Garioch Area At Upper Jericho Woodland Colpy Insch
Permission granted. Work must normally begin within three years of the decision or the permission lapses.
Proposal
Installation of 2 Span Spur 33Kv Overhead Line and Wooden Poles
As published by the council, reference APP/2024/0705
Application record
- Reference
- APP/2024/0705
- Type
- Hydro Electric Notification
- Status
- Decided
- Decision
- Granted As published: No Objection
- Received
- 25 Apr 2024
- Validated
- 25 Apr 2024
- Decided
- 17 Jun 2024
- Ward
- West Garioch
- Parish
- Bennachie
- Decision by
- Delegated
Timeline
Dates from the published record
-
25 Apr 2024
Received by Aberdeenshire
-
17 Jun 2024
Decision issued: No Objection
-
5 Aug 2026
Added to PlanIndex
What this grant of permission means
Aberdeenshire granted permission on 17 June 2024, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.
About less common application types
This application sits outside the common categories, and the council record linked on this page sets out the specific procedure that applies. More in our guide to planning application types.
Other less common application types
In Aberdeenshire
-
APP/2026/1317 Granted
Mains Of Cowie Stonehaven
Consultation under Section 37 of the Electricity Act 1989 for Change in Pole Height from 8.53m to 14m to Support 11kV Overhead Line
-
APP/2026/1343 Awaiting decision
New Deer To Netherton Hub, Peterhead Tie-In
Consultation under Section 37 of The Electricity Act 1989 for the Installation of 400KV Overhead Lines, 18 Steel Lattice Towers, 2 Temporary Towers and Associated Infrastructure
-
APP/2026/0761 Granted
Glendronach Distillery Forgue Huntly AB54 6DB
Erection of Overhead Line (Retrospective)
-
APP/2024/2146 Granted
Roemex Ltd Badentoy Crescent Badentoy Industrial Estate Portlethen Aberdeenshire AB12 4YD
Storage of Hazardous Substances
-
APP/2025/1786 Granted
132kV Overhead Line From Glendye Wind Farm To Fetteresso Substation
Consultation under Section 37 of The Electricity Act 1989 for the Installation of 132KV Overhead Line and Associated Infrastructure