Former Coal Yard, Ferrybridge 'C' Power Station Kirkhaw Lane Knottingley Ferrybridge

Awaiting decision Wakefield 23/00100/SUB38

Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.

Proposal

Application to discharge Condition 39 (Earthworks Verification) for Zone A of Planning Permission 23/00100/S7301

As published by the council, reference 23/00100/SUB38

Application record

Reference
23/00100/SUB38
Status
Awaiting decision
Received
7 Oct 2026
Validated
7 Oct 2026

Site history

Applications at this address on the Wakefield register

This site has had 4 applications since 2025: 2 approved, 0 refused.

  • 23/00100/NMC03 Decided

    Former Coal Yard, Ferrybridge 'C' Power Station Kirkhaw Lane Knottingley Ferrybridge

    Non material amendment to application number 23/00100/REM04 Approval of Reserved Matters pursuant to 23/00100/S7301 (Internal Access, Appearance, Landscaping, Layout, and Scale) at Development Zone B for the erection of one B8 (Storage and Distribution Unit) (Unit 3A) with associated ancillary structures, plant, boundary enclosures, vehicle parking, hard and soft landscaping, and associated external works, to amend the wording of approved plans condition (Condition 2 Approved Plans).

    Decided 18 Aug 2026
  • 23/00100/REM04 Granted

    Former Coal Yard, Ferrybridge 'C' Power Station Kirkhaw Lane Knottingley Ferrybridge

    Approval of Reserved Matters pursuant to 23/00100/S7301 (Internal Access, Appearance, Landscaping, Layout, and Scale) at Development Zone B for the erection of one B8 (Storage and Distribution Unit) (Unit 3A) with associated ancillary structures, plant, boundary enclosures, vehicle parking, hard and soft landscaping, and associated external works.

    Decided 9 Jul 2026 Reserved matters
  • 23/00100/REM05 Granted

    Former Coal Yard, Ferrybridge 'C' Power Station Kirkhaw Lane Knottingley Ferrybridge

    Approval of Reserved Matters pursuant to 23/00100/S7301 (Internal Access, Appearance, Landscaping, Layout, and Scale) at Development Zone B for the erection of three B2 (general industrial)/B8 (Storage and Distribution) Units (Units 3, 4 and 5) with associated ancillary structures, plant, boundary enclosures, vehicle parking, hard and soft landscaping, and associated external works.

    Decided 30 Jun 2026 Reserved matters

Timeline

Dates from the published record

  1. 7 Oct 2026

    Received by Wakefield

  2. 9 Oct 2026

    Added to PlanIndex

  3. Decision

    Awaiting decision

    Decision expected by 2 December 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.

    Wakefield took a median of 79 days over the applications it decided in the last year.

What happens while it is decided

This application is with Wakefield for determination, against a statutory target of eight weeks. Over the last year Wakefield's median decision took 79 days. More in our guide to how long planning decisions take.

About this record

The published feed does not state which type of application this is; the register entry on Wakefield's portal will say. Our guide explains the common types.