Hill Of Fare Wind Farm Aberdeenshire

Refused Aberdeenshire APP/2023/2196 Notification under Electricity Act 1989

Refused. Only the applicant can appeal, within the statutory time limit, and a revised scheme can be submitted instead.

Proposal

Section 36 Consultation for Erection of Wind Farm

As published by the council, reference APP/2023/2196

Application record

Reference
APP/2023/2196
Type
Notification under Electricity Act 1989
Status
Decided
Decision
Refused As published: Objection
Received
27 Nov 2023
Validated
27 Nov 2023
Decided
12 May 2025
Ward
Aboyne, Upper Deeside And Donside
Parish
Torphins
Decision by
Committee

Timeline

Dates from the published record

  1. 27 Nov 2023

    Received by Aberdeenshire

  2. 12 May 2025

    Decision issued: Objection

  3. 1 Sep 2026

    Added to PlanIndex

Documents

Plans, drawings, consultee responses and the officer's report

199 documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Watch members (£5 a month) open the document list from here.

Open the documents

What this refusal means

Aberdeenshire refused this application for the reasons on the decision notice; only the applicant can appeal, and refused schemes often return in revised form. More in our guide to what happens after a planning decision.

About less common application types

This application sits outside the common categories, and the council record linked on this page sets out the specific procedure that applies. More in our guide to planning application types.

In Aberdeenshire

  • APP/2026/1317 Granted

    Mains Of Cowie Stonehaven

    Consultation under Section 37 of the Electricity Act 1989 for Change in Pole Height from 8.53m to 14m to Support 11kV Overhead Line

    Received 30 Jul, published by the council 5 Aug 2026 Other
  • APP/2026/1343 Awaiting decision

    New Deer To Netherton Hub, Peterhead Tie-In

    Consultation under Section 37 of The Electricity Act 1989 for the Installation of 400KV Overhead Lines, 18 Steel Lattice Towers, 2 Temporary Towers and Associated Infrastructure

    Received 5 Aug, published by the council 7 Aug 2026 Other
  • APP/2026/0761 Granted

    Glendronach Distillery Forgue Huntly AB54 6DB

    Erection of Overhead Line (Retrospective)

    Received 6 May, published by the council 28 Jul 2026 Other
  • APP/2024/2146 Granted

    Roemex Ltd Badentoy Crescent Badentoy Industrial Estate Portlethen Aberdeenshire AB12 4YD

    Storage of Hazardous Substances

    Received 23 Dec, published by the council 1 Sep 2026 Other
  • APP/2025/1786 Granted

    132kV Overhead Line From Glendye Wind Farm To Fetteresso Substation

    Consultation under Section 37 of The Electricity Act 1989 for the Installation of 132KV Overhead Line and Associated Infrastructure

    Received 31 Oct, published by the council 28 Jul 2026 Other