full applications
  • 2026/2160/P Granted

    120 College Place London NW1 0DJ

    Erection of a rear roof extension, formation of a rear roof terrace and installation of 2x rooflights to front roof slope, and associated works.