Former Ferrybridge Substation Stranglands Lane Ferrybridge WF11 8DX

Awaiting decision Wakefield 24/01465/SUB01

Relates to 24/01465/FUL

Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.

Proposal

Discharge of conditions 3 (CEMP), 4 (BNG Plan) and 5 (Habitat Management and Monitoring Plan) from approved application 24/01465/FUL.

As published by the council, reference 24/01465/SUB01

Application record

Reference
24/01465/SUB01
Status
Awaiting decision
Received
16 Sep 2026
Validated
16 Sep 2026
Postcode
WF11 8DX

Timeline

Dates from the published record

  1. 16 Sep 2026

    Received by Wakefield

  2. 22 Sep 2026

    Added to PlanIndex

  3. Decision

    Awaiting decision

    Decision expected by 11 November 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.

    Wakefield took a median of 70 days over the applications it decided in the last year.

Cases linked to this one on the register

  • 24/01465/FUL Granted

    Former Ferrybridge Power Station Stranglands Lane Ferrybridge WF11 8DX

    Proposed substation compound including transformers, switch house, generator and associated fencing

    Decided 18 Dec 2024 Full applications

What happens while it is decided

This application is with Wakefield for determination, against a statutory target of eight weeks. Over the last year Wakefield's median decision took 70 days. More in our guide to how long planning decisions take.

About this record

The published feed does not state which type of application this is; the register entry on Wakefield's portal will say. Our guide explains the common types.

Nearby applications

Within 0.3 miles