The National Grid (Bramford To Twinstead Reinforcement) Order 2024

Decided Babergh DC/25/04004 Discharge of Requirement

Decided. The decision notice on the council portal carries the outcome in full, including any conditions.

Proposal

Approval of Details reserved by Schedule 3, Requirement 3(1) - Notification of Pre-commencement Operations

As published by the council, reference DC/25/04004

Application record

Reference
DC/25/04004
Type
Discharge of Requirement
Status
Awaiting decision
Decision
Comment
Received
9 Sep 2025
Validated
9 Sep 2025
Decided
16 Sep 2025
Decision by
Delegated Decision

Timeline

Dates from the published record

  1. 9 Sep 2025

    Received by Babergh

  2. 16 Sep 2025

    Decision issued: Comment

  3. 9 Aug 2026

    Added to PlanIndex

Documents

Plans, drawings, consultee responses and the officer's report

1 document on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Trade members open them from here.

Open the documents

After the decision

The process from here

The council has decided this application; the published outcome sits in the record above and the decision notice on the council portal carries the detail, including any conditions.

If permission was granted, work must normally begin within three years of the decision. If it was refused, the applicant can appeal within the statutory time limit or submit a revised scheme.

About conditions applications

How this application type works

This type of application deals with conditions attached to an existing permission, either by supplying the details a condition requires, called discharging it, or by asking to vary or remove one. It does not reopen the principle of the permission itself. Building often cannot lawfully start, or continue past a set stage, until the named conditions are discharged.

More on conditions applications in our guide

Nearby applications

Within 500 metres

  • The National Grid (Bramford To Twinstead Reinforcement) Order 2024

    DC/26/03850 Submitted 4 Sep 2026 0m away

    95% historically approved · decision due ~30 Oct

    Submission of details reserved by Requirement 4(1)(d) Landscape and Ecological Management Plan for Stage 6 of the authorised development pursuant to The National Grid (Bramford to Twinstead Reinforcement) Order 2024

    Awaiting decision Conditions
  • The National Grid (Bramford To Twinstead Reinforcement) Order 2024

    DC/26/02061 Submitted 14 May 2026 0m away

    95% historically approved · decision due ~9 Jul

    The National Grid (Bramford to Twinstead Reinforcement) Order 2024: Written notice of the commencement of construction of Stage 4.2 of the Authorised Development (Schedule 3, Requirement 3(4)) - commenced on 11 May 2026.

    Awaiting decision Conditions
  • The National Grid (Bramford To Twinstead Reinforcement) Order 2024

    DC/26/03842 Submitted 3 Sep 2026 0m away

    95% historically approved · decision due ~29 Oct

    Submission of Details reserved by Requirement 4(a) - Construction Environmental Management Plan for Stages 6-8 of the authorised development pursuant to the The National Grid (Bramford to Twinstead Reinforcement) Order 2024

    Awaiting decision Conditions
  • The National Grid (Bramford To Twinstead Reinforcement) Order 2024

    DC/26/03080 Submitted 16 Jul 2026 0m away

    Submission of Details reserved by Requirement 6 - Detailed Written Scheme of Investigation (DWSI) for Stage 3 - pursuant to The National Grid (Bramford To Twinstead Reinforcement) Order 2024 to approve area(s) where no further archaeological investigation is required at land in vicinity of Polstead Heath, Holt Road and B1068, Leavenheath.

    Granted Conditions 5 docs
  • The National Grid (Bramford To Twinstead Reinforcement) Order 2024

    DC/25/04004 Submitted 9 Sep 2025 0m away

    Approval of Details reserved by Schedule 3, Requirement 3(1) - Notification of Pre-commencement Operations

    Decided Conditions 1 doc
  • The National Grid (Bramford To Twinstead Reinforcement) Order 2024

    DC/26/01485 Submitted 7 Apr 2026 0m away

    The National Grid (Bramford to Twinstead Reinforcement) Order 2024: Notification of Pre commencement Operation - temporary access at locations, BM1 and BM2 , associated with Stage 4 of the Authorised Development - The anticipated programme for these pre commencement operations is from Tuesday 14 April 2026 to Friday 22 May 2026.

    Decided Conditions 2 docs

In Babergh

  • DC/26/03850 Awaiting decision

    The National Grid (Bramford To Twinstead Reinforcement) Order 2024

    Submission of details reserved by Requirement 4(1)(d) Landscape and Ecological Management Plan for Stage 6 of the authorised development pursuant to The National Grid (Bramford to Twinstead Reinforcement) Order 2024

    4 Sep 2026 Conditions
  • DC/26/03834 Awaiting decision

    Land East And West Of Aubrey Drive Sudbury Part In The Parish Of Chilton

    Discharge of Conditions Application for DC/21/06676 - 3 (Surface Water Managemet Strategy), 4 (Surface Water Management Strategy - Implementation and maintenance), 6 (Construction Surface Water Management Plan), 8 (Biodiversity Enhancement Strategy), 10 (Archaeological Works), 13 (Construction Management - Environmental protection), 14 (Construction Management - Highway Safety) and 15 (Landscaping Scheme)

    3 Sep 2026 Conditions
  • DC/26/03842 Awaiting decision

    The National Grid (Bramford To Twinstead Reinforcement) Order 2024

    Submission of Details reserved by Requirement 4(a) - Construction Environmental Management Plan for Stages 6-8 of the authorised development pursuant to the The National Grid (Bramford to Twinstead Reinforcement) Order 2024

    3 Sep 2026 Conditions
  • DC/26/03458 Granted

    Land East Of Old Station Road Mendlesham Suffolk

    Discharge of Conditions Application for DC/24/04832 - Condition 26 (Site investigation and post investigation assessment)

    11 Aug 2026 Conditions
  • DC/26/03798 Awaiting decision

    Land To The East Of Ely Road Barham Suffolk

    Discharge of Conditions Application for DC/22/06117 - Discharge of Conditions 5 (Advance Planting), 6 (Landscape Management), 7 (Hard and Soft Landscaping), 9 (Open Space and Play Space), 19 (Fire Hydrants), 28 (Ecology Mitigation and Enhancement Measures), 30 (Landscape and Ecological Management Plan), 31 (Lighting Design Scheme for Biodiversity) and 32 (SPA and Ramsar Site)