Planning application
UCL Cruciform Building Gower Street London WC1E 6AE
Permission granted. Work must normally begin within three years of the decision or the permission lapses.
Proposal
Refurbishment of existing laboratory at Wing 2.1 on second floor.
As published by the council, reference 2016/2168/L
Application record
- Reference
- 2016/2168/L
- Category
- Heritage and listed buildings
- Status
- Final Decision
- Decision
- Granted
- Decided
- 5 Aug 2016
- Postcode
- WC1E 6AE
Site history
Applications at this address on the Camden register
This site has had 2 applications since 2016: 2 approved, 0 refused.
-
2016/4926/L Granted
UCL Cruciform Building Gower Street London WC1E 6AE
The works involve replacing the existing heating, steam and condensate pipework that are currently in a sub-basement duct which runs between the adjacent Rockefeller Building and The Cruciform Building. The route of the new pipework runs at basement level via the link tunnel between the two buildings and vaults adjacent to The Cruciform Building. As part of the re-routing the pipework will need to leave the vaults, cross the lightwell and enter The Cruciform Building basement plantroom via new core drilled holes. The reason for the re-routing is that the structural condition and presence of asbestos would entail a prolonged shutdown of the existing services .
Timeline
Dates from the published record
-
5 Aug 2016
Decision issued: Granted
-
22 Jul 2026
Added to PlanIndex
What this grant of permission means
Camden granted permission on 5 August 2016, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.
About heritage and listed building applications
Listed building consent is needed for works that affect the special interest of a listed building, and carrying out such works without it is a criminal offence. More in our guide to planning application types.
Nearby applications
Within 0.3 miles
-
UCL Cruciform Building Gower Street London WC1E 6AE
The works involve replacing the existing heating, steam and condensate pipework that are currently in a sub-basement duct which runs between the adjacent Rockefeller Building and The Cruciform Building. The route of the new pipework runs at basement level via the link tunnel between the two buildings and vaults adjacent to The Cruciform Building. As part of the re-routing the pipework will need to leave the vaults, cross the lightwell and enter The Cruciform Building basement plantroom via new core drilled holes. The reason for the re-routing is that the structural condition and presence of asbestos would entail a prolonged shutdown of the existing services .
Granted Heritage and listed buildings -
Ucl Cruciform Building Gower Street London WC1E 6AU
Approval of condition 5b (2012/6522/L) For: The erection of a glazed extension at ground floor level to provide entrance and 2x roof lights at ground level on the Gower street elevation, opening up of blocked up windows at lower ground floor level along Gower Street elevation and installation of new windows to match existing and associated internal alterations at lower ground level all in connection with existing educational facility (Class D1)
Granted Heritage and listed buildings Extension Loft or dormer +1 -
UCL Cruciform Building Gower Street London WC1E 6AU
Condition 5 a) Details of lighting design; part 5 b) Stair door, moulding & architrave; part 5 c) New joinery details; 5 d) Sample of roofing material, of listed building consent (2012/6522/L) dated 11/02/2013 for the erection of glazed extension entrance at ground floor level and various alterations.
Granted Heritage and listed buildings Extension Windows or glazing -
UCL Cruciform Building Gower Street London WC1E 6BT
96% historically approved · decision due ~2 Sep
Replacement of existing chiller units at Level 01 roof level with 4no. heat pump cabinets and 4no. flatbed dry air coolers; reconfiguration of plant screen; installation of an access ladder, alongside associated works.
Awaiting decision Heritage and listed buildings 2 docs -
UCL Cruciform Building Gower Street London WC1E 6BT
91% historically approved · decision due ~2 Sep
Replacement of existing chiller units at Level 01 roof level with 4no. heat pump cabinets and 4no. flatbed dry air coolers; reconfiguration of plant screen; installation of an access ladder, alongside associated works.
Awaiting decision Full applications 14 docs -
o/s UCH Cruciform Building, Gower Street BT Public Telephone Kiosk Public Footway London Gower Street WC1E 6AE
Change of use from BT Standard KX100 Series public telephone kiosk to a Standard KX100 Series with new antenna containing small cell equipment and fan vent, and removal of one kiosk.
Refused Full applications
Other heritage and listed building applications
In Camden
-
2026/3449/L Awaiting decision
Alexandra & Ainsworth TRA Hall 100 Rowley Way London NW8 0SW
Reconstuction of roof loggia and roof lantern drainage channel pursuant to planning permission ref 2023/3413/P and listed building consent ref 2023/4012/L granted on 18/12/2024, for various works of roof repair and replacement.
-
2026/3087/L Granted
205 Albany Street London NW1 4AB
Installation of a free standing air source heat pump in the rear courtyard. Installation of an innovative, thin and flexible PV panels to the flat section of the roof
-
2026/4003/L Awaiting decision
10 Sicilian Avenue London Camden WC1A 2QH
Internal alterations to ground floor and basement level, including new partitions and mechanical ventillation.
-
2026/4002/L Awaiting decision
Flat A 4 Rowley Way London NW8 0SF
Internal refurbishment including replacement of non-original kitchen and bathroom fittings, repair and refinishing of original internal timber joinery, replacement of floor finishes and internal redecoration.
-
2026/3990/L Awaiting decision
Unison Centre 130 Euston Road London Camden NW1 2AY
Repair and refurbishment works.