Planning application
25/07598/ADFULL
47 Berkeley Square London W1J 5AU
Proposal
Details of Pre-demolition audit pursuant to partial discharge of condition 9(a) of planning permission dated 13th August 2024 (RN: 24/02158/FULL).
As published by the council, reference 25/07598/ADFULL
Timeline
Dates from the published record
-
21 Oct 2025
Received by Westminster
-
21 Jul 2026
Added to PlanIndex
-
Decision
Awaiting decision
The statutory target is eight weeks for most applications and thirteen for major development. Extensions of time are common.
What happens while it is decided
The process from here
This application is with Westminster for determination. The council publicises it, consults neighbours and technical bodies where required, and weighs the responses against local and national planning policy.
The statutory target is eight weeks for most applications and thirteen for major development, though extensions of time are common. Comments carry most weight while the case is undecided, so check the council portal for the deadline if you want to respond.
About full applications applications
How this application type works
A full application seeks permission for a complete, detailed proposal in one go: siting, design, access and landscaping are all fixed at this stage. It is the standard route for new buildings, conversions and changes of use. The statutory target is eight weeks for smaller schemes and thirteen weeks for major development, though complex cases often take longer by agreement.
Nearby applications
Within 500 metres
-
26/02428/ADFULL Awaiting decision
46 Berkeley Square London W1J 5AT
Detailed drawings (at scales 1:20 and 1:5) and a sample (if they are not made of timber) of the both sets of doors to the ground floor frontage of 46 Hay's Mews pursuant to condition 27 of planning permission dated 30th January 2018 (RN:17/07633/FULL)
-
26/00731/FULL Awaiting decision
46 Berkeley Square London W1J 5AT
Variation of Conditions 14 and removal of Condition 15 of planning permission dated 30 January 2018 (RN: 17/07633/FULL) for 'Variation of Conditions 1 and 8 of planning permission dated 28 April 2017 (RN 16/07773/FULL) for the Use of 46 Berkeley Square as a private members club (sui generis use), with internal and external alterations including mechanical plant, and erection of Annabel's canopy to front; use of 46 Hay's Mews as a private members club, and a health and wellbeing club (sui generis) and alterations to the mews building including the erection of a pitched roof extension with mechanical plant; and erection of a full length retractable glazed canopy from the mews building to the main building enclosing the external dining terrace/courtyard; associated mechanical plant and landscaping (site includes 46 Hay's Mews): namely, to vary Condition 1 to enable alterations to the Hays Mews elevation, chimney to 46 Hays Mews to be raised in height, provision of a rear facing balcony and associated internal alterations and variation of Condition 8 to change the maximum capacities allowed in the two areas of the club from 550 to 750 people'. Amendments now proposed are NAMELY, to allow temporary refuse storage and collection arrangements for a period of two years.
-
26/01812/ADV Awaiting decision
46 Berkeley Square London W1J 5AT
Display of externally illuminated hoarding sign over scaffolding measuring 12.5m x 13.1m for a temporary period from 4th June to 8th July 2026.
-
25/07267/ADFULL Granted
46 Berkeley Square London W1J 5AT
Detailed operational management assessment pursuant to Condtition 19 of planning permission dated 30th January 2018 (RN:17/07633)
-
25/06669/NMA Withdrawn
46 Berkeley Square London W1J 5AT
Amendments to planning permission dated 30th January 2018 (RN 17/07633/FULL) for the Variation of Conditions 1 and 8 of planning permission dated 28 April 2017 (RN 16/07773/FULL) for the Use of 46 Berkeley Square as a private members club (sui generis use), with internal and external alterations including mechanical plant, and erection of Annabel's canopy to front; use of 46 Hay's Mews as a private members club, and a health and wellbeing club (sui generis) and alterations to the mews building including the erection of a pitched roof extension with mechanical plant; and erection of a full length retractable glazed canopy from the mews building to the main building enclosing the external dining terrace/courtyard; associated mechanical plant and landscaping (site includes 46 Hay's Mews): NAMELY, to remedial measures identified in the Monitoring Report dated 17th September 2025 shall be carried out at all times while the building is in use.
-
26/03965/ADV Awaiting decision
46 Berkeley Square London W1J 5AT
Display of an internally illuminated hoarding sign over temporary structure measuring 12.7m x 12.9m for a temporary period from 6th November 2026 - 3rd January 2027.
Other full applications applications
In Westminster
-
26/04824/ADFULL Granted
New Zealand House 80 Haymarket London SW1Y 4TE
Detailed design and specification of new blinds to NZH based on mock-up trials on-site. pursuant to condition 32 (i) of planning permission dated 8th April 2024 (23/00571/FULL).
-
26/04829/ADFULL Granted
New Zealand House 80 Haymarket London SW1Y 4TE
Details of external and internal signage strategy pursuant to Condition 33(E) of planning permission dated 8th April 2024 (RN: 23/00571/FULL)
-
26/04841/ADFULL Granted
29 Henstridge Place London NW8 6QD
Details of the facing materials you will use, including glazing, and elevations and roof plans annotated to show where the materials are to be located pursuant to condition 5 of planning permission dated 18th November 2025 (RN:25/06159).
-
26/04989/FULL Awaiting decision
1 Kildare Terrace London W2 5JT
Erection of a mansard roof extending over the main house and side wing, replacement lower ground rear extension with roof terrace above, lowering of lower ground floor slab, installation of an air source heat pump in rear garden, new front boundary treatment, and new second floor window on the north elevation.
-
26/04986/FULL Awaiting decision
Inver Court Inverness Terrace London W2 6JB
Replacement of combustible materials in the render facades; timber decking and plastic soffits/ fascias to terraces with non-combustible materials on the 5th and 6th floors.