Granted West Suffolk DCON(G)/22/0593 Discharge of Condition(s)

Relates to DC/22/0593/HYB

Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

Application to discharge conditions 22 (enhanced walking and cycling facilities - Stn Hill, Cullum Rd), 24 (enhanced walking and cycling facilities - brandt Way, Barons Road and Laundry), 25, (enhanced walking and cycling facilities - Sicklesmere Rd across Hardwick Heath), 26 (enhanced walking and cycling facilities - River Linnett) of application DC/22/0593/HYB

As published by the council, reference DCON(G)/22/0593

Application record

Reference
DCON(G)/22/0593
Type
Discharge of Condition(s)
Status
Decided
Decision
Granted As published: Approve application
Received
20 Nov 2025
Validated
20 Nov 2025
Decided
31 Jul 2026
Ward
Southgate
Parish
Bury St Edmunds Town Council
Decision by
Delegated

Site history

Applications at this address on the West Suffolk register

This site has had 8 applications since 2025: 2 approved, 0 refused.

  • DCON(K)/22/0593 Awaiting decision

    Land At Hardwick Manor Hardwick Lane Bury St Edmunds Suffolk

    Application to discharge conditions 63 (Ecology mitigation and enhancements), 65 (Biodiversity Enhancement Strategy), 67 (Natural England Mitigation Licence), 70 (Construction Environmental Management Plan) and 73 (Lighting design for the site) of application DC/22/0593/HYB

    Submitted 27 Oct 2026
  • NMA(C)/22/0539 Awaiting decision

    Land At Hardwick Manor Hardwick Lane Bury St Edmunds Suffolk

    Non-material amendment to DC/22/0593/HYB - a. amendments to trigger points for condition 67 and condition 69 b. amendment to wording of condition 79 and condition 83

    Submitted 20 Oct 2026
  • DCON(J)/22/0593 Awaiting decision

    Land At Hardwick Manor Hardwick Lane Bury St Edmunds Suffolk

    Application to discharge conditions 9 (loading/unloading areas) and 84 (agree details of the waste bins) of DC/22/0593/HYB

    Submitted 7 Oct 2026
  • DCON(I)/22/0593 Awaiting decision

    Land At Hardwick Manor Hardwick Lane Bury St Edmunds Suffolk

    Application to discharge condition 23 (water meadow) of application DC/22/0593/HYB

    Submitted 2 Jul 2026 Conditions
  • DCON(H)/22/0593 Awaiting decision

    Land At Hardwick Manor Hardwick Lane Bury St Edmunds Suffolk

    Application to discharge condition 42 (Post Excavation Assessments) of application DC/22/0593/HYB

    Submitted 7 Apr 2026 Conditions
  • NMA(B)/22/0593 Granted

    Land At Hardwick Manor Hardwick Lane Bury St Edmunds Suffolk

    Non-material amendment to DC/22/0593/HYB - a. amendment to proposed developable area b. amendments to building heights parameters c. updated proposed zones of restricted access parameter plan

    Decided 2 Apr 2026 Amendments
  • DCON(F)/22/0593 Awaiting decision

    Land At Hardwick Manor Hardwick Lane Bury St Edmunds Suffolk

    Application to discharge condition 40 (Site-Specific Written Schemes of Investigation) of DC/22/0593/HYB

    Submitted 2 Sep 2025 Conditions

Timeline

Dates from the published record

  1. 20 Nov 2025

    Received by West Suffolk

  2. 24 Jul 2026

    Added to PlanIndex

  3. 31 Jul 2026

    Decision issued: Approve application

Cases linked to this one on the register

  • DC/22/0593/HYB Granted

    Land At Hardwick Manor Hardwick Lane Bury St Edmunds IP33 2RD Suffolk

    Hybrid planning application - a. outline application (means of access to be considered) for a new hospital (use class C2) of up to 100,000 square metres and surface and multistorey car park with associated infrastructure, structural landscape buffer, temporary construction compound and demolition of existing hospital buildings. b. full planning application - change of use of Hardwick Manor from a single residential dwelling (use class C3) to health related uses associated with the new hospital (use class C2) as amended by plans and documents received 08.08.2022 and 07.10.2022

    Decided 3 May 2023

Who's behind it

Company information only, from the register and Companies House

Newsteer Agent, registered in Fleet

Active · incorporated 2019 · Fleet

51 applications on PlanIndex · across 21 councils · 100% granted

Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.

See their track record

Documents

Plans, drawings, consultee responses and the officer's report

109 documents on file for this application

  • CONDITION 25 ROUTE D SITE CLEARANCE PLAN SHEET 4 Site and Other Plans/Drawings · 21 Nov 2025
  • CONDITION 22 ROUTE A SURFACE & KERB LAYOUT SHEET 2 Site and Other Plans/Drawings · 21 Nov 2025
  • CONDITION 22 ROUTE A ENG LAYOUT SHEET 2 Site and Other Plans/Drawings · 21 Nov 2025
  • APPLICATION FORM - WITHOUT PERSONAL DATA Application Form · 20 Nov 2025
  • COVERING LETTER Supporting Documents · 20 Nov 2025
  • CONDITION 22 ROUTE A ARBORICULTURAL METHOD STATEMENT Supporting Documents · 20 Nov 2025
  • CONDITION 22 ROUTE A GA SHEET 1 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 22 ROUTE A GA SHEET 2 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 22 ROUTE A GA SHEET 3 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 22 ROUTE A GA SHEET 4 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 22 ROUTE A ENG LAYOUT SHEET 1 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 22 ROUTE A ENG LAYOUT SHEET 3 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 22 ROUTE A ENG LAYOUT SHEET 4 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 22 ROUTE A ENG LAYOUT SHEET 5 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 22 ROUTE A SITE CLEARANCE LAYOUT SHEET 1 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 22 ROUTE A SITE CLEARANCE LAYOUT SHEET 2 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 22 ROUTE A SITE CLEARANCE LAYOUT SHEET 3 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 22 ROUTE A SITE CLEARANCE LAYOUT SHEET 4 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 22 ROUTE A COLOUR PLAN SHEET 1 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 22 ROUTE A COLOUR PLAN SHEET 2 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 22 ROUTE A COLOUR PLAN SHEET 3 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 22 ROUTE A COLOUR PLAN SHEET 4 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 22 ROUTE A SURFACE & KERB LAYOUT SHEET 1 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 22 ROUTE A SURFACE & KERB LAYOUT SHEET 3 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 22 ROUTE A SURFACE & KERB LAYOUT SHEET 4 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 22 ROUTE A SURFACE & KERB LAYOUT SHEET 5 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 22 ROUTE A CONSTRUCTION DETS SHEET 1 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 22 ROUTE A CONSTRUCTION DETS SHEET 2 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 22 ROUTE A TAYFEN RD/ST ANDREWS CROSS SECTIONS Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 22 PROPOSED LIGHTING IMPROVEMENTS Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 22 PROPOSED LIGHTING IMPROVEMENTS Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 22 PROPOSED LIGHTING IMPROVEMENTS Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 24 ROUTE B ARBORICULTURAL METHOD STATEMENT Supporting Documents · 20 Nov 2025
  • CONDITION 24 ROUTE B GA SHEET 1 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 24 ROUTE B GA SHEET 2 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 24 ROUTE B GA SHEET 3 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 24 ROUTE B GA SHEET 4 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 24 ROUTE B CONSTRUCTION DETS SHEET 1 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 24 ROUTE B CONSTRUCTION DETS SHEET 2 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 24 ROUTE B ENGINEER LAYOUT SHEET 1 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 24 ROUTE B ENGINEERING LAYOUT SHEET 2 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 24 ROUTE B ENGINEERING LAYOUT SHEET 3 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 24 ROUTE B SITE CLEARANCE LAYOUT SHEET 1 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 24 ROUTE B SITE CLEARANCE LAYOUT SHEET 2 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 24 ROUTE B SITE CLEARANCE LAYOUT SHEET 3 Site and Other Plans/Drawings · 20 Nov 2025
  • OUTDOOR LIGHTING REPORT Supporting Documents · 20 Nov 2025
  • CONDITION 24 PROPOSED LIGHTING IMPROVEMENTS Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 24 PROPOSED LIGHTING IMPROVEMENTS Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 24 PROPOSED LIGHTING IMPROVEMENTS Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 24 PROPOSED LIGHTING IMPROVEMENTS Site and Other Plans/Drawings · 20 Nov 2025
  • DRAWING ISSUE REGISTER Supporting Documents · 20 Nov 2025
  • CONDITION 25 ROUTE D ARBORICULTURAL METHOD STATEMENT Supporting Documents · 20 Nov 2025
  • CONDITION 25 ROUTE D GA SHEET 3 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 25 ROUTE D GA SHEET 4 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 25 ROUTE D ENGINEERING LAYOUT SHEET 1 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 25 ROUTE D ENGINEERING LAYOUT SHEET2 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 25 ROUTE D ENGINEERING LAYOUT SHEET 3 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 25 ROUTE D ENGINEERING LAYOUT SHEET 4 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 25 ROUTE D ENGINEERING LAYOUT SHEET 5 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 25 ROUTE D ENGINEERING LAYOUT SHEET 6 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 25 ROUTE D ENGINEERING LAYOUT SHEET 7 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 25 ROUTE D SECTION 278 COLOUR PLAN SHEET 1 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 25 ROUTE D SECTION 278 COLOUR PLAN SHEET 2 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 22 ROUTE D SECTION 278 COLOUR PLAN SHEET 3 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 25 ROUTE D SECTION 278 COLOUR PLAN SHEET 4 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 25 ROUTE D CONSTRUCTION DETS SHEET 1 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 25 ROUTE D CONSTRUCTION DETS SHEET 2 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 25 ROUTE D SITE CLEARANCE PLAN SHEET 1 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 25 ROUTE D SITE CLEARANCE PLAN SHEET 2 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 25 ROUTE D SITE CLEARANCE PLAN SHEET 3 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 25 ROUTE D CROSS SECTION Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 25 ROUTE D GA SHEET 1 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 25 ROUTE D GA SHEET 2 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 25 PROPOSED LIGHTING IMPROVEMENTS Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 25 PROPOSED LIGHTING IMPROVEMENTS Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 25 PROPOSED LIGHTING IMPROVEMENTS Site and Other Plans/Drawings · 20 Nov 2025
  • ARBORICULTURAL METHOD STATEMENT Supporting Documents · 20 Nov 2025
  • CONDITION 26 RIVER LINNETT GA SHEET 1 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 26 RIVER LINNETT GA SHEET 2 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 26 RIVER LINNETT GA SHEET 3 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 26 RIVER LINNETT ENGINEERING LAYOUT SHEET 1 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 26 RIVER LINNETT ENGINEERING LAYOUT SHEET 2 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 26 RIVER LINNETT ENGINEERING LAYOUT SHEET 3 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 26 RIVER LINNETT ENGINEERING LAYOUT SHEET 4 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 26 RIVER LINNETT ENGINEERING LAYOUT PLAN SHEET 5 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 26 RIVER LINNETT ENGINEERING LAYOUT PLAN SHEET 6 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 26 RIVER LINNETT ENGINEERING LAYOUT PLAN SHEET 7 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 26 RIVER LINNETT ENGINEERING LAYOUT SHEET 8 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 26 RIVER LINNETT SITE CLEARANCE PLAN SHEET 1 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 26 RIVER LINNETT SITE CLEARANCE PLAN SHEET 2 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 26 RIVER LINNETT SITE CLEARANCE PLAN SHEET 3 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 26 RIVER LINNETT SITE CLEARANCE PLAN SHEET 4 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 26 RIVER LINNETT SITE CLEARANCE PLAN SHEET 5 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 26 RIVER LINNETT SITE CLEARANCE PLAN SHEET 6 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 26 RIVER LINNETT SITE CLEARANCE PLAN SHEET 7 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 26 RIVER LINNETT SITE CLEARANCE PLAN SHEET 8 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 26 RIVER LINNETT COLOUR PLAN SHEET 1 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 26 RIVER LINNETT COLOUR PLAN SHEET 2 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 26 RIVER LINNETT COLOUR PLAN SHEET 3 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 26 RIVER LINNETT COLOUR PLAN SHEET 4 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 26 RIVER LINNETT COLOUR PLAN SHEET 5 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 26 RIVER LINNETT COLOUR PLAN SHEET 6 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 26 RIVER LINNETT COLOUR PLAN SHEET 7 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 26 RIVER LINNETT COLOUR PLAN SHEET 8 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 26 RIVER LINNETT CONSTRUCTION DETS SHEET 1 Site and Other Plans/Drawings · 20 Nov 2025
  • CONDITION 26 RIVER LINNETT CONSTRUCTION DETS SHEET 2 SECTIONS Site and Other Plans/Drawings · 20 Nov 2025
  • DRAWING ISSUE REGISTER Supporting Documents · 20 Nov 2025
  • DRAWING ISSUE REGISTER Supporting Documents · 20 Nov 2025
  • DRAWING ISSUE REGISTER Supporting Documents · 20 Nov 2025

Watch members (£5 a month) open the document list from here.

Open the documents

What this grant of permission means

West Suffolk granted permission on 31 July 2026, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About condition discharge and variation applications

This application deals with conditions on an existing permission, supplying the details a condition requires or asking to vary or remove one, without reopening the permission itself. More in our guide to planning application types.

Nearby applications

Within 0.3 miles

  • Land At Hardwick Manor Hardwick Lane Bury St Edmunds Suffolk

    DCON(H)/22/0593 Submitted 7 Apr 2026 50 yards away

    99% historically approved · decision due ~2 Jun

    Application to discharge condition 42 (Post Excavation Assessments) of application DC/22/0593/HYB

    Awaiting decision Conditions 4 docs
  • Land At Hardwick Manor Hardwick Lane Bury St Edmunds Suffolk

    NMA(B)/22/0593 Submitted 20 Jan 2026 50 yards away

    Non-material amendment to DC/22/0593/HYB - a. amendment to proposed developable area b. amendments to building heights parameters c. updated proposed zones of restricted access parameter plan

    Granted Amendments 12 docs
  • Land At Hardwick Manor Hardwick Lane Bury St Edmunds IP33 2RD Suffolk

    DC/22/0593/HYB Submitted 4 Apr 2022 50 yards away

    Hybrid planning application - a. outline application (means of access to be considered) for a new hospital (use class C2) of up to 100,000 square metres and surface and multistorey car park with associated infrastructure, structural landscape buffer, temporary construction compound and demolition of existing hospital buildings. b. full planning application - change of use of Hardwick Manor from a single residential dwelling (use class C3) to health related uses associated with the new hospital (use class C2) as amended by plans and documents received 08.08.2022 and 07.10.2022

    Granted Demolition 345 docs
    Domestic
  • West Suffolk Hospital Hardwick Lane Bury St Edmunds Suffolk

    DC/26/0647/RM Submitted 23 Apr 2026 50 yards away

    96% historically approved · decision due ~18 Jun

    Reserved Matters Application - Submission of details under DC/22/0593/HYB - the means of appearance, landscaping, layout and scale for new hospital (Class C2), including car parking, associated infrastructure, structural landscape buffer, temporary construction compound and demolition of existing hospital buildings

    Awaiting decision Reserved matters Demolition 154 docs
  • Land At Hardwick Manor Hardwick Lane Bury St Edmunds Suffolk

    DCON(F)/22/0593 Submitted 2 Sep 2025 50 yards away

    99% historically approved · decision due ~28 Oct

    Application to discharge condition 40 (Site-Specific Written Schemes of Investigation) of DC/22/0593/HYB

    Awaiting decision Conditions 4 docs
  • Park View 25 Sharp Road Bury St Edmunds Suffolk IP33 2NB

    DC/24/1009/HH Submitted 18 Jul 2024 50 yards away

    Householder planning application - detached carport

    Refused Householder 7 docs
    Domestic

In West Suffolk

  • DCON(B)/22/1678 Granted

    The Yews 49 High Street Lakenheath Suffolk IP27 9DS

    Application to discharge condition 3 (EPS license) and condition 7 (Historic post investigation) of application DC/23/1596/VAR

    Received 13 Oct, published by the council 24 Jul 2026 Conditions
  • DCON(BGP)/25/1926 Awaiting decision

    Beck Row Primary School The Street Beck Row Bury St Edmunds Suffolk IP28 8AE

    Application to discharge condition 10 (BNG Gain Plan) of application DC/25/1926/FUL

    Received 4 Sep, published by the council 7 Sep 2026 Conditions
  • DCON(BGP)/25/1927 Awaiting decision

    Beck Row Primary School The Street Beck Row Bury St Edmunds Suffolk IP28 8AE

    Application to discharge condition 4 (BNG Gain Plan) of application DC/25/1927/FUL

    Received 4 Sep, published by the council 7 Sep 2026 Conditions
  • DCON(A)/25/2037 Awaiting decision

    Newmarket Community Hospital 56 Exning Road Newmarket Suffolk CB8 7JG

    Application to discharge conditions 4 (CMP- PRECOMM), 5 (CEMP- PRECOMM) and 9 (CSWMP- PRECOMM) of application DC/25/2037/FUL

    Received 2 Sep, published by the council 4 Sep 2026 Conditions
  • DCON(A)/25/1927 Awaiting decision

    Beck Row Primary School The Street Beck Row Suffolk IP28 8AE

    Application to discharge condition 6 (LEMP pre-commencement) of application DC/25/1927/FUL

    Received 20 Aug, published by the council 24 Aug 2026 Conditions