Land at Royal Mint St Mansell St and Chamber St, Royal Mint Street, London E1

Awaiting decision Tower Hamlets PA/26/00002/S Variation / Removal Condition (TCPA S73)

Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.

Proposal

Variation of Conditions 1 (Method Statement - Approved Documents and Plans), 2 (Scheme Details) and 35 (Temporary Sleeping Accommodation) of planning permission PA/22/01284/S, dated 23/12/2024: Reconfigure internal floor plans. Amended façades and roof profile, including plant equipment, lift overruns and means of escape. Installation of Docklands Light Railway smoke ventilation duct. Re-location of communal amenity space. Changes to housing mix.

As published by the council, reference PA/26/00002/S

Application record

Reference
PA/26/00002/S
Type
Variation / Removal Condition (TCPA S73)
Status
Registered
Received
9 Mar 2026
Validated
9 Mar 2026
Ward
Whitechapel
Decision by
Delegated

Site history

Applications at this address on the Tower Hamlets register

This site has had 5 applications since 2025: 3 approved, 0 refused.

  • PA/26/00517/S Granted

    Land at Royal Mint St Mansell St and Chamber St, Royal Mint Street, London, E1

    Submission of details pursuant to Condition 41 (Water Efficiency Calculator) of planning permission ref: PA/22/01284, dated 23/12/2024.

    Decided 9 Apr 2026 Conditions
  • PA/26/00504/S Awaiting decision

    Land at Royal Mint St Mansell St and Chamber St, Royal Mint Street, London E1

    Application for non-material amendment of planning permission PA/22/01284, dated 23/12/2023: Amendment to wording of Condition 19, part b).

    Submitted 19 Mar 2026 Amendments
  • PA/25/01739/NC Granted

    Land at Royal Mint St Mansell St and Chamber St, Royal Mint Street, London E1

    Application for non-material amendment of planning permission dated 23/12/2024, ref: PA/22/01284. Non-material amendment(s) sought: - Amendment to the trigger of Condition 1

    Decided 22 Oct 2025 Amendments
  • PA/25/01738/NC Granted

    Land at Royal Mint St Mansell St and Chamber St, Royal Mint Street, London E1

    Application for non-material amendment of planning permission dated 23/12/2024, ref: PA/22/01284. Non-material amendment(s) sought: - Amendment to the trigger of Condition 48

    Decided 21 Oct 2025 Amendments

Timeline

Dates from the published record

  1. 9 Mar 2026

    Received by Tower Hamlets

  2. 25 Jul 2026

    Added to PlanIndex

  3. Decision

    Awaiting decision

    Decision expected by 4 May 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.

    Tower Hamlets took a median of 56 days over the applications it decided in the last year.

Cases linked to this one on the register

  • Application: PA/22/01284/S (Decided)

Who's behind it

Company information only, from the register and Companies House

Rolfe Judd Planning Ltd Agent, a planning consultancy registered in The Oval

Active · incorporated 1992 · The Oval

522 applications on PlanIndex · across 22 councils · 94% granted

Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.

See their track record

RMS (England) Limited Applicant, registered in London

Active · incorporated 2012 · London

4 applications on PlanIndex

Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.

See their track record

Documents

Plans, drawings, consultee responses and the officer's report

214 documents on file for this application

  • APPLICANT RESPONSE TO EIA REVIEW ? WIND Correspondence · 11 Aug 2026
  • HISTORIC ENGLAND Consultee Comment · 28 Jul 2026
  • ES ADDENDUM FINAL REVIEW PREPARED FOR LBTH Consultee Comment · 07 Jul 2026
  • APPLICANT RESPONSE TO EIA REVIEW - HTVIA Correspondence · 26 May 2026
  • APPLICANT RESPONSE TO EIA REVIEW Correspondence · 26 May 2026
  • FACADE EWS 10 (SCW - 311) BAY STUDY ANALYSIS Current Plan · 19 May 2026
  • FACADE EWS 10A (SCW - 311) BAY STUDY ANALYSIS Current Plan · 19 May 2026
  • FACADE EWS 05 (UCW-115D) BAY STUDY ANALYSIS Current Plan · 19 May 2026
  • EWS 01 (UCW-111) - TYPICAL UNITISED FACADE DETAILS Current Plan · 19 May 2026
  • WALKWAY GANTRY DETAILS- SHEET 01 Current Plan · 19 May 2026
  • SCS-712/ CRS-612 -RESI SOFFIT DETAIL Current Plan · 19 May 2026
  • MECHANICAL SERVICES VENTILATION LAYOUT RESIDENTIAL BUILDING LEVEL 02 Current Plan · 19 May 2026
  • MECHANICAL SERVICES VENTILATION LAYOUT RESIDENTIAL BUILDING LEVEL 03 Current Plan · 19 May 2026
  • RMS VENTILATION FLOWRATES (RESIDENTIAL) Report · 19 May 2026
  • PART O THERMAL COMFORT REPORT Report · 19 May 2026
  • DOORSET FOR INTEGRAL SUBSTATION Current Plan · 19 May 2026
  • BRICK SAMPLE Correspondence · 19 May 2026
  • WASTE STORAGE AND COLLECTION STRATEGY Report · 19 May 2026
  • APPROVED ARCHAEOLOGICAL POST- EXCAVATION ASSESSMENT Report · 19 May 2026
  • LANDSCAPE LIGHTING CONCEPT Report · 19 May 2026
  • MATERIAL SAMPLE: MORTAR ? BLACK LIGHT Photo · 19 May 2026
  • APARTHOTEL ROOFTOP BAR Current Plan · 19 May 2026
  • FACADE TREATMENT Design Statement · 19 May 2026
  • EXPOSED GUTTERING Design Statement · 19 May 2026
  • PLANT SPECIFICATION - Q-AIRE Report · 19 May 2026
  • SSL CALCULATIONS Report · 19 May 2026
  • PLANT SPECIFICATION MIDI Report · 19 May 2026
  • PROVISIONAL ALUM COLUMN CLADDING Current Plan · 19 May 2026
  • PROVISIONAL GRC COLUMN CLADDING Current Plan · 19 May 2026
  • SCW-311 PARTIAL ELEVATION (EAST) Current Plan · 19 May 2026
  • SCW-311 VS & HS THROUGH SINGLE DOOR Current Plan · 19 May 2026
  • SCW-311 VS APARTHOTEL ENTRANCE Current Plan · 19 May 2026
  • SCW-311 VERTICAL SECTION DOOR CAFE Current Plan · 19 May 2026
  • SCW-311 VS PORTAL DOOR @ F&B ENTRANCE Current Plan · 19 May 2026
  • SCW-311 VS DOOR AT EAST ELEVATION Current Plan · 19 May 2026
  • SCW-311 VS DOOR AT EAST ELEVATION Current Plan · 19 May 2026
  • SCW-311 VS DOOR AT EAST ELEVATION Current Plan · 19 May 2026
  • SCW-311 VS DOOR& BRICK FACED GRC Current Plan · 19 May 2026
  • GA SOUTH & EAST ELEVATION GROUND FLOOR Current Plan · 19 May 2026
  • GA NORTH & WEST ELEVATION GROUND FLOOR Current Plan · 19 May 2026
  • APARTHOTEL -EXTERNAL DOOR TYPE ELEVATIONS Current Plan · 19 May 2026
  • TYPICAL EXTERNAL SERVICING LOUVRE DOOR ELEVATION Current Plan · 19 May 2026
  • PROPOSED TYPICAL RESIDENTIAL RECESSED BALCONY Current Plan · 19 May 2026
  • GA PLAN - CYCLE STORE Current Plan · 19 May 2026
  • ARCH 41 - RESIDENTIAL CYCLE STORE SECTION Current Plan · 19 May 2026
  • ARCH 41 - RESIDENTIAL CYCLE STORE PART PLAN - PART A Current Plan · 19 May 2026
  • ARCH 41 - RESIDENTIAL CYCLE STORE PART PLAN - PART B Current Plan · 19 May 2026
  • ARCH 41 - RESIDENTIAL CYCLE STORE PART PLAN - PART C Current Plan · 19 May 2026
  • GA PLAN -WASTE STORE Current Plan · 19 May 2026
  • CHAMBER STREET ENTRANCE PLAN Current Plan · 19 May 2026
  • NR ARCHES - CHAMBER STREET ENTRANCE POINTS Current Plan · 19 May 2026
  • GA PLANS -ROOF FLOOR Current Plan · 19 May 2026
  • GA PLANS -ROOF FLOOR (ADDITIONAL PLAN) Current Plan · 19 May 2026
  • ROOF ZONE E -ROOF LEVEL- SHEET 1 Current Plan · 19 May 2026
  • ROOF ZONE E -ROOF LEVEL- SHEET 2 Current Plan · 19 May 2026
  • ROOF ZONE E -ROOF LEVEL- SHEET 3 Current Plan · 19 May 2026
  • ROOF ZONE I -RESI ROOF LEVEL Current Plan · 19 May 2026
  • LIFT OVERRUN TYPICAL DETAIL Current Plan · 19 May 2026
  • TYPICAL ROOF TYPES SHEET 1 Current Plan · 19 May 2026
  • DETAILED SECTIONS -SHEET 07 Current Plan · 19 May 2026
  • FACADE EWS 01 (UCW-111) BAY STUDY ANALYSIS Current Plan · 19 May 2026
  • FACADE EWS 05 (UCW-115) BAY STUDY ANALYSIS Current Plan · 19 May 2026
  • FACADE EWS 05B (UCW-115B) BAY STUDY ANALYSIS Current Plan · 19 May 2026
  • FACADE EWS 07 (SCW-311) BAY STUDY ANALYSIS Current Plan · 19 May 2026
  • FACADE EWS 08 (SCW-311) BAY STUDY ANALYSIS Current Plan · 19 May 2026
  • FACADE EWS 02B (UCW-112B) BAY STUDY ANALYSIS Current Plan · 19 May 2026
  • FACADE EWS 05 (UCW-115D) BAY STUDY ANALYSIS Current Plan · 19 May 2026
  • FACADE EWS 06 (CRS-631) BAY STUDY ANALYSIS Current Plan · 19 May 2026
  • FACADE EWS 09B (SCW-311) BAY STUDY ANALYSIS Current Plan · 19 May 2026
  • FACADE EWS 02C (SCW-312) BAY STUDY ANALYSIS Current Plan · 19 May 2026
  • FACADE EWS 07B (CSW-311) BAY STUDY ANALYSIS Current Plan · 19 May 2026
  • FACADE EWS 10 (SCW-311) BAY STUDY ANALYSIS Current Plan · 19 May 2026
  • FACADE EWS 03 (UCW - 116) BAY STUDY ANALYSIS Current Plan · 19 May 2026
  • APPLICANT RESPONSE TO HRP COMMENTS Correspondence · 06 May 2026
  • GLA RESPONSE Consultee Comment · 15 Apr 2026
  • HISTORIC ROYAL PALACES Consultee Comment · 13 Apr 2026
  • TFL - INFRASTRUCTURE PROTECTION Consultee Comment · 10 Apr 2026
  • CITY OF LONDON Consultee Comment · 09 Apr 2026
  • BUILDING SAFETY REGULATOR Consultee Comment · 02 Apr 2026
  • HISTORIC ENGLAND - GLAAS Consultee Comment · 01 Apr 2026
  • ENVIRONMENT AGENCY Consultee Comment · 01 Apr 2026
  • TFL - SPATIAL PLANNING Consultee Comment · 31 Mar 2026
  • NATURAL ENGLAND Consultee Comment · 23 Mar 2026
  • APPROVED ES VOL 2 (DECEMBER 2022) - ANNEX E - FLOOD RISK, DRAINAGE AND WATER RESOURCES Environmental Statement · 19 Mar 2026
  • AS APPROVED GLA CONSULTATION ENERGY MEMO Correspondence · 19 Mar 2026
  • AS APPROVED REGULATIONS COMPLIANCE REPORT - 3 BED TOP FLOOR CHP Correspondence · 19 Mar 2026
  • AS APPROVED REGULATIONS COMPLIANCE REPORT - 3 BED DUAL MID FLOOR CHP Correspondence · 19 Mar 2026
  • AS APPROVED REGULATIONS COMPLIANCE REPORT - 2 BED MID FLOOR SOUTH CHP Correspondence · 19 Mar 2026
  • AS APPROVED REGULATIONS COMPLIANCE REPORT - 2 BED MID FLOOR CHP Correspondence · 19 Mar 2026
  • AS APPROVED REGULATIONS COMPLIANCE REPORT - 1 BED TOP FLOOR CHP Correspondence · 19 Mar 2026
  • AS APPROVED REGULATIONS COMPLIANCE REPORT - 1 BED MID FLOOR CHP Correspondence · 19 Mar 2026
  • AS APPROVED REGULATIONS COMPLIANCE REPORT - 3 BED TOP FLOOR BE GREEN Correspondence · 19 Mar 2026
  • AS APPROVED REGULATIONS COMPLIANCE REPORT - 3 BED DUAL MID FLOOR BE GREEN Correspondence · 19 Mar 2026
  • AS APPROVED REGULATIONS COMPLIANCE REPORT - 2 BED MID FLOOR SOUTH BE GREEN Correspondence · 19 Mar 2026
  • AS APPROVED REGULATIONS COMPLIANCE REPORT - 2 BED MID FLOOR BE GREEN Correspondence · 19 Mar 2026
  • AS APPROVED REGULATIONS COMPLIANCE REPORT - 1 BED TOP FLOOR BE GREEN Correspondence · 19 Mar 2026
  • AS APPROVED REGULATIONS COMPLIANCE REPORT - 1 BED MID FLOOR BE GREEN Correspondence · 19 Mar 2026
  • AS APPROVED REGULATIONS COMPLIANCE REPORT - 3 BED TOP FLOOR BE LEAN Correspondence · 19 Mar 2026
  • AS APPROVED REGULATIONS COMPLIANCE REPORT - 3 BED DUAL MID FLOOR BE LEAN Correspondence · 19 Mar 2026
  • AS APPROVED REGULATIONS COMPLIANCE REPORT - 2 BED MID FLOOR SOUTH BE LEAN Correspondence · 19 Mar 2026
  • AS APPROVED REGULATIONS COMPLIANCE REPORT - 2 BED MID FLOOR BE LEAN Correspondence · 19 Mar 2026
  • AS APPROVED REGULATIONS COMPLIANCE REPORT - 1 BED TOP FLOOR BE LEAN Correspondence · 19 Mar 2026
  • AS APPROVED REGULATIONS COMPLIANCE REPORT - 1 BED MID FLOOR BE LEAN Correspondence · 19 Mar 2026
  • APPROVED ES VOL 2 (DECEMBER 2022) - ANNEX F - GROUND CONDITIONS & CONTAMINATION - PT 1 Environmental Statement · 19 Mar 2026
  • APPROVED ES VOL 2 (DECEMBER 2022) - ANNEX F - GROUND CONDITIONS & CONTAMINATION - PT 2 Environmental Statement · 19 Mar 2026
  • APPROVED ES VOL 2 (DECEMBER 2022) - ANNEX F - GROUND CONDITIONS & CONTAMINATION - PT 3 Environmental Statement · 19 Mar 2026
  • APPROVED ES VOL 2 (DECEMBER 2022) - ANNEX F - GROUND CONDITIONS & CONTAMINATION - PT 4 Environmental Statement · 19 Mar 2026
  • APPROVED ES VOL 2 (DECEMBER 2022) - ANNEX F - GROUND CONDITIONS & CONTAMINATION - PT 5 Environmental Statement · 19 Mar 2026
  • APPROVED ES VOL 2 (DECEMBER 2022) - ANNEX F - GROUND CONDITIONS & CONTAMINATION - PT 6 Environmental Statement · 19 Mar 2026
  • APPROVED ES VOL 2 (DECEMBER 2022) - ANNEX F - GROUND CONDITIONS & CONTAMINATION - PT 7 Environmental Statement · 19 Mar 2026
  • SITE NOTICE 1 Correspondence · 13 Mar 2026
  • SITE NOTICE 2 Correspondence · 13 Mar 2026
  • SITE NOTICE 3 Correspondence · 13 Mar 2026
  • SITE NOTICE 4 Correspondence · 13 Mar 2026
  • APPROVED ENERGY STRATEGY Report · 11 Mar 2026
  • APPROVED ENERGY STRATEGY - APPENDIX A PT 3 Report · 11 Mar 2026
  • APPROVED ENERGY STRATEGY - APPENDIX A PT 1 Report · 11 Mar 2026
  • APPROVED ENERGY STRATEGY - APPENDIX A PT 4 Report · 11 Mar 2026
  • APPROVED ENERGY STRATEGY - APPENDIX A PT 2 Report · 11 Mar 2026
  • APPROVED ENERGY STRATEGY - APPENDIX C Report · 11 Mar 2026
  • APPROVED ENERGY STRATEGY - APPENDIX D Report · 11 Mar 2026
  • APPROVED ENERGY STRATEGY - APPENDIX E - HOTEL Report · 11 Mar 2026
  • APPROVED ENERGY STRATEGY - APPENDIX E - RESIDENTIAL Report · 11 Mar 2026
  • APPROVED ENERGY STRATEGY - APPENDIX F Report · 11 Mar 2026
  • APPROVED ENERGY STRATEGY - APPENDIX G Report · 11 Mar 2026
  • APPROVED ENERGY STRATEGY - APPENDIX H Report · 11 Mar 2026
  • GLA MECHANICAL PLANTROOM CONNECTIONS LAYOUT Current Plan · 11 Mar 2026
  • GATEWAY 1 FIRE STATEMENT FORM Report · 11 Mar 2026
  • APPROVED STAGE 3 FIRE STRATEGY Report · 11 Mar 2026
  • CIRCULAR ECONOMY STATEMENT Report · 11 Mar 2026
  • APPROVED CYCLE PARKING TECHNICAL NOTE Correspondence · 11 Mar 2026
  • APPROVED VIABILITY ASSESSMENT Report · 11 Mar 2026
  • EARLY STAGE OVERHEATING RISK TOOL Report · 11 Mar 2026
  • APPROVED ES ADDENDUM VOL 1 - NON-TECHNICAL SUMMARY (MARCH 2024) Environmental Statement · 11 Mar 2026
  • APPROVED ES ADDENDUM (SEPTEMBER 2023) Environmental Statement · 11 Mar 2026
  • APPROVED ES ADDENDUM (DECEMBER 2023) Environmental Statement · 11 Mar 2026
  • APPROVED HEALTH IMPACT ASSESSMENT Report · 11 Mar 2026
  • INTERNAL DAYLIGHT SUNLIGHT AND OVERSHADOWING REPORT - 24 JULY 2023 Daylight & Sunlight · 11 Mar 2026
  • APPROVED LANDSCAPE AND PLAY STRATEGY Report · 11 Mar 2026
  • FORMER APPLICATION VIABILITY SUMMARY LETTER DATED 18 JUNE 2024 Report · 11 Mar 2026
  • FORMER APPLICATION VIABILITY SUMMARY LETTER DATED 20 NOVEMBER 2023 Report · 11 Mar 2026
  • POST EXCAVATION ASSESSMENT AND UPDATED PROJECT DESIGN Report · 11 Mar 2026
  • APPROVED ES VOL 2 - MAIN REPORT (DECEMBER 2022) Environmental Statement · 11 Mar 2026
  • APPROVED STAGE 2 FIRE STRATEGY Report · 11 Mar 2026
  • CARBON EMISSIONS TECHNICAL NOTE Report · 11 Mar 2026
  • APPROVED THERMAL COMFORT REPORT Report · 11 Mar 2026
  • THERMAL COMFORT REPORT - DSY 1-1970063 Report · 11 Mar 2026
  • THERMAL COMFORT REPORT - DSY 2-1970064 Report · 11 Mar 2026
  • THERMAL COMFORT REPORT - DSY 3-1970065 Report · 11 Mar 2026
  • APPROVED WASTE MANAGEMENT REQUIREMENTS Report · 11 Mar 2026
  • APPROVED ES VOL 2 (DECEMBER 2022) - ANNEX A - AIR QUALITY Environmental Statement · 11 Mar 2026
  • APPROVED ES VOL 2 (DECEMBER 2022) - ANNEX B - ARCHAEOLOGY Environmental Statement · 11 Mar 2026
  • APPROVED ES VOL 2 (DECEMBER 2022) - ANNEX C - CLIMATE CHANGE Environmental Statement · 11 Mar 2026
  • APPROVED ES VOL 2 (DECEMBER 2022) - ANNEX D - DAYLIGHT, SUNLIGHT, OVERSHADOWING & SOLAR GLARE PT 1 Environmental Statement · 11 Mar 2026
  • APPROVED ES VOL 2 (DECEMBER 2022) - ANNEX D - DAYLIGHT, SUNLIGHT, OVERSHADOWING & SOLAR GLARE PT 2 Environmental Statement · 11 Mar 2026
  • APPROVED ES VOL 2 (DECEMBER 2022) - ANNEX D - DAYLIGHT, SUNLIGHT, OVERSHADOWING & SOLAR GLARE PT 3 Environmental Statement · 11 Mar 2026
  • APPROVED ES VOL 2 (DECEMBER 2022) - ANNEX D - DAYLIGHT, SUNLIGHT, OVERSHADOWING & SOLAR GLARE PT 4 Environmental Statement · 11 Mar 2026
  • APPROVED ES VOL 2 (DECEMBER 2022) - ANNEX G - NOISE & VIBRATION Environmental Statement · 11 Mar 2026
  • APPROVED ES VOL 2 (DECEMBER 2022) - ANNEX H - SOCIO- ECONOMICS Environmental Statement · 11 Mar 2026
  • APPROVED ES VOL 2 (DECEMBER 2022) - ANNEX J - TRANSPORT PT 1 Environmental Statement · 11 Mar 2026
  • APPROVED ES VOL 2 (DECEMBER 2022) - ANNEX J - TRANSPORT PT 2 Environmental Statement · 11 Mar 2026
  • APPROVED ES VOL 2 (DECEMBER 2022) - ANNEX K - WASTE Environmental Statement · 11 Mar 2026
  • APPROVED ES VOL 2 (DECEMBER 2022) - ANNEX L - WIND Environmental Statement · 11 Mar 2026
  • APPROVED DAS PART 1 Design & Access Statement · 11 Mar 2026
  • APPROVED DAS PART 2 Design & Access Statement · 11 Mar 2026
  • APPROVED DAS PART 3 Design & Access Statement · 11 Mar 2026
  • APPROVED DAS PART 4 Design & Access Statement · 11 Mar 2026
  • PIAZZA PLAY SPACE LOCATION Current Plan · 10 Mar 2026
  • EXISTING SITE PLAN Current Plan · 10 Mar 2026
  • CONSENTED SITE PLAN Current Plan · 10 Mar 2026
  • PROPOSED SITE PLAN - ROYAL MINT DEVELOPMENT Current Plan · 10 Mar 2026
  • PROPOSED SITE PLAN GROUND LEVEL - ROYAL MINT DEVELOPMENT Current Plan · 10 Mar 2026
  • PROPOSED SITE PLAN - PHASE 2B: BLOCK A Current Plan · 10 Mar 2026
  • FIRE SERVICE ACCESS PLAN - PHASE 2B: BLOCK A Current Plan · 10 Mar 2026
  • GROUND FLOOR PLAN & FIRST FLOOR PLAN Current Plan · 10 Mar 2026
  • SECOND FLOOR PLAN & THIRD FLOOR PLAN Current Plan · 10 Mar 2026
  • FOURTH FLOOR PLAN & FIFTH FLOOR PLAN Current Plan · 10 Mar 2026
  • SIXTH (TYPICAL 06-08) & NINTH FLOOR PLAN Current Plan · 10 Mar 2026
  • TENTH (TYPICAL 10-12) & THIRTEENTH FLOOR PLAN Current Plan · 10 Mar 2026
  • FOURTEENTH FLOOR PLAN & ROOF FLOOR PLAN Current Plan · 10 Mar 2026
  • ELEVATIONS Current Plan · 10 Mar 2026
  • SECTIONS Current Plan · 10 Mar 2026
  • SECTION EE Current Plan · 10 Mar 2026
  • PART 1 Design & Access Statement · 27 Feb 2026
  • PART 2 Design & Access Statement · 27 Feb 2026
  • PART 3 Design & Access Statement · 27 Feb 2026
  • PART 4 Design & Access Statement · 27 Feb 2026
  • PART 5 Design & Access Statement · 27 Feb 2026
  • SIXTH (TYPICAL 06-08) & NINTH FLOOR PLAN Current Plan · 02 Jan 2026
  • TENTH (TYPICAL 10-12) & THIRTEENTH FLOOR PLAN Current Plan · 02 Jan 2026
  • FOURTEENTH FLOOR PLAN & ROOF FLOOR PLAN Current Plan · 02 Jan 2026
  • ES ADDENDUM VOL 1 - NON- TECHNICAL SUMMARY (DECEMBER 2025) Environmental Statement · 02 Jan 2026
  • ES ADDENDUM (DECEMBER 2025) Environmental Statement · 02 Jan 2026
  • DRAWING LIST Current Plan · 02 Jan 2026
  • PROPOSED SITE PLAN GROUND LEVEL ROYAL MINT DEVELOPMENT Current Plan · 02 Jan 2026
  • FIRE SERVICE ACCESS PLAN PHASE 2B: BLOCK A Current Plan · 02 Jan 2026
  • EXISTING SITE PLAN ROYAL MINT DEVELOPMENT Current Plan · 02 Jan 2026
  • CONSENTED SITE PLAN ROYAL MINT DEVELOPMENT Current Plan · 02 Jan 2026
  • PROPOSED SITE PLAN ROYAL MINT DEVELOPMENT Current Plan · 02 Jan 2026
  • PROPOSED SITE PLAN PHASE 2B: BLOCK A Current Plan · 02 Jan 2026
  • ELEVATIONS Current Plan · 02 Jan 2026
  • SECTIONS Current Plan · 02 Jan 2026
  • SECTIONS Current Plan · 02 Jan 2026
  • GROUND FLOOR PLAN & FIRST FLOOR PLAN Current Plan · 02 Jan 2026
  • SECOND FLOOR PLAN & THIRD FLOOR PLAN Current Plan · 02 Jan 2026
  • FOURTH FLOOR PLAN & FIFTH FLOOR PLAN Current Plan · 02 Jan 2026
  • ES ADDENDUM (DECEMBER 2025) - ANNEX A - DAYLIGHT, SUNLIGHT, OVERSHADOWING & SOLAR GLARE Environmental Statement · 02 Jan 2026
  • ES ADDENDUM (DECEMBER 2025) - ANNEX B - TOWNSCAPE, HERITAGE & VISUAL IMPACT ASSESSMENT Environmental Statement · 02 Jan 2026
  • ES ADDENDUM (DECEMBER 2025) ANNEX C - WIND Environmental Statement · 02 Jan 2026
  • APPROVED DRAWING PACK - AS APPROVED BY PLANNING PERMISSION PA 22 01284 - PART 1 Current Plan · 02 Jan 2026
  • APPROVED DRAWING PACK - AS APPROVED BY PLANNING PERMISSION PA 22 01284 - PART 2 Current Plan · 02 Jan 2026
  • APPROVED DRAWING PACK - AS APPROVED BY PLANNING PERMISSION PA 22 01284 - PART 3 Current Plan · 02 Jan 2026
  • LANDSCAPE STRATEGY REPORT Report · 02 Jan 2026
  • FINANCIAL VIABILITY REVIEW LETTER DATED: 11.12.25 Report · 02 Jan 2026

Trade members open them from here.

Open the documents

What happens while it is decided

This application is with Tower Hamlets for determination, against a statutory target of eight weeks. Over the last year Tower Hamlets decided amendment applications in a median of 45 days. More in our guide to how long planning decisions take.

About amendment applications

An amendment application makes limited changes to a permission that already exists; anything beyond modest adjustment needs a fresh application. More in our guide to planning application types.

Nearby applications

Within 500 metres

In Tower Hamlets

  • PA/26/00532/S Granted

    Land Comprising Harriott House, Apsley House, Pattison House, The Redcoat Centre & Redcoat Community Centre, London, E1

    Application for Non-Material amendment to planning permission ref: PA/24/00368, dated 26/06/2025. Non Material amendments Sought: Several technical amendments to ensure that the consented scheme achieves full compliance with current Building Regulations, British Standards, and fire safety requirements.

    15 Apr 2026 Amendments
  • PA/26/00838/NC Granted

    Tower Wharf, Tower of London and Arches beneath Tower Bridge, Tower Bridge Approach, London, EC3N 4AB

    Application for Non-Material amendment to planning permission ref: PA/25/00620, Dated 30/06/2025. Non Material amendment(s) Sought: Reconfiguration of Reveller entrance doors Alterations to doors within Moat Arches Increase in ASHP enclosure footprint

    12 May 2026 Amendments
  • PA/26/00812/S Granted

    Pavement in front of 197 to 337 Whitechapel Road, Whitechapel Road, London, E1

    Application for non-material amendment of Planning permission Ref: PA/24/01403, Dated 07/02/2025 Non Material Amendment(s) Sought: Removal of Bulkhead: The overhead bulkhead as been omitted in favour of demountable components. A fall to the roof tarp will be formed through the installation of a 'pitch former' fixed to the top bars.

    7 May 2026 Amendments
  • PA/26/00935/S Granted

    Wood Wharf RM01A (Development Plots A1, A4 and B3) Wood Wharf, Prestons Road, London E14

    Application for Non-Material amendment to planning permission ref: PA/16/00772, Dated 16/06/2026. Non Material amendment(s) Sought: The repositioning of the fence line at One Park Drive (Plot A1) Removal of Condition 3 to the RMA 01A

    28 May 2026 Amendments
  • PA/26/00734/S Granted

    Former News International Site, Buildings H & J, London Dock, 1 Virginia Street, London E98 1XY

    Application for Non-Material Amendment to planning permission ref: PA/23/02079, Dated 26/06/2024. Non-Material Amendment(s) Sought: Minor internal and external modifications to Building H resulting from a new core configuration and the optimisation of internal layouts

    24 Apr 2026 Amendments