Berewood Phase 1 Hambledon Road Denmead Hampshire

Awaiting decision Winchester 26/02069/DIC Details in Compliance

Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.

Proposal

Discharge of condition 4 (details of the connection to the multiuse greenway) and 11 (maintenance of all roads) of application 25/01354/REM

As published by the council, reference 26/02069/DIC

Application record

Reference
26/02069/DIC
Type
Details in Compliance
Status
Current
Received
6 Oct 2026
Validated
6 Oct 2026
Ward
DENMEAD WARD
Parish
Newlands

Site history

Applications at this address on the Winchester register

This site has had 100 applications since 2020: 60 approved, 0 refused.

  • 26/02242/S106 Awaiting decision

    Berewood Phase 1 Hambledon Road Denmead Hampshire

    S106 DISCHARGE OF OBLIGATIONS Section 27.1 (Written notice of the proposed commencement date to be served on the three authorities prior to Commencement.)

    Submitted 27 Oct 2026
  • 26/02243/S106 Awaiting decision

    Berewood Phase 1 Hambledon Road Denmead Hampshire

    S106 DISCHARGE OF OBLIGATIONS Section 25 (Southern Primary School Site - Release Notice) Clause 25.40, 25.41, 25.42, 25.43, 25.44.1, 25.44.2, 25.44.3, 25.44.4, 25.45.1, 25.45.2, 25.45.3, 25.45.4, 2...

    Submitted 27 Oct 2026
  • 26/02203/DIC Granted

    Berewood Phase 1 Hambledon Road Denmead Hampshire

    Discharge of conditions 11 (CEMP) of planning application 10/02862/OUT

    Decided 27 Oct 2026
  • 26/02070/DIC Awaiting decision

    Berewood Phase 1 Hambledon Road Denmead Hampshire

    Discharge of condition 7 (Contamination report) of application 10/02862/OUT

    Submitted 6 Oct 2026 Conditions
  • 26/02005/DIC Awaiting decision

    Berewood Phase 1 Hambledon Road Denmead Hampshire

    Condition 17 of 10/02862/OUT Noise and Vibration Impact Assessment Issue 2.0 Dated 22 July 2026

    Submitted 29 Sep 2026 Conditions
  • 26/01892/S106 Awaiting decision

    Berewood Phase 1 Hambledon Road Denmead Hampshire

    S106 DISCHARGE OF OBLIGATIONS Section 24 (Construction Route Traffic Management Plan (CTMP)) Clause 24.1, 24.2, 24.3, 24.4, 24.5,

    Submitted 8 Sep 2026 Conditions
  • 26/01843/NMA Decided

    Berewood Phase 1 Hambledon Road Denmead Hampshire

    NMA to application 20/01035/REM to the approved landscaping plans to allow for the addition of two footpath links.

    Decided 24 Sep 2026 Amendments
  • 26/01826/DIC Awaiting decision

    Berewood Phase 1 Hambledon Road Denmead Hampshire

    Confirmation of outline conditions not requiring discharge for application 10/02862/OUT

    Submitted 3 Sep 2026 Conditions
  • 26/01702/NMA Awaiting decision

    Berewood Phase 1 Hambledon Road Denmead Hampshire

    (Amended Description) NMA to application to amend Condition 1 of 10/02862/OUT to read as follows: The first application for approval of reserved matters shall be made to the local planning authority before the expiration of five years from the date of this permission. Subsequent reserved matters applications shall be submitted no later than fifteen years from the date of this permission, with the exception of the reserved matters applications relating to Phases E1, E2,02, 04, 05, 06, 07, 09, and 13 as shown on the strategic phasing plan page 95 of the Newlands Masterplan Design Document (November 2010) which shall be submitted no later than 30th March 2030 Reason: To comply with the provisions of section 92(2) of the Town and Country Planning Act 1990

    Submitted 18 Aug 2026 Amendments
  • 26/01641/DIC Granted

    Berewood Phase 1 Hambledon Road Denmead Hampshire

    Discharge of Condition 8 (Verification Report) of Outline Planning Permission Ref: 10/01862/OUT - Plot 500, Berewood E2 Employment Land,

    Decided 15 Sep 2026 Conditions

Timeline

Dates from the published record

  1. 6 Oct 2026

    Received by Winchester

  2. 14 Nov 2026

    Added to PlanIndex

  3. Decision

    Awaiting decision

    Decision expected by 1 December 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.

    Winchester took a median of 63 days over the applications it decided in the last year.

Documents

7 documents on file for this application

A planning file usually holds the application form, the consultee responses, the officer's report and the decision notice.

Watch members (£5 a month) open the document list from here.

Open the documents

Working a patch? Trade sends you every new job in your area each morning. 14 days free.

What happens while it is decided

This application is with Winchester for determination, against a statutory target of eight weeks. Over the last year Winchester decided condition discharge and variation applications in a median of 56 days. More in our guide to how long planning decisions take.

About condition discharge and variation applications

This application deals with conditions on an existing permission, supplying the details a condition requires or asking to vary or remove one, without reopening the permission itself. More in our guide to planning application types.

Nearby applications

Within 0.3 miles

  • Berewood Phase 1 Hambledon Road Denmead Hampshire

    26/01516/DIC Submitted 23 Jul 2026 50 yards away

    discharge conditions 5 (External surface material details) and partial agreement of condition 6 (Hard landscaping) for application 25/01354/REM

    Granted Conditions Drawings (7) 15 docs
  • Berewood Phase 1 Hambledon Road Denmead Hampshire

    25/01354/REM Submitted 3 Jul 2025 50 yards away

    Reserved Matters Approval pursuant to outline consent 10/02862/OUT (layout, siting and scale, design and external appearance, means of access, and landscaping) comprising 62 residential dwellings and a pumping station with associated amenity space, garages, parking, internal roads, pathways, and landscaping for phase 11b. Part discharge of condition 3, condition 4, condition 6 (i), condition 6 (ii) a), b), c), d), e), f), h), i), j), k), l), m), n) and condition 18 The outline consent was subject to EIA. (amended plans)

    Granted Reserved matters 188 docs
  • Berewood Phase 1 Hambledon Road Denmead Hampshire

    26/00928/NMA Submitted 30 Apr 2026 50 yards away

    Amendment of 25/01354/REM - layout changes to reflect building regs requirements, reduce size of house types Bartley and Beaulieu, update in house type names on plans, change of house type for plot 60 from 4 bed no bay window to 4 bed with bay window.

    Decided Amendments Windows or glazing Drawings (13) 20 docs
  • Berewood Phase 1 Hambledon Road Denmead Hampshire

    26/01575/NMA Submitted 3 Aug 2026 100 yards away

    Amendments to the site layout are sought to address inconsistencies noted between the approved housetype drawings and the approved site layout.

    Decided Amendments Drawings (10) 17 docs
  • Berewood Phase 1 Hambledon Road Denmead Hampshire

    24/02579/DIC Submitted 27 Nov 2024 100 yards away

    Condition 11 of outline consent 10/02862/OUT in relation to the Phase 9c/11a Substation which was approved under the Reserved Matters Application 23/00433/REM.

    Granted Conditions 7 docs
  • Berewood Phase 1 Hambledon Road Denmead Hampshire

    24/00169/REM Submitted 23 Jan 2024 100 yards away

    (Amended Description) APPLICATION FOR APPROVAL OF RESERVED MATTERS: SUBSTATION (Phase 12) RESERVED MATTERS 6 (i) (a), (b) and (c) Approval of conditions 3, 4, 6 (i) (a) (b) (c), 6 (ii) (a) (f) (h) (i) (j) and condition 11 of planning consent APP/10/00828 &10/02862/OUT An Environmental Impact Statement was submitted and approved with the outline planning application.

    Granted Reserved matters Drawings (5) 27 docs

In Winchester

  • 26/02081/DIC Awaiting decision

    The Gorse 111 Main Road Colden Common Winchester Hampshire SO21 1TB

    Discharge of conditions 3 (materials), 4 part a (water efficiency), 5 (BNG), 6 (HMMP), 7 (finished floor level), 9 (Landscape), 14, 16 and 17 (Trees), 19 (southern water drainage), 20 (climate change mitiigation) of planning application 26/00049/FUL

    Received 7 Oct, published by the council 15 Oct 2026 Conditions
  • 26/02070/DIC Awaiting decision

    Berewood Phase 1 Hambledon Road Denmead Hampshire

    Discharge of condition 7 (Contamination report) of application 10/02862/OUT

    Received 6 Oct, published by the council 20 Nov 2026 Conditions
  • 26/02059/DIC Awaiting decision

    North Whiteley Urban Extension Botley Road Curbridge Hampshire

    Discharge of condition 6 (SAP Calculations) for application 22/01634/REM

    Received 6 Oct, published by the council 20 Nov 2026 Conditions
  • 26/02051/DIC Awaiting decision

    4 The Close Winchester Hampshire SO23 9LS

    Discharge of Condition 5 (Method Statement) of planning permission 25/02553/LIS

    Received 5 Oct, published by the council 19 Oct 2026 Conditions
  • 26/02056/DIC Awaiting decision

    Queens Head Portsmouth Road Fishers Pond Hampshire

    Discharge of Condition(s) 10 (Verication of Remidial Strategy (Geogolgy)) for application 26/00106/VAR.

    Received 5 Oct, published by the council 12 Oct 2026 Conditions