Skip to content
PlanIndex Get alerts
Menu

Planning application

Moray Offshore Windfarm Outer Moray Firth

Granted Aberdeenshire APP/2021/1662 Notification under Electricity Act 1989

Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

Variation Request to Application for Consent Under Section 36 Electricity Act 1989 (As Amended) And Marine Licence Under Part 4 of the Marine (Scotland) Act 2010 and Marine Coastal Access Act 2009 to Construct and Operate Moray West Offshore Wind Farm

As published by the council, reference APP/2021/1662

Application record

Reference
APP/2021/1662
Type
Notification under Electricity Act 1989
Status
Decided
Decision
Granted As published: No Objection
Received
8 Jul 2021
Validated
8 Jul 2021
Decided
28 Jul 2021
Ward
Banff And District
Parish
Fordyce & Sandend
Decision by
Delegated

Timeline

Dates from the published record

  1. 8 Jul 2021

    Received by Aberdeenshire

  2. 28 Jul 2021

    Decision issued: No Objection

  3. 4 Sep 2026

    Added to PlanIndex

Documents

Plans, drawings, consultee responses and the officer's report

2 documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Watch members (£5 a month) open the document list from here.

Open the documents

What this grant of permission means

Aberdeenshire granted permission on 28 July 2021, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About less common application types

This application sits outside the common categories, and the council record linked on this page sets out the specific procedure that applies. More in our guide to planning application types.

In Aberdeenshire

  • APP/2026/1317 Granted

    Mains Of Cowie Stonehaven

    Consultation under Section 37 of the Electricity Act 1989 for Change in Pole Height from 8.53m to 14m to Support 11kV Overhead Line

    Received 30 Jul, published by the council 5 Aug 2026 Other
  • APP/2026/1343 Awaiting decision

    New Deer To Netherton Hub, Peterhead Tie-In

    Consultation under Section 37 of The Electricity Act 1989 for the Installation of 400KV Overhead Lines, 18 Steel Lattice Towers, 2 Temporary Towers and Associated Infrastructure

    Received 5 Aug, published by the council 7 Aug 2026 Other
  • APP/2026/0761 Granted

    Glendronach Distillery Forgue Huntly AB54 6DB

    Erection of Overhead Line (Retrospective)

    Received 6 May, published by the council 28 Jul 2026 Other
  • APP/2024/2146 Granted

    Roemex Ltd Badentoy Crescent Badentoy Industrial Estate Portlethen Aberdeenshire AB12 4YD

    Storage of Hazardous Substances

    Received 23 Dec, published by the council 1 Sep 2026 Other
  • APP/2025/1786 Granted

    132kV Overhead Line From Glendye Wind Farm To Fetteresso Substation

    Consultation under Section 37 of The Electricity Act 1989 for the Installation of 132KV Overhead Line and Associated Infrastructure

    Received 31 Oct, published by the council 28 Jul 2026 Other