Alyth-Tealing 400kV OHL Upgrade (ECU00005167)

Granted Angus 24/00754/S37 Overhead Power Line Consent

Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

Consultation to Angus Council from Energy Consents Unit for the Alyth-Tealing 400kV OHL Project - (ECU Reference ECU00005167)

As published by the council, reference 24/00754/S37

Application record

Reference
24/00754/S37
Type
Overhead Power Line Consent
Status
No Objection
Decision
Granted As published: No Objection
Received
18 Dec 2024
Validated
18 Dec 2024
Decided
12 Mar 2025
Ward
Monifieth & Sidlaw
Parish
Tealing
Decision by
Delegated

Timeline

Dates from the published record

  1. 18 Dec 2024

    Received by Angus

  2. 12 Mar 2025

    Decision issued: No Objection

  3. 13 Aug 2026

    Added to PlanIndex

Documents

Plans, drawings, consultee responses and the officer's report

5 documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Watch members (£5 a month) open the document list from here.

Open the documents

What this grant of permission means

Angus granted permission on 12 March 2025, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About less common application types

This application sits outside the common categories, and the council record linked on this page sets out the specific procedure that applies. More in our guide to planning application types.

In Angus

  • 25/00564/S37 Granted

    Emmock & Tealing Overhead Line Tie-ins Tealing

    ECU consultation on Emmock and Tealing OHL tie-ins. The proposed development comprises the diversion of short sections of the Alyth to Tealing and Westfield to Tealing 275kv OHL. An opinion is also sought under the same submission for the installation of two short sections of parallel 275kv OHL tiebacks between the proposed Emmock substation and Tealing substation.

    Received 16 Oct, published by the council 28 Jul 2026 Other
  • 25/00374/HAZ Granted

    Drambond Sir William Smith Road Kirkton Industrial Estate Arbroath DD11 3RD

    Use of warehouse for storage of whisky casks

    Received 3 Jul, published by the council 22 Aug 2026 Other
  • 25/00512/S37 Granted

    New Substation At Emmock Near Tealing And An Existing Substation At Kintore Aberdeenshire

    Operate and keep installed approximately 105.2 kilometre (km) 400 kV Overhead Line (OHL), supported on steel lattice tower structures including downleads, between a proposed new substation named Emmock near to Tealing in Angus and an existing substation at Kintore, Aberdeenshire

    Received 19 Sep, published by the council 28 Jul 2026 Other
  • 24/00700/HAZ Withdrawn

    2 James Chalmers Road Kirkton Industrial Estate Arbroath DD11 3RD

    Use of warehouse for storage of whisky casks

    Received 19 Nov, published by the council 11 Oct 2026 Other
  • 24/00598/S37 Granted

    Field 490M North East Of Airlie Lodge Cortachy Kirriemuir

    Relocation of 1 x Pole, Installation of 4 x Poles, Removal of 4 x Poles and Realignment of 11kV Overhead Line and Ancillary Works (Retrospective)

    Received 18 Jun, published by the council 1 Sep 2026 Other