Planning application
The National Grid (Bramford To Twinstead Reinforcement) Order 2024
Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.
Proposal
Approval of Details reserved by Schedule 3, Requirement 14(1) - Soil Management Plan - Stage 3 pursuant to The National Grid (Bramford To Twinstead Reinforcement) Order 2024
As published by the council, reference DC/25/04512
Application record
- Reference
- DC/25/04512
- Type
- Discharge of Requirement
- Status
- Awaiting decision
- Received
- 10 Oct 2025
- Validated
- 10 Oct 2025
Site history
Applications at this address on the Babergh register
This site has had 75 applications since 2025: 38 approved, 1 refused.
-
DC/26/04408 Awaiting decision
The National Grid (Bramford To Twinstead Reinforcement) Order 2024
Submission of Details reserved by Requirement 6 Detailed Written Scheme of Investigation for Stage 3 of the authorised development pursuant to The National Grid (Bramford To Twinstead Reinforcement) Order 2024
-
DC/26/04237 Awaiting decision
The National Grid (Bramford To Twinstead Reinforcement) Order 2024
Approval of Details reserved by Stage 3 Requirement 6 of the Detailed Written Scheme of Investigation (DWSI) pursuant to the The National Grid (Bramford To Twinstead Reinforcement) Order 2024 to approve area(s) - where no further archaeological investigation is required at land in the vicinity of Trenches 367-370 - as marked on the attached plans.
-
DC/26/04195 Awaiting decision
The National Grid (Bramford To Twinstead Reinforcement) Order 2024
Approval of Details reserved by Stage 3 Requirement 6 of the Detailed Written Scheme of Investigation (DWSI) pursuant to the The National Grid (Bramford To Twinstead Reinforcement) Order 2024 to approve area(s) - where no further archaeological investigation is required at land in the vicinity of Trenches 305-320 - as marked on the attached plans.
-
DC/26/04067 Awaiting decision
The National Grid (Bramford To Twinstead Reinforcement) Order 2024
Submission of Details reserved by Schedule 3; Requirement 8 Retention and Removal of Trees, Woodlands and Hedgerows Plan for Stage 6 of the authorised development pursuant to The National Grid (Bramford to Twinstead Reinforcement) Order 2024
-
DC/26/04076 Awaiting decision
The National Grid (Bramford To Twinstead Reinforcement) Order 2024
Submission of Details reserved by Requirement 8(1) Retention and Removal of Trees, Woodlands and Hedgerows for Stage 8 of the authorised development pursuant to The National Grid (Bramford to Twinstead Reinforcement) Order 2024
-
DC/26/04068 Awaiting decision
The National Grid (Bramford To Twinstead Reinforcement) Order 2024
Submission of Details reserved by Requirement 8(1) Retention and Removal of Trees, Woodlands and Hedgerows for Stage 7 of the authorised development pursuant to The National Grid (Bramford To Twinstead Reinforcement) Order 2024
-
DC/26/04022 Awaiting decision
The National Grid (Bramford To Twinstead Reinforcement) Order 2024
Submission of Detials reserved by Requirement 14 - Soil Management Plan for Stages 6-8 of the authorised development pursuant to The National Grid (Bramford to Twinstead Reinforcement) Order 2024
-
DC/26/03944 Awaiting decision
The National Grid (Bramford To Twinstead Reinforcement) Order 2024
Submission of Details reserved by Requirement 4(1)(d) - Landscape and Ecological Management Plan for Stage 8 of the authorised development pursuant to The National Grid (Bramford to Twinstead Reinforcement) Order 2024
-
DC/26/03938 Awaiting decision
The National Grid (Bramford To Twinstead Reinforcement) Order 2024
Submission of Details reserved by Requirement 4(1)(d) Landscape and Ecological Management Plan for Stage 7 of the authorised development pursuant to The National Grid (Bramford to Twinstead Reinforcement) Order 2024
-
DC/26/03856 Awaiting decision
The National Grid (Bramford To Twinstead Reinforcement) Order 2024
Submission of Details reserved by Requirement 8 Retention and Removal of Trees, Woodlands and Hedgerows Plan for Stage 4.2 of the authorised development pursuant to The National Grid (Bramford To Twinstead Reinforcement) Order 2024
Timeline
Dates from the published record
-
10 Oct 2025
Received by Babergh
-
9 Aug 2026
Added to PlanIndex
-
Decision
Awaiting decision
Decision expected by 5 December 2025, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.
Babergh took a median of 52 days over the applications it decided in the last year.
Documents
Plans, drawings, consultee responses and the officer's report
2 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Watch members (£5 a month) open the document list from here.
Open the documentsWhat happens while it is decided
This application is with Babergh for determination, against a statutory target of eight weeks. Over the last year Babergh decided condition discharge and variation applications in a median of 49 days. More in our guide to how long planning decisions take.
About condition discharge and variation applications
This application deals with conditions on an existing permission, supplying the details a condition requires or asking to vary or remove one, without reopening the permission itself. More in our guide to planning application types.
Nearby applications
Within 0.3 miles
-
The National Grid (Bramford To Twinstead Reinforcement) Order 2024
95% historically approved · decision due ~30 Oct
Submission of details reserved by Requirement 4(1)(d) Landscape and Ecological Management Plan for Stage 6 of the authorised development pursuant to The National Grid (Bramford to Twinstead Reinforcement) Order 2024
Awaiting decision Conditions -
The National Grid (Bramford To Twinstead Reinforcement) Order 2024
The National Grid (Bramford to Twinstead Reinforcement) Order 2024: Written notice of the commencement of construction of Stage 4.2 of the Authorised Development (Schedule 3, Requirement 3(4)) - commenced on 11 May 2026.
Awaiting decision Conditions 1 doc -
The National Grid (Bramford To Twinstead Reinforcement) Order 2024
95% historically approved · decision due ~29 Oct
Submission of Details reserved by Requirement 4(a) - Construction Environmental Management Plan for Stages 6-8 of the authorised development pursuant to the The National Grid (Bramford to Twinstead Reinforcement) Order 2024
Awaiting decision Conditions 1 doc -
The National Grid (Bramford To Twinstead Reinforcement) Order 2024
Submission of Details reserved by Requirement 6 - Detailed Written Scheme of Investigation (DWSI) for Stage 3 - pursuant to The National Grid (Bramford To Twinstead Reinforcement) Order 2024 to approve area(s) where no further archaeological investigation is required at land in vicinity of Polstead Heath, Holt Road and B1068, Leavenheath.
Granted Conditions 5 docs -
The National Grid (Bramford To Twinstead Reinforcement) Order 2024
Approval of Details reserved by Schedule 3, Requirement 3(1) - Notification of Pre-commencement Operations
Decided Conditions 1 doc -
The National Grid (Bramford To Twinstead Reinforcement) Order 2024
95% historically approved · decision due ~30 Oct
Submission of Details reserved by Requirement 8 Retention and Removal of Trees, Woodlands and Hedgerows Plan for Stage 4.2 of the authorised development pursuant to The National Grid (Bramford To Twinstead Reinforcement) Order 2024
Awaiting decision Conditions Trees 8 docs
Other condition discharge and variation applications
In Babergh
-
DC/26/00236 Granted
Chilton Woods Mixed Development To North Of Woodhall Business Park Sudbury Suffolk
Discharge of Conditions Application for B/15/01718 - Part discharge of Conditions 38 (Landscaping) and 43 (Open Space) for phase 4 only.
-
DC/26/00355 Refused
Land To The Rear Of 30 Market Hill Sudbury Suffolk
Application under Section 73 of The Town and Country Planning Act 1990 - Variation of Condition 2 (Approved Plans and Documents) and Condition 12 (Provision of Access Prior to Any Other Works Commencing) of Planning Permission DC/25/05227 dated 23/01/2026 - Erection of 4No. (terraced) dwellings and alterations/improvement to: (1) outbuilding to form cycle store, (2) boundary wall and (3) existing access.
-
DC/26/04408 Awaiting decision
The National Grid (Bramford To Twinstead Reinforcement) Order 2024
Submission of Details reserved by Requirement 6 Detailed Written Scheme of Investigation for Stage 3 of the authorised development pursuant to The National Grid (Bramford To Twinstead Reinforcement) Order 2024
-
DC/26/04407 Awaiting decision
High Elm Bungalow Crowfield Road Stonham Aspal Suffolk
Discharge of Conditions Application for DC/24/01026 - Condition 3 (Biodiversity Net Gain)
-
DC/26/04395 Awaiting decision
Little Wenham Hall Hall Lane Wenham Parva Colchester Suffolk CO7 6PZ
Discharge of Conditions for DC/24/02709 - Condition 14 (Historic Floor Finishes- Building D)