Planning application

Garioch Area At Upper Jericho Woodland Colpy Insch

Granted Aberdeenshire APP/2024/0705 Hydro Electric Notification

Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

Installation of 2 Span Spur 33Kv Overhead Line and Wooden Poles

As published by the council, reference APP/2024/0705

Application record

Reference
APP/2024/0705
Type
Hydro Electric Notification
Status
Decided
Decision
No Objection
Received
25 Apr 2024
Validated
25 Apr 2024
Decided
17 Jun 2024
Ward
West Garioch
Parish
Bennachie
Decision by
Delegated

Timeline

Dates from the published record

  1. 25 Apr 2024

    Received by Aberdeenshire

  2. 17 Jun 2024

    Decision issued: No Objection

  3. 5 Aug 2026

    Added to PlanIndex

What this grant of permission means

Aberdeenshire granted permission on 17 June 2024, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About less common application types

This application sits outside the common categories, and the council record linked on this page sets out the specific procedure that applies. More in our guide to planning application types.

In Aberdeenshire

  • APP/2026/0761 Granted

    Glendronach Distillery Forgue Huntly AB54 6DB

    Erection of Overhead Line (Retrospective)

    6 May 2026 Other
  • APP/2024/2146 Granted

    Roemex Ltd Badentoy Crescent Badentoy Industrial Estate Portlethen Aberdeenshire AB12 4YD

    Storage of Hazardous Substances

    23 Dec 2024 Other
  • APP/2025/1786 Granted

    132kV Overhead Line From Glendye Wind Farm To Fetteresso Substation

    Consultation under Section 37 of The Electricity Act 1989 for the Installation of 132KV Overhead Line and Associated Infrastructure

    31 Oct 2025 Other
  • APP/2025/1555 Granted

    Land Approximately 1.2 Km To The South Of A950 Longside Peterhead Aberdeenshire AB42 0LY

    Consultation under Section 36 of the Electricity Act 1989 for the Installation of Battery Energy Storage System (BESS) with an Installed Capacity of up to 400MW and Associated Works

    19 Sep 2025 Other
  • APP/2026/0449 Granted

    The Forkins Midmar AB51 7NR

    Retrospective S37 Consent for Overhead Line

    17 Mar 2026 Other