Decision times · East of England
How long planning decisions take in Maldon
74 days. Ranked 39 of 45.
In the year to December 2026, the median planning application decided by Maldon took 74 days from submission to decision — 18 days beyond the eight week target. That is measured across 549 decisions where the council published both dates.
How Maldon compares
Year to December 2026
Maldon takes longer than the country as a whole: 17 days above the national median of 57 days. Nationally 49% of applications are decided within eight weeks; here it is 17%.
The average here is 123 days, longer than the median because a handful of applications take very much longer than the rest. For planning around, 279 days is the more useful number: nine applications in ten were decided inside it.
-
Within eight weeks the statutory target 95 17%
-
Eight to thirteen weeks the major development band 230 42%
-
Over thirteen weeks commonly an agreed extension 224 41%
The last few years
Each row is a full twelve months of decisions, ending in the quarter shown
Rolling twelve month windows overlap by nine months, so this reads as a trend rather than as four separate quarters. Only windows our records reach far enough back to measure in full are listed.
| Twelve months to | Median days | UK rank |
|---|---|---|
| December 2026 | 74 | 39 of 45 |
| September 2026 | 79 | 50 of 56 |
| March 2026 | 174 | 36 of 38 |
| December 2025 | 140 | 22 of 24 |
| September 2025 | 63 | 19 of 27 |
| June 2025 | 57 | 15 of 31 |
| March 2025 | 57 | 14 of 30 |
| December 2024 | 57 | 28 of 57 |
Against the same twelve months a year earlier, when the median was 140 days, Maldon has moved down 17 places in the table.
By type of application
Year to December 2026 · types with at least ten decisions
The headline median mixes every kind of application together. A householder extension and an outline application for a housing site are not the same job, and the difference between them is usually larger than the difference between two councils.
-
Trees 52 decided 52 days
-
Amendments 31 decided 57 days
-
Lawful development 33 decided 57 days
-
Heritage and listed buildings 34 decided 79 days
-
Householder 71 decided 85 days
-
Reserved matters 57 decided 87 days
-
Full applications 125 decided 138 days
-
Advertising 12 decided 148 days
-
Outline 20 decided 264 days
What Maldon decides
Year to December 2026
Maldon issued 549 decisions in the year to December 2026. Of the clear-cut outcomes, 82% were approvals: 379 granted against 84 refused. Split decisions, withdrawals and other outcomes sit outside that percentage rather than being counted as either.
Speed and approval rate are separate things. A council that refuses quickly is not doing the same job as one that negotiates an approval slowly, and neither figure alone says which served the applicant better.
Common questions
How long does a planning decision take in Maldon?
The median planning application decided by Maldon in the year to December 2026 took 74 days from submission to decision, 18 days beyond the eight week target. That is measured across 549 decisions where the council published both a start date and a decision date. It ranks 39 of 45 UK councils on decision speed.
Does Maldon meet the eight week target?
17% of the 549 decisions Maldon made in the year to December 2026 came within eight weeks of the application being received, and 59% within thirteen weeks. Nine in ten were decided within 279 days. Councils can agree an extension of time with an applicant, so a decision past eight weeks is not necessarily a missed deadline.
Is Maldon faster or slower than average?
Maldon is slower than average: its median of 74 days is 17 days above the national median of 57 days.
Is Maldon getting faster or slower?
Against the same twelve month window a year earlier, when its median was 140 days, Maldon has moved down 17 places in the table. Its median has fallen by 66 days.
What proportion of applications does Maldon approve?
82% of the clear-cut outcomes Maldon issued in the year to December 2026 were approvals: 379 granted against 84 refused. Split decisions, withdrawals and other outcomes are excluded from that percentage.
Cite these figures
Click the text to select the whole citation.
Maldon planning decision times, year to December 2026: median 74 days from application to decision (18 days beyond the eight week target), across 549 decisions with both dates published. 17% were decided within the eight week statutory target, 59% within thirteen weeks; nine in ten within 279 days. Ranked 39 of 45 UK councils on decision speed (national median 57 days). 82% of clear-cut outcomes were approvals. Source: PlanIndex, planindex.co.uk.
Or take the data itself: this council's history (CSV) or the full league table (CSV).
Embed these figures
Paste either snippet into your page. Click a snippet to select all of it. The credit line is part of the embed.
<script src="https://planindex.co.uk/embed/decision-times.js" data-council="maldon" defer></script>
If your CMS strips scripts, use the frame directly:
<iframe src="https://planindex.co.uk/embed/decision-times/maldon" title="Planning decision times in Maldon" width="100%" height="215" loading="lazy" frameborder="0"></iframe>
<p>Data: <a href="https://planindex.co.uk/planning-decision-times/maldon">Planning decision times, from PlanIndex</a></p>