Planning application
Land At Lower Stock Farm Bakers Lane Langford Churchill
Permission granted. Work must normally begin within three years of the decision or the permission lapses.
Proposal
Full planning application for the construction and operation of a ground mounted solar array and battery energy storage system, associated infrastructure and landscape and biodiversity enhancements.
As published by the council, reference 24/P/1011/FUL
Application record
- Reference
- 24/P/1011/FUL
- Type
- Full Application
- Status
- Decided
- Decision
- Approve
- Received
- 16 May 2024
- Validated
- 24 May 2024
- Decided
- 18 Dec 2024
- Ward
- Blagdon And Churchill
- Parish
- Churchill
- Decision by
- Delegated Decision
Timeline
Dates from the published record
-
16 May 2024
Received by Bristol, City of
-
24 May 2024
Validated
Checked as complete and ready for consideration.
-
18 Dec 2024
Decision issued: Approve
-
28 Aug 2026
Added to PlanIndex
Who's behind it
Company information only, from the register and Companies House
Agent on file, a design practice registered in Brighton
23 applications on PlanIndex · across 11 councils · 100% granted
Trade members see who it is, their full track record, and every application they have filed.
See who's behind itApplicant on file, registered in London
1 application on PlanIndex
Trade members see who it is, their full track record, and every application they have filed.
See who's behind itDocuments
Plans, drawings, consultee responses and the officer's report
106 documents on file for this application
- DECISION (FUL) APPROVE
- NORTH SOMERSET OFFICER REPORT
- HTDM COMMENTS
- GREEN INFRASTRUCTURE PLAN REV 02
- COVER LETTER DATED 15 OCT 2024
- LANDSCAPE AND ECOLOGICAL MANAGEMENT PLAN - UPDATED SEPTEMBER 2024
- BNG REPORT - REVISED OCTOBER 2024
- BNG REPORT - APPENDICES
- BNG REPORT - FIGURES
- BNG METRIC TOOL - OCTOBER 2024
- BNG METRIC TOOL - ITERATION 3 - OCTOBER 2024
- HABITAT EVALUATION PROCEDURE ASSESSMENT - ADDENDUM REPORT
- HVG BUILDING - REV B
- HABITAT EVALUATION PROCESS (HEP) WORKSHEET - REVISED 01-10-24
- DOCUMENT ISSUE SHEET - NO.23
- DOCUMENT FROM MEMBER OF THE PUBLIC
- LANDSCAPE COMMENTS
- UPDATED APPLICANTS RESPONSE TO HIGHWAYS COMMENTS
- GRID ROUTE CONSTRUCTION METHODOLOGY
- ENVIRONMENT AGENCY COMMENTS
- LLFA COMMENTS
- EA COMMENTS
- BESS FIRE PROTECTION DRAINAGE MEASURES
- LLFA COMMENTS
- HTDM COMMENTS
- ENVIRONMENT AGENCY COMMENTS
- SUPPLEMENTARY COMMENT
- COMMENTS FROM MR TONY HARDEN
- INTERNAL DRAINAGE BOARD COMMENTS
- GENERAL PV LAYOUT
- ENVIRONMENTAL PROTECTION TEAM COMMENTS
- WRINGTON PARISH COUNCIL COMMENTS
- ECOLOGY COMMENTS
- PRESS ADVERT LIST FOR 06/06/24
- BNG METRIC
- APPLICATION FORM REDACTED
- TREE CONSTRAINTS PLAN OVERVIEW
- TREE CONSTRAINT PLANS - S1 TO S9
- TREE PROTECTION PLAN OVERVIEW
- TREE PROTECTION PLANS S1 TO S13
- COVER LETTER
- GREEN INFRASTRUCTURE PLAN
- LANDSCAPE & ECOLOGICAL MANAGEMENT PLAN
- PLANNING, DESIGN & ACCESS STATEMENT
- SITE LOCATION PLAN
- PUBLIC RIGHTS OF WAY
- FRA & DRAINAGE STRATEGY - PART 1
- FRA & DRAINAGE STRATEGY - PART 2
- FRA & DRAINAGE STRATEGY - PART 3
- FRA & DRAINAGE STRATEGY - PART 4
- FRA & DRAINAGE STRATEGY - PART 5
- FRA & DRAINAGE STRATEGY - PART 6
- APPENDIX 7 - FIGURES 01 TO 03B
- APPENDIX 7 - FIGURES 04 TO 06
- APPENDIX 7 - FIGURES 19A TO 19G ILLUSTRATIVE VIEWPOINTS A TO K
- APPENDIX 7 - FIGURE 21 VIEWPOINT 4 SHEETS 1 TO 3
- APPENDIX 7 - FIGURE 22 VIEWPOINT 9 SHEETS 1 TO 3
- APPENDIX 7 - FIGURE 23 VIEWPOINT 11 SHEETS 1 TO 3
- APPENDIX 7 - FIGURE 24 VIEWPOINT 12 SHEETS 1 TO 3
- APPENDIX 7 - FIGURES 25 TO 26
- CIL FORM 1 - ADDITIONAL INFORMATION FORM
- STATEMENT OF COMMUNITY INVOLVEMENT
- BNG REPORT
- BNG REPORT - FIGURES
- BNG REPORT - APPENDICES
- ABORICULTURAL IMPACT ASSESSMENT
- CONSTRUCTION TRAFFIC MANAGEMENT PLAN
- ECOLOGICAL APPRAISAL
- ECOLOGICAL APPRAISAL - PHOTOGRAPHS
- ECOLOGICAL APPRAISAL - FIGURES
- ECOLOGICAL APPRAISAL - APPENDICES
- GLINT ASSESSMENT
- HISTORIC ENVIRONMENT DBA
- NOISE IMPACT ASSESSMENT
- TREE SURVEY
- GEOPHYSICAL SURVEY PART 1 - HEADLAND ARCHAEOLOGY
- GEOPHYSICAL SURVEY PART 2
- GEOPHYSICAL SURVEY PART 3
- GEOPHYSICAL SURVEY PART 4
- GEOPHYSICAL SURVEY PART 5
- NST PRESS NOTICE 24 APRIL 2024
- HABITATS REGULATIONS ASSESSMENT
- HABITATS REGULATIONS ASSESSMENT - FIGURES
- HABITATS REGULATIONS ASSESSMENT - APPENDICES
- PV SITE LAYOUT PLAN
- COMPOUND LAYOUT
- TOPOGRAPHY LINES
- MONITORING CABIN
- HVG BUILDING FLOOR PLANS
- HVG BUILDING ELEVATIONS
- BESS - SECTIONS AND ELEVATIONS
- STORAGE CONTAINER - ELEVATIONS AND PLAN VIEW
- INTERNAL TRACK SECTION DETAIL
- FENCE ELEVATION
- GATE ELEVATION
- PV PANELS FRAMEWORK ELEVATIONLEVATION
- CCTV ELEVATION
- LV TRENCH SECTION DETAIL
- MV TRENCH SECTION DETAIL
- TRANSFORMER STATION ELEVATION
- EDGE OF PARK SWITCHGEAR STATION ELEVATIONS AND PLAN VIEW
- WEATHER STATION ELEVATION
- AGRICULTURAL CONSIDERATIONS
- APPENDIX 7 - FIGURES 07 TO 18 REPRESENTATIVE VIEWPOINTS 1 TO 12
- APPENDIX 7 - FIGURE 20
- APPENDIX 7 - FIGURE 27
Trade members open them from here.
Open the documentsWhat this grant of permission means
Bristol, City of granted permission on 18 December 2024, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.
About full applications
A full application seeks permission for a complete, detailed proposal in one go, with siting, design, access and landscaping all fixed at this stage. More in our guide to planning application types.
Other full applications
In Bristol, City of
-
26/P/1249/FUL Granted
47 Corondale Road Weston-super-Mare BS22 8PY
Proposed erection of 1.5 storey dwelling house in the rear garden area.
-
26/P/1407/FUL Granted
37 Orchard Street Weston-super-Mare BS23 1RH
Proposed infill extension of internal courtyard and reconfiguration to form Deli and Storage Area.
-
26/P/1334/FUL Granted
Building To NE Of Open Acres Backwell Hill Backwell BS48 3EJ
Change of use of part of a building from workshop into 4no. units of short-term visitor accommodation (Class C1) and associated building operations (all retrospective)
-
26/P/1323/FUL Granted
14 Portland Drive Portishead BS20 6YQ
Proposed erection of a single-storey flat roof rear extension.
-
26/P/1083/FUL Granted
Flat H 1 South Road Weston-super-Mare BS23 2HA
Proposed replacement of all first floor windows with new UPVC casement windows.