Planning application
Development Site At 180 Piccadilly And 48 To 50 Jermyn Street London
Works: Demolition Windows or glazing
Decided. The decision notice on the council portal carries the outcome in full, including any conditions.
Proposal
Amendments to planning permission dated 7 March 2024 (RN:23/05424/FULL) for the Variation of conditions 1, 11, 23, 27, 36 and 37 of planning permission dated 17th May 2022 (RN:21/01138/FULL) for the Demolition of existing buildings and redevelopment of the site to create a Class E use building, including basement plant and cycle parking facilities, installation of roof top plant and all other works incidental to the proposals. NAMELY, removal of solid panels above secondary doors to south elevation, and replacement with glazing.
As published by the council, reference 26/05965/NMA
Application record
- Reference
- 26/05965/NMA
- Category
- Amendments
- Status
- Decided
- Received
- 1 Sep 2026
- Validated
- 1 Sep 2026
Site history
Applications at this address on the Westminster register
This site has had 6 applications since 2025: 4 approved, 0 refused.
-
26/04480/NMA Granted
Development Site At 180 Piccadilly And 48 To 50 Jermyn Street London
Amendments to planning permission dated 07 March 2024 (RN: 23/05424/FULL) which itself varied conditions 1, 11, 23, 27, 36 and 37 of planning permission dated 17th May 2022 (RN 21/01138/FULL) for the Demolition of existing buildings and redevelopment of the site to create a Class E use building, including basement plant and cycle parking facilities, installation of roof top plant and all other works incidental to the proposals. Namely, to allow addition of two Nicholson box enclosures, flue, and weather station.
-
26/01623/ADFULL Awaiting decision
Development Site At 180 Piccadilly And 48 To 50 Jermyn Street London
Detailed servicing management plan pursuant to condition 24 of planning permission dated 7th March 2024 (RN:23/05424).
-
26/00244/ADFULL Granted
Development Site At 180 Piccadilly And 48 To 50 Jermyn Street London
Details of PV Panels including section showing relationship to finished height of plant enclosure, pursuant to condition 9 (part 9) of planning permission dated 7th March 2024 (23/05424/FULL)
-
25/08829/NMA Granted
Development Site At 180 Piccadilly And 48 To 50 Jermyn Street London
Amendments to planning permission dated 7th March 2024 (RN:23/05424/FULL) for: Demolition of existing buildings and redevelopment of the site to create a Class E use building, including basement plant and cycle parking facilities, installation of roof top plant and all other works incidental to the proposals NAMELY; amendments to waste management arrangements and wording of Condition 23, internal layout, rooftop landscaping on Piccadilly elevation and relocation of fuel fill point on Duke Street elevation.
-
25/05525/ADFULL Granted
Development Site At 180 Piccadilly And 48 To 50 Jermyn Street London
Detailed drawings and a bio-diversity management plan pursuant to Condition 37 of planning permission dated 7 March 2024 (RN 23/05424/FULL)
Timeline
Dates from the published record
-
1 Sep 2026
Received by Westminster
-
8 Sep 2026
Added to PlanIndex
-
1 Oct 2026
Status changed to Decided
Previously Pending.
After the decision
Westminster has decided this application; the outcome above is the register's own wording and the decision notice on the council portal carries the detail. More in our guide to what happens after a planning decision.
About amendment applications
An amendment application makes limited changes to a permission that already exists; anything beyond modest adjustment needs a fresh application. More in our guide to planning application types.
Other amendment applications
In Westminster
-
26/07181/NMA Awaiting decision
Newlands House 37 - 40 Berners Street London W1T 3NA
Amendments to planning permission dated 9th October 2025 (RN:25/04048/FULL) forInfilling of the ground floor undercroft along Mortimer Street (Class E), replacement of ground floor frontage to the whole building and refurbishment of the upper floor facades. Namely, alterations to the approved green roof area at the site.
-
26/07132/NMA Awaiting decision
157 - 159 Victoria Street London SW1E 5NA
Amendments to planning permission dated 27 August 2026 (RN: 26/04666/FULL) for the: Installation of combined defibrillator and bleed kit cabinets to external wall of Nationwide Building Society branch. NAMELY, to allow alteration to design of combined defibrillator and bleed kit cabinet.
-
26/07086/NMA Awaiting decision
Windsor House 50 Victoria Street London SW1H 0TL
Amendments to planning permission dated 18th September 2026 (RN 26/01445/FULL) for the Refurbishment of Windsor House and Christchurch House (excluding residential part), including re-cladding and amendment of facades, replacement of windows, new end-of-trip facilities, installation of roof-level plant and screening, and associated works, to provide office, retail, restaurant and indoor recreation accommodation (Class E) with amenity spaces, including a new roof level pavilion to Christchurch House and link bridge between Windsor House and Christchurch House. NAMELY, amendments to the wording of Conditions 1, 11, 12, 13,14, 15 and 26.
-
26/07071/NMA Awaiting decision
London School Of Economics & Political Science Houghton Street London WC2A 2AE
Amendments to planning permission dated 21st Februrary 2018 (RN:17/05855/FULL) for Variation of Condition 1 of planning permission dated 19 October 2016 (RN:16/05155/FULL) for demolition of existing buildings known as Clare Market, The Anchorage, the East Building, St Clements (partial) and Tower One (partial) and redevelopment to provide replacement interconnected academic facilities for Class D1 and ancillary uses, comprising a two storey basement, a part six storey / part 13 storey building and a seven storey core extension to the St Clements building and associated cycle parking and other works; all arranged around a new public square namely, removal of two cycle stands.
-
26/06211/NMA Decided
15 Portland Place London W1B 1PT
Amendments to planning permission dated 21 July 2022 (RN:22/03521/FULL) which varied Condition 5 of planning permission dated 11 April 2018 (17/10815/FULL) for: Use of the building for a temporary period of 20 years as a medical use (Use Class D1) personal to OM Tower LLP namely to amend the wording of Condition 3 to omit the words " No one else may benefit from this permission" to allow the use by third party practitioners.