Condition 2b)i, 2b)ii, 2b)iii, 2b)iv, 2b)v, 2b)vi, 2b)vii, 2b)viii, 2b)ix, 2b)x (Development Phase - 400kV and 132KV Substation) of Planning Permission of Planning Permission ref: APP/2024/1714 for Erection of a Strategic Electricity Transmission Hub Including 400kV AC Substation, 132kV AC Substation, 2 HVDC Converter Stations, Transmission Hall, Spares Warehouse, Operations Base and Associated Works
As published by the council, reference APP/2026/1104
Application record
- Reference
- APP/2026/1104
- Type
- Approval of Matters Specified in Conds
- Status
- Awaiting decision
- Received
- 26 Jun 2026
- Validated
- 24 Jul 2026
- Ward
- Central Buchan
- Parish
- Longside & District
Timeline
Dates from the published record
-
26 Jun 2026
Received by Aberdeenshire
-
24 Jul 2026
Validated
Checked as complete and ready for consideration.
-
5 Aug 2026
Added to PlanIndex
-
Decision
Awaiting decision
Decision expected by 18 September 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.
Aberdeenshire took a median of 64 days over the applications it decided in the last year.
Related applications
Cases linked to this one on the register
-
APP/2024/1714 Granted
Netherton Hub Land To The West Of Parkhill Farm Blackhills Peterhead
National for Erection of a Strategic Electricity Transmission Hub Including 400kV AC Substation, 132kV AC Substation, 2 HVDC Converter Stations, Transmission Hall, Spares Warehouse, Operations Base and Associated Works
1 later application on the register refers to this one:
-
APP/2026/1713 Awaiting decision
Longside AC Substation Netherton Hub Land To The West Of Parkhill Farm Blackhills Peterhead
Discharge of Conditions 7 (Construction Traffic Management Plan) and 8 (CEMP) of Planning Permission Reference APP/2024/1714 - National for Erection of a Strategic Electricity Transmission Hub Including 400kV AC Substation, 132kV AC Substation, 2 HVDC Converter Stations, Transmission Hall, Spares Warehouse, Operations Base and Associated Works (in Association with MSC Application ref: APP/2026/1104)
Documents
Plans, drawings, consultee responses and the officer's report
81 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Watch members (£5 a month) open the document list from here.
Open the documentsWhat happens while it is decided
This application is with Aberdeenshire for determination, against a statutory target of eight weeks. Over the last year Aberdeenshire decided condition discharge and variation applications in a median of 84 days. More in our guide to how long planning decisions take.
About condition discharge and variation applications
This application deals with conditions on an existing permission, supplying the details a condition requires or asking to vary or remove one, without reopening the permission itself. More in our guide to planning application types.
Nearby applications
Within 0.3 miles
-
Land Approximately 1.2 Km To The South Of A950 Longside Peterhead Aberdeenshire AB42 0LY
Consultation under Section 36 of the Electricity Act 1989 for the Installation of Battery Energy Storage System (BESS) with an Installed Capacity of up to 400MW and Associated Works
Granted Other 149 docs -
House To The South West Longleys Longside Aberdeenshire AB42 3ED
Demolition of Dwellinghouse
Granted Prior approval Demolition 9 docsDomestic
Other condition discharge and variation applications
In Aberdeenshire
-
APP/2026/1059 Granted
Plots 26 & 27 Queen Elizabeth Drive South Of Pheppie Burn Chapelton Stonehaven
Condition 3J (Layout, Siting, Design and Finish) of Planning Permission in Principle Reference APP/2011/3100 for New Settlement Comprising Residential (Up to 4045 Dwellinghouses), Commercial, Retail and Community Facilities with Associated Landscaping, Open Space, Drainage and Roads Infrastructure and Services
-
APP/2026/0959 Granted
Land At Backhill Lenabo Kinknockie Mintlaw Aberdeenshire AB42 5BA
Condition 2(a) Layout, Siting, (b) External Appearance, Finishing Materials, (c) Landscaping, (d) Levels, Cross Sections, Finished Floor Levels, (e) Drainage, (f) Means of Access, Visibility Splays, (g) Car Parking, Vehicle Turning Area, (h) Biodiversity Enhancement Plan of Planning Permission Reference APP/2024/0870 for Erection of Dwellinghouse
-
APP/2026/1097 Granted
Stables At Glencommon Farm Bridge Of Canny Banchory AB31 4FN
Condition 2a (Layout & Siting), 2b (External Appearance), 2c (Levels), 2d (Disposal of Foul & Surface Water), 2e (Visibility Splays), 2f (Parking/Vehicle Turning Area/Lay-by), 2g (Refuse Uplift), 2h (Biodiversity & Habitat Enhancement) of Planning Permission in Principle Reference APP/2024/1247 for Erection of Dwellinghouse
-
APP/2026/1341 Awaiting decision
Kirkton Heights Phase 2 Development Boothby Road Fraserburgh Aberdeenshire
Discharge of Planning Obligation (Waste and Recylcing) of APP/2025/1683 for Erection of 175 Dwellinghouses and Associated Infrastructure
-
APP/2026/1340 Awaiting decision
Kirkton Heights Phase 2 Development Boothby Road Fraserburgh Aberdeenshire
Discharge of Planning Obligation (Sports and Recreation) of APP/2025/1683 for Erection of 175 Dwellinghouses and Associated Infrastructure