Decision times · East of England

How long planning decisions take in Norwich

55 days. Ranked 118 of 343.

In the year to September 2026, the median planning application decided by Norwich took 55 days from submission to decision — 1 day inside the eight week target. That is measured across 218 decisions where the council published both dates.

55 days
Median decision 1 day inside the eight week target
118 of 343
UK rank down 91 places in a year
57%
Within eight weeks 74% within thirteen
217 days
Nine in ten decided by The wait to budget for

How Norwich compares

Year to September 2026

Norwich decides faster than the country as a whole: 1 day below the national median of 56 days. Nationally 55% of applications are decided within eight weeks; here it is 57%.

The average here is 111 days, longer than the median because a handful of applications take very much longer than the rest. For planning around, 217 days is the more useful number: nine applications in ten were decided inside it.

  1. Within eight weeks the statutory target 125 57%
  2. Eight to thirteen weeks the major development band 37 17%
  3. Over thirteen weeks commonly an agreed extension 56 26%

The last few years

Each row is a full twelve months of decisions, ending in the quarter shown

Rolling twelve month windows overlap by nine months, so this reads as a trend rather than as four separate quarters. Only windows our records reach far enough back to measure in full are listed.

Norwich: median days from application to decision, by rolling twelve month window. Source: PlanIndex, planindex.co.uk.
Twelve months to Median days UK rank
September 2026 55 118 of 343
June 2026 52 79 of 328
September 2025 38 27 of 324
June 2025 40 7 of 313
March 2025 40 6 of 315
December 2024 40 7 of 319

Against the same twelve months a year earlier, when the median was 38 days, Norwich has moved down 91 places in the table.

By type of application

Year to September 2026 · types with at least ten decisions

The headline median mixes every kind of application together. A householder extension and an outline application for a housing site are not the same job, and the difference between them is usually larger than the difference between two councils.

  1. Trees 42 decided 41 days
  2. Advertising 10 decided 46 days
  3. Heritage and listed buildings 41 decided 52 days
  4. Amendments 13 decided 56 days
  5. Conditions 17 decided 58 days
  6. Full applications 81 decided 66 days

How these types compare nationally

What Norwich decides

Year to September 2026

Norwich issued 218 decisions in the year to September 2026. Of the clear-cut outcomes, 92% were approvals: 171 granted against 14 refused. Split decisions, withdrawals and other outcomes sit outside that percentage rather than being counted as either.

Speed and approval rate are separate things. A council that refuses quickly is not doing the same job as one that negotiates an approval slowly, and neither figure alone says which served the applicant better.

Common questions

How long does a planning decision take in Norwich?

The median planning application decided by Norwich in the year to September 2026 took 55 days from submission to decision, 1 day inside the eight week target. That is measured across 218 decisions where the council published both a start date and a decision date. It ranks 118 of 343 UK councils on decision speed.

Does Norwich meet the eight week target?

57% of the 218 decisions Norwich made in the year to September 2026 came within eight weeks of the application being received, and 74% within thirteen weeks. Nine in ten were decided within 217 days. Councils can agree an extension of time with an applicant, so a decision past eight weeks is not necessarily a missed deadline.

Is Norwich faster or slower than average?

Norwich is faster than average: its median of 55 days is 1 day below the national median of 56 days.

Is Norwich getting faster or slower?

Against the same twelve month window a year earlier, when its median was 38 days, Norwich has moved down 91 places in the table. Its median has risen by 17 days.

What proportion of applications does Norwich approve?

92% of the clear-cut outcomes Norwich issued in the year to September 2026 were approvals: 171 granted against 14 refused. Split decisions, withdrawals and other outcomes are excluded from that percentage.

Cite these figures

Click the text to select the whole citation.

Norwich planning decision times, year to September 2026: median 55 days from application to decision (1 day inside the eight week target), across 218 decisions with both dates published. 57% were decided within the eight week statutory target, 74% within thirteen weeks; nine in ten within 217 days. Ranked 118 of 343 UK councils on decision speed (national median 56 days). 92% of clear-cut outcomes were approvals. Source: PlanIndex, planindex.co.uk.