Planning application
Former Coal Yard, Ferrybridge 'C' Power Station Ferrybridge Kirkhaw Lane Knottingley
Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.
Proposal
Application to Discharge 11 (Construction Environmental Management Plan (CEMP), Condition 12 (Construction Traffic Management Plan (CTMP) and Condition 21 (Temporary Drainage) for Stage 5 of Planning Permission 23/00100/S7301
As published by the council, reference 23/00100/SUB30
Application record
- Reference
- 23/00100/SUB30
- Status
- Awaiting decision
- Received
- 9 Jul 2026
- Validated
- 15 Jul 2026
- Ward
- Knottingley
Site history
Applications at this address on the Wakefield register
This site has had 15 applications since 2025: 3 approved, 0 refused.
-
23/00100/SUB36 Awaiting decision
Former Coal Yard, Ferrybridge 'C' Power Station Ferrybridge Kirkhaw Lane Knottingley
Application to discharge Condition 41 (Gas Protection) for Unit 1 (Zone C) of Planning Permission 23/00100/S7301
-
23/00100/SUB34 Granted
Former Coal Yard, Ferrybridge 'C' Power Station Ferrybridge Kirkhaw Lane Knottingley
Application to discharge Condition 45 (fencing) of Planning Permission 23/00100/S7301
-
23/00100/SUB32 Decided
Former Coal Yard, Ferrybridge 'C' Power Station Ferrybridge Kirkhaw Lane Knottingley
Application to Discharge Condition 30 (Energy) for Units 1 & 2 of Planning Permission 23/00100/S7301
-
23/00100/SUB31 Awaiting decision
Former Coal Yard, Ferrybridge 'C' Power Station Ferrybridge Kirkhaw Lane Knottingley
Application to Discharge Condition 23 (Drainage) for Zone B of Planning Permission 23/00100/S7301
-
23/00100/SUB28 Awaiting decision
Former Coal Yard, Ferrybridge 'C' Power Station Ferrybridge Kirkhaw Lane Knottingley
Application to Discharge Condition 19 (Landscape and Ecological Management Plan (LEMP)) for development Zone B of Planning Permission 23/00100/S7301
-
26/01211/ADV Decided
Former Coal Yard, Ferrybridge 'C' Power Station Ferrybridge Kirkhaw Lane Knottingley
Internally Illuminated Signage Scheme
-
23/00100/SUB27 Decided
Former Coal Yard, Ferrybridge 'C' Power Station Ferrybridge Kirkhaw Lane Knottingley
Application to Discharge Condition 27 (Artificial Lighting) for Units 1 and 2 (within Zone C) of Planning Permission 23/00100/S7301
-
23/00100/SUB25 Decided
Former Coal Yard, Ferrybridge 'C' Power Station Ferrybridge Kirkhaw Lane Knottingley
Application to discharge Condition 41 (Gas Protection) for Unit 2 (Zone C) of Planning Permission 23/00100/S7301
-
23/00100/SUB24 Decided
Former Coal Yard, Ferrybridge 'C' Power Station Ferrybridge Kirkhaw Lane Knottingley
Application to discharge Condition 44 (Employment and Skills Plan) for Unit 2 (Zone c) of Planning Permission 23/00100/S7301
-
23/00100/SUB23 Decided
Former Coal Yard, Ferrybridge 'C' Power Station Ferrybridge Kirkhaw Lane Knottingley
Application to Discharge Condition 43 (Acoustic Fencing) as amended under 23/00100/NMC02 of Planning Permission 23/00100/S7301
Timeline
Dates from the published record
-
9 Jul 2026
Received by Wakefield
-
15 Jul 2026
Validated
Checked as complete and ready for consideration.
-
22 Jul 2026
Added to PlanIndex
-
Decision
Awaiting decision
Decision expected by 9 September 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.
Wakefield took a median of 63 days over the applications it decided in the last year.
Related applications
Cases linked to this one on the register
- Application: 23/00100/S7301 (Decided)
Who's behind it
Company information only, from the register and Companies House
Oxalis Planning Ltd Agent, a planning consultancy registered in Loughborough
Active · incorporated 2010 · Loughborough
79 applications on PlanIndex · across 7 councils · 98% granted
Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.
See their track recordDocuments
Plans, drawings, consultee responses and the officer's report
5 documents on file for this application
- WAKEFIELD COUNCIL DRAINAGE
- NATIONAL HIGHWAYS
- NATIONAL HIGHWAYS
- APPLICATIONFORMREDACTED
- CONSTRUCTION ENVIRONMENT MANAGEMENT PLAN
Trade members open them from here.
Open the documentsWhat happens while it is decided
This application is with Wakefield for determination, against a statutory target of eight weeks. Over the last year Wakefield's median decision took 63 days. More in our guide to how long planning decisions take.
About this record
The published feed does not state which type of application this is; the register entry on Wakefield's portal will say. Our guide explains the common types.