Decision times · East of England
How long planning decisions take in West Suffolk
56 days. Ranked 132 of 343.
In the year to September 2026, the median planning application decided by West Suffolk took 56 days from submission to decision — exactly the eight week target. That is measured across 1,665 decisions where the council published both dates.
How West Suffolk compares
Year to September 2026
West Suffolk sits exactly on the national median of 56 days. Nationally 55% of applications are decided within eight weeks; here it is 53%.
The average here is 71 days, longer than the median because a handful of applications take very much longer than the rest. For planning around, 115 days is the more useful number: nine applications in ten were decided inside it.
-
Within eight weeks the statutory target 880 53%
-
Eight to thirteen weeks the major development band 525 32%
-
Over thirteen weeks commonly an agreed extension 260 16%
The last few years
Each row is a full twelve months of decisions, ending in the quarter shown
Rolling twelve month windows overlap by nine months, so this reads as a trend rather than as four separate quarters. Only windows our records reach far enough back to measure in full are listed.
| Twelve months to | Median days | UK rank |
|---|---|---|
| September 2026 | 56 | 132 of 343 |
| June 2026 | 55 | 119 of 328 |
| March 2026 | 54 | 114 of 243 |
| December 2025 | 49 | 87 of 236 |
| September 2025 | 63 | 242 of 324 |
| June 2025 | 68 | 245 of 313 |
| March 2025 | 68 | 251 of 315 |
| December 2024 | 67 | 254 of 319 |
Against the same twelve months a year earlier, when the median was 63 days, West Suffolk has moved up 110 places in the table.
By type of application
Year to September 2026 · types with at least ten decisions
The headline median mixes every kind of application together. A householder extension and an outline application for a housing site are not the same job, and the difference between them is usually larger than the difference between two councils.
-
Other 21 decided 28 days
-
Trees 444 decided 40 days
-
Amendments 100 decided 50 days
-
Conditions 274 decided 54 days
-
Prior approval 50 decided 55 days
-
Lawful development 74 decided 56 days
-
Householder 332 decided 61 days
-
Outline 10 decided 64 days
-
Heritage and listed buildings 105 decided 70 days
-
Advertising 35 decided 71 days
-
Full applications 196 decided 83 days
What West Suffolk decides
Year to September 2026
West Suffolk issued 1,665 decisions in the year to September 2026. Of the clear-cut outcomes, 96% were approvals: 1,425 granted against 65 refused. Split decisions, withdrawals and other outcomes sit outside that percentage rather than being counted as either.
Speed and approval rate are separate things. A council that refuses quickly is not doing the same job as one that negotiates an approval slowly, and neither figure alone says which served the applicant better.
Common questions
How long does a planning decision take in West Suffolk?
The median planning application decided by West Suffolk in the year to September 2026 took 56 days from submission to decision, exactly the eight week target. That is measured across 1,665 decisions where the council published both a start date and a decision date. It ranks 132 of 343 UK councils on decision speed.
Does West Suffolk meet the eight week target?
53% of the 1,665 decisions West Suffolk made in the year to September 2026 came within eight weeks of the application being received, and 84% within thirteen weeks. Nine in ten were decided within 115 days. Councils can agree an extension of time with an applicant, so a decision past eight weeks is not necessarily a missed deadline.
Is West Suffolk faster or slower than average?
West Suffolk sits exactly on the national median of 56 days.
Is West Suffolk getting faster or slower?
Against the same twelve month window a year earlier, when its median was 63 days, West Suffolk has moved up 110 places in the table. Its median has fallen by 7 days.
What proportion of applications does West Suffolk approve?
96% of the clear-cut outcomes West Suffolk issued in the year to September 2026 were approvals: 1,425 granted against 65 refused. Split decisions, withdrawals and other outcomes are excluded from that percentage.
Cite these figures
Click the text to select the whole citation.
West Suffolk planning decision times, year to September 2026: median 56 days from application to decision (exactly the eight week target), across 1,665 decisions with both dates published. 53% were decided within the eight week statutory target, 84% within thirteen weeks; nine in ten within 115 days. Ranked 132 of 343 UK councils on decision speed (national median 56 days). 96% of clear-cut outcomes were approvals. Source: PlanIndex, planindex.co.uk.