Planning application
Legoland Windsor Resort Winkfield Road Windsor SL4 4AY
Permission granted. Work must normally begin within three years of the decision or the permission lapses.
Proposal
Non material amendments to planning permission 17/01878/OUT as per covering letter.
As published by the council, reference 23/01760/NMA
Application record
- Reference
- 23/01760/NMA
- Type
- Non-material Amendment
- Status
- Decided
- Decision
- Granted As published: Application Permitted
- Received
- 20 Jul 2023
- Validated
- 24 Jul 2023
- Decided
- 23 Aug 2023
- Ward
- Clewer And Dedworth East
- Parish
- Windsor Unparished
- Decision by
- Delegated
- Postcode
- SL4 4AY
Site history
Applications at this address on the Windsor and Maidenhead register
This site has had 37 applications since 2020: 35 approved, 0 refused.
-
26/01718/TPO Granted
Legoland Windsor Resort Winkfield Road Windsor SL4 4AY
(T1) T001 - Willow - Re pollard to previous points by removal of up to 5m in branch length. (040/2016/TPO)
-
26/01717/TPO Withdrawn
Legoland Windsor Resort Winkfield Road Windsor SL4 4AY
(T1) T001 - Poplar - Fell. (T2) T002 - Oak - Remove 2 x dead limbs back to trunk, growing towards neighbouring property (003/1961/TPO).
-
26/01050/CPD Granted
Legoland Windsor Resort Winkfield Road Windsor SL4 4AY
Certificate of lawfulness to determine whether the proposed installation of plant and machinery in the form of a coaster ride with ancillary elements including operators cabin, loading platform and perimeter fencing is lawful.
-
26/00887/TPO Granted
Legoland Windsor Resort Winkfield Road Windsor SL4 4AY
Refer to tree report. (003/1963/TPO)
-
26/00362/DEM Granted
Legoland Windsor Resort Winkfield Road Windsor SL4 4AY
Prior notification for the demolition of the Viking River Splash Ride and associated buildings and structures.
-
25/03138/TPO Granted
Legoland Windsor Resort Winkfield Road Windsor SL4 4AY
(G1) 2 no. Cherry trees - Fell as close to ground level as possible. (T2) Hornbeam - Prune secondary and smaller branches to give up to 1.5m clearance to the barn, including over its roof. (T3) Sweet chestnut - Crown lift to provide 2.5m clearance over ride and 1m over roof. (003/1963/TPO)
-
24/02200/CONDIT Granted
Legoland Windsor Resort Winkfield Road Windsor SL4 4AY
Details required by Condition 24 (partial discharge) (BREEAM in relation to Holiday Village 1) of planning permission 17/01878/OUT for a Hybrid planning application seeking permission for the following Full (detailed) projects: Project 1 - the erection of 65 permanent semi-detached lodges (130 units) and 20 'barrels' with associated amenity facilities block to provide visitor accommodation, a central facilities 'hub' building, SUDS ponds, landscaping works (including equipped play areas) and associated infrastructure works ('Phase 1' of the holiday village); Project 2 - Reconfiguration of car parking and internal accesses and associated engineering/infrastructure works; Project 3 - Change of use of existing farm buildings from agricultural/'sui generis' use to Use Class D2, ancillary 'back of house'; accommodation and land for re-use by the theme park and the creation of one new access point from the existing car park and Project 4 - Extension and alterations to 'The Beginning' comprising new admissions building, extension to existing toilet facilities and new entrance portal. Permission for the following Outline projects: Project 5 - Construction of the '2019 attraction' comprising three 'attraction zones' for up to three new rides (one to be an indoor attraction and the other two to be uncovered or covered) with associated queue line areas, landscaping works and associated infrastructure; Project 6 - Construction of a new indoor ride on the 'Haunted House' site with associated queue line area, landscaping works and associated infrastructure; Project 7 - Extension to the existing 'Big Shop' LEGO store in 'The Beginning' area; Project 8 - Erection of up to 300 units of visitor accommodation ('Phases 2 and 3' of the holiday village) with two associated central facilities 'hub' buildings, SUDS ponds, landscaping, infrastructure works and car parking area.
-
24/01632/TPO Granted
Legoland Windsor Resort Winkfield Road Windsor SL4 4AY
Please see tree report and spreadsheet. (003/1963/TPO)
-
24/00891/FULL Granted
Legoland Windsor Resort Winkfield Road Windsor SL4 4AY
Upgrading of the arrival area, "The Beginning" at Windsor Resort, including external alterations to buildings, replacement and additional structures, landscaping and provision of associated infrastructure.
-
23/02320/CONDIT Granted
Legoland Windsor Resort Winkfield Road Windsor SL4 4AY
Details required by Conditions 4 (archaeology) and 6 (external lighting) of planning permission 22/01593/FULL for the construction of a new building with associated works and infrastructure to create an indoor attraction - development to dovetail with planning permission 17/01878/OUT.
Timeline
Dates from the published record
-
20 Jul 2023
Received by Windsor and Maidenhead
-
24 Jul 2023
Validated
Checked as complete and ready for consideration.
-
23 Aug 2023
Decision issued: Application Permitted
-
12 Sep 2026
Added to PlanIndex
Documents
Plans, drawings, consultee responses and the officer's report
22 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Watch members (£5 a month) open the document list from here.
Open the documentsWhat this grant of permission means
Windsor and Maidenhead granted permission on 23 August 2023, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.
About amendment applications
An amendment application makes limited changes to a permission that already exists; anything beyond modest adjustment needs a fresh application. More in our guide to planning application types.
Nearby applications
Within 0.3 miles
-
Legoland Windsor Resort Winkfield Road Windsor SL4 4AY
Details required by Condition 3 (Parcel Plan) and Condition 17 (partial dischage) (Archaeology - projects 1 and 2) of planning permission 17/01878/OUT for a Hybrid planning application seeking permission for the following Full (detailed) projects: Project 1 - the erection of 65 permanent semi-detached lodges (130 units) and 20 'barrels' with associated amenity facilities block to provide visitor accommodation, a central facilities 'hub' building, SUDS ponds, landscaping works (including equipped play areas) and associated infrastructure works ('Phase 1' of the holiday village); Project 2 - Reconfiguration of car parking and internal accesses and associated engineering/infrastructure works; Project 3 - Change of use of existing farm buildings from agricultural/'sui generis' use to Use Class D2, ancillary 'back of house'; accommodation and land for re-use by the theme park and the creation of one new access point from the existing car park and Project 4 - Extension and alterations to 'The Beginning' comprising new admissions building, extension to existing toilet facilities and new entrance portal. Permission for the following Outline projects: Project 5 - Construction of the '2019 attraction' comprising three 'attraction zones' for up to three new rides (one to be an indoor attraction and the other two to be uncovered or covered) with associated queue line areas, landscaping works and associated infrastructure; Project 6 - Construction of a new indoor ride on the 'Haunted House' site with associated queue line area, landscaping works and associated infrastructure; Project 7 - Extension to the existing 'Big Shop' LEGO store in 'The Beginning' area; Project 8 - Erection of up to 300 units of visitor accommodation ('Phases 2 and 3' of the holiday village) with two associated central facilities 'hub' buildings, SUDS ponds, landscaping, infrastructure works and car parking area.
Granted Conditions Extension 14 docsMajor scheme -
Legoland Windsor Resort Winkfield Road Windsor SL4 4AY
Details required by Condition 3 (Parcel Plan); 8 (Partial Discharge) (CEMP); 10 (Partial Discharge) (Protection of the Hedgerows, Trees and Woodland/Arboricultural Method Statement); 11 (Partial Discharge) (Buffer Zones and Veteran Tree Reserves); 12 (Partial Discharge) (Landscaping); 15 (Partial Discharge) (Car Parking) and 17 (Partial Discharge) (Archaeological Works) and 19 (Car Park Surfacing (E)) of planning permission 17/01878/OUT (as described in full on the application form).
Granted Conditions Trees 48 docs -
Legoland Windsor Resort Winkfield Road Windsor SL4 4AY
Details required by Condition 24 (partial discharge) (BREEAM in relation to Holiday Village 1) of planning permission 17/01878/OUT for a Hybrid planning application seeking permission for the following Full (detailed) projects: Project 1 - the erection of 65 permanent semi-detached lodges (130 units) and 20 'barrels' with associated amenity facilities block to provide visitor accommodation, a central facilities 'hub' building, SUDS ponds, landscaping works (including equipped play areas) and associated infrastructure works ('Phase 1' of the holiday village); Project 2 - Reconfiguration of car parking and internal accesses and associated engineering/infrastructure works; Project 3 - Change of use of existing farm buildings from agricultural/'sui generis' use to Use Class D2, ancillary 'back of house'; accommodation and land for re-use by the theme park and the creation of one new access point from the existing car park and Project 4 - Extension and alterations to 'The Beginning' comprising new admissions building, extension to existing toilet facilities and new entrance portal. Permission for the following Outline projects: Project 5 - Construction of the '2019 attraction' comprising three 'attraction zones' for up to three new rides (one to be an indoor attraction and the other two to be uncovered or covered) with associated queue line areas, landscaping works and associated infrastructure; Project 6 - Construction of a new indoor ride on the 'Haunted House' site with associated queue line area, landscaping works and associated infrastructure; Project 7 - Extension to the existing 'Big Shop' LEGO store in 'The Beginning' area; Project 8 - Erection of up to 300 units of visitor accommodation ('Phases 2 and 3' of the holiday village) with two associated central facilities 'hub' buildings, SUDS ponds, landscaping, infrastructure works and car parking area.
Granted Conditions Extension 5 docsMajor scheme -
Legoland Windsor Resort Winkfield Road Windsor SL4 4AY
Details required by Condition 7, part discharge (Materials) and Condition 8, part discharge (Construction Environmental Management Plan) of planning permission 17/01878/OUT for a Hybrid planning application seeking permission for the following Full (detailed) projects: Project 1 - the erection of 65 permanent semi-detached lodges (130 units) and 20 'barrels' with associated amenity facilities block to provide visitor accommodation, a central facilities 'hub' building, SUDS ponds, landscaping works (including equipped play areas) and associated infrastructure works ('Phase 1' of the holiday village); Project 2 - Reconfiguration of car parking and internal accesses and associated engineering/infrastructure works; Project 3 - Change of use of existing farm buildings from agricultural/'sui generis' use to Use Class D2, ancillary 'back of house'; accommodation and land for re-use by the theme park and the creation of one new access point from the existing car park and Project 4 - Extension and alterations to 'The Beginning' comprising new admissions building, extension to existing toilet facilities and new entrance portal. Permission for the following Outline projects: Project 5 - Construction of the '2019 attraction' comprising three 'attraction zones' for up to three new rides (one to be an indoor attraction and the other two to be uncovered or covered) with associated queue line areas, landscaping works and associated infrastructure; Project 6 - Construction of a new indoor ride on the 'Haunted House' site with associated queue line area, landscaping works and associated infrastructure; Project 7 - Extension to the existing 'Big Shop' LEGO store in 'The Beginning' area; Project 8 - Erection of up to 300 units of visitor accommodation ('Phases 2 and 3' of the holiday village) with two associated central facilities 'hub' buildings, SUDS ponds, landscaping, infrastructure works and car parking area.
Granted Conditions Extension 8 docsMajor scheme -
Legoland Windsor Resort Winkfield Road Windsor SL4 4AY
Details required by Condition 6 (plans/sections) (partial discharge), Condition 7 (Materials) (partial discharge), Condition 16 (Security/Access) (partial discharge) Condition 21 (surface water drainage scheme) of Planning Permission 17/01878 for Hybrid planning application seeking permission for the following Full (detailed) projects: Project 1 - the erection of 65 permanent semi-detached lodges (130 units) and 20 'barrels' with associated amenity facilities block to provide visitor accommodation, a central facilities 'hub' building, SUDS ponds, landscaping works (including equipped play areas) and associated infrastructure works ('Phase 1' of the holiday village); Project 2 - Reconfiguration of car parking and internal accesses and associated engineering/infrastructure works; Project 3 - Change of use of existing farm buildings from agricultural/'sui generis' use to Use Class D2, ancillary 'back of house'; accommodation and land for re-use by the theme park and the creation of one new access point from the existing car park and Project 4 - Extension and alterations to 'The Beginning' comprising new admissions building, extension to existing toilet facilities and new entrance portal. Permission for the following Outline projects: Project 5 - Construction of the '2019 attraction' comprising three 'attraction zones' for up to three new rides (one to be an indoor attraction and the other two to be uncovered or covered) with associated queue line areas, landscaping works and associated infrastructure; Project 6 - Construction of a new indoor ride on the 'Haunted House' site with associated queue line area, landscaping works and associated infrastructure; Project 7 - Extension to the existing 'Big Shop' LEGO store in 'The Beginning' area; Project 8 - Erection of up to 300 units of visitor accommodation ('Phases 2 and 3' of the holiday village) with two associated central facilities 'hub' buildings, SUDS ponds, landscaping, infrastructure works and car parking area.
Granted Conditions Extension 24 docsMajor scheme -
Legoland Windsor Resort Winkfield Road Windsor SL4 4AY
(G1) 2 no. Cherry trees - Fell as close to ground level as possible. (T2) Hornbeam - Prune secondary and smaller branches to give up to 1.5m clearance to the barn, including over its roof. (T3) Sweet chestnut - Crown lift to provide 2.5m clearance over ride and 1m over roof. (003/1963/TPO)
Granted Trees 10 docs
Other amendment applications
In Windsor and Maidenhead
-
26/00814/VAR Granted
Land West of Switchback Road North And North of Nightingale Lane Maidenhead
Variation (under Section 73a) of planning permission 21/02963/FULL to vary the wording of Condition 8 (Drainage), 9 (Vehicles), 10 (Landscaping) and 11 (Painting) without complying with one month time limit.
-
26/01411/VAR Granted
Whiteladies Park Prince Albert Drive Ascot SL5 8AQ
Variation (under Section 73) of Condition 11 to substitute those plans approved under 25/03016/FULL for the Redevelopment of existing dwelling, including demolition and reconstruction of western extension, the construction of an eastern extension including an indoor swimming pool, and creation of a basement area with amended plans.
-
26/01792/VAR Granted
Silver Birches St Marys Road Ascot SL5 9JE
Variation (under Section 73) of Condition 9 (Approved Plans) to substitute those plans approved under 26/00205/FULL for a raised ridge, 2 no. front dormers and 1 no. rear dormer, 1no. side bay window, new chimney, single storey side/rear extension, alterations to fenestration and hardstanding, following demolition of existing elements with amended plans.
-
26/02420/NMA Awaiting decision
Development At King Street And Queen Street And Broadway Maidenhead
Non material amendments to planning permission 25/00066/VAR as per covering letter.
-
26/02152/NMA Granted
Land Bounded By Ascot Fire Station Station Hill And West of Hermitage Parade And South of High Street Ascot SL5 7HF
Non material amendments to planning permission 25/01050/FULL to amend the wording of Condition 8 (Bat Mitigation Scheme).