Skip to content
PlanIndex Get alerts
Menu

Planning application

25/07684/ADFULL

1 Clifton Hill London NW8 0QE

Awaiting decision Westminster Approval of Details (Full PP)

Proposal

Details of Arboricultural Method Statement pursuant to condition 5 of planning permssion dated 19th August 2025 (RN:25/04603/FULL).

As published by the council, reference 25/07684/ADFULL

Timeline

Dates from the published record

  1. 23 Oct 2025

    Received by Westminster

  2. 21 Jul 2026

    Added to PlanIndex

  3. Decision

    Awaiting decision

    The statutory target is eight weeks for most applications and thirteen for major development. Extensions of time are common.

What happens while it is decided

The process from here

This application is with Westminster for determination. The council publicises it, consults neighbours and technical bodies where required, and weighs the responses against local and national planning policy.

The statutory target is eight weeks for most applications and thirteen for major development, though extensions of time are common. Comments carry most weight while the case is undecided, so check the council portal for the deadline if you want to respond.

About full applications applications

How this application type works

A full application seeks permission for a complete, detailed proposal in one go: siting, design, access and landscaping are all fixed at this stage. It is the standard route for new buildings, conversions and changes of use. The statutory target is eight weeks for smaller schemes and thirteen weeks for major development, though complex cases often take longer by agreement.

More on full applications applications in our guide

Nearby applications

Within 500 metres

  • 26/02244/FULL Awaiting decision

    1 Clifton Hill London NW8 0QE

    Variation of condition 1 of planning permission dated 27 October 2025 (RN: 25/06173/FULL) for the erection of side extension at ground floor and part-first floor; use of the existing rear extension roof as a terrace; alterations to rear elevation fenestration; installation of conservation style rooflights; erection of two new dormer windows; and installation of permeable paving to front driveway; NAMELY, to vary the approved drawing numbers to allow for new sash windows, addition of fanlights to garage doors, repositioning of windows to ground floor extension, installation of new window and door surround and installation of new coping to rear elevation.

    2 Apr 2026 0m away Full applications
  • 26/02449/ADFULL Awaiting decision

    1 Clifton Hill London NW8 0QE

    Details of brick samples pursuant to condition 5 of planning permission dated 10 September 2025 (RN: 25/06173/FULL)

    14 Apr 2026 0m away Full applications
  • 26/02152/FULL Awaiting decision

    1 Clifton Hill London NW8 0QE

    Variation of condition 1 of planning permission dated 27th October 2025 (RN:25/06173/FULL) for the Erection of side extension at ground floor and part-first floor; use of the existing rear extension roof as a terrace; alterations to rear elevation fenestration; installation of conservation style rooflights; erection of two new dormer windows; and installation of permeable paving to front driveway. NAMELY, allow modification to existing vehicle gate and front brick walls to incorporate a new pedestrian gate, with the aim of improving access and safety for pedestrians entering the property.

    31 Mar 2026 0m away Full applications
  • 25/06895/ADFULL Awaiting decision

    1 Clifton Hill London NW8 0QE

    Detailed Arboricultural Method Statement pursuant to condition 5 of planning permission dated 19th August 2025 (RN:25/04603).

    25 Sep 2025 0m away Full applications
  • 25/07997/ADFULL Awaiting decision

    1 Clifton Hill London NW8 0QE

    Detailed Arboricultural Method Statement and Tree Protection Plan explaining the measures you will take to protect the trees on and close to the site pursuant to condition 11 of planning permission dated 27th October 2025 (RN:25/06173).

    4 Nov 2025 0m away Full applications
  • 26/03997/FULL Awaiting decision

    1 Clifton Hill London NW8 0QE

    Variation of condition 1 of planning permission dated 27 October 2025 (RN: 25/06173/FULL) for the: Erection of side extension at ground floor and part-first floor; use of the existing rear extension roof as a terrace; alterations to rear elevation fenestration; installation of conservation style rooflights; erection of two new dormer windows; and installation of permeable paving to front driveway. Namely, to allow the replacement of other existing windows with timber double glazed sash windows.

    17 Jun 2026 0m away Full applications

In Westminster

  • 26/04824/ADFULL Granted

    New Zealand House 80 Haymarket London SW1Y 4TE

    Detailed design and specification of new blinds to NZH based on mock-up trials on-site. pursuant to condition 32 (i) of planning permission dated 8th April 2024 (23/00571/FULL).

    20 Jul 2026 Full applications
  • 26/04829/ADFULL Granted

    New Zealand House 80 Haymarket London SW1Y 4TE

    Details of external and internal signage strategy pursuant to Condition 33(E) of planning permission dated 8th April 2024 (RN: 23/00571/FULL)

    20 Jul 2026 Full applications
  • 26/04841/ADFULL Granted

    29 Henstridge Place London NW8 6QD

    Details of the facing materials you will use, including glazing, and elevations and roof plans annotated to show where the materials are to be located pursuant to condition 5 of planning permission dated 18th November 2025 (RN:25/06159).

    20 Jul 2026 Full applications
  • 26/04989/FULL Awaiting decision

    1 Kildare Terrace London W2 5JT

    Erection of a mansard roof extending over the main house and side wing, replacement lower ground rear extension with roof terrace above, lowering of lower ground floor slab, installation of an air source heat pump in rear garden, new front boundary treatment, and new second floor window on the north elevation.

    24 Jul 2026 Full applications
  • 26/04986/FULL Awaiting decision

    Inver Court Inverness Terrace London W2 6JB

    Replacement of combustible materials in the render facades; timber decking and plastic soffits/ fascias to terraces with non-combustible materials on the 5th and 6th floors.

    24 Jul 2026 Full applications