Land To The West Of Romsey Road Winchester Road Goodworth Clatford Andover Hampshire SP11 7HP

Awaiting decision Test Valley 25/00799/FULLN

Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.

Proposal

Installation of substation comprising of customer and DNO compound and associated infrastructure, POC mast, new access off Romsey Road (A3057), underground cable between the substation and adjacent solar farm, septic tank, and landscaping

As published by the council, reference 25/00799/FULLN

Application record

Reference
25/00799/FULLN
Status
Current
Received
4 Apr 2025
Validated
10 Sep 2026
Ward
ANNA
Parish
GOODWORTH CLATFORD
Postcode
SP11 7HP

Timeline

Dates from the published record

  1. 4 Apr 2025

    Received by Test Valley

  2. 28 Jul 2026

    Added to PlanIndex

  3. 10 Sep 2026

    Validated

    Checked as complete and ready for consideration.

  4. Decision

    Awaiting decision

    Decision expected by 5 November 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.

    Test Valley took a median of 51 days over the applications it decided in the last year.

Who's behind it

Company information only, from the register and Companies House

Dalcour Maclaren Ltd Agent, registered in Bicester

Active · incorporated 2003 · Bicester

417 applications on PlanIndex · across 87 councils · 66% granted

Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.

See their track record

Wherwell Solar Limited Applicant, registered in London

Active · incorporated 2021 · London

1 application on PlanIndex

Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.

See their track record

Documents

Plans, drawings, consultee responses and the officer's report

49 documents on file for this application

  • LEAD FLOOD AUTHORITY (HCC) Consultation Responses · 17 Oct 2026
  • LANDSCAPE (TVBC) Consultation Responses · 08 Oct 2026
  • TREES (TVBC) Consultation Responses · 02 Oct 2026
  • ENVIRONMENT AGENCY Consultation Responses · 30 Sep 2026
  • MR CHRISTOPHER LOCKHART-MUMMERY(FULL) Public Comments · 22 Sep 2026
  • ARCHAEOLOGY - WILTSHIRE COUNCIL Consultation Responses · 18 Sep 2026
  • REVISED SURFACE WATER DRAINAGE STRATEGY & FLOOD RISK ASSESSMENT Supporting Information · 10 Sep 2026
  • REVISED PROPOSED SITE LAYOUT Drawing · 10 Sep 2026
  • REVISED LOCATION PLAN Drawing · 10 Sep 2026
  • REVISED BIODIVERSITY NET GAIN ASSESSMENT V7 Supporting Information · 10 Sep 2026
  • REVISED ARBORICULTURAL SURVEY TREE CONSTRAINTS PLAN Drawing · 10 Sep 2026
  • REVISED BNG STATUTORY METRIC Supporting Information · 10 Sep 2026
  • REVISED ARBORICULTURAL SURVEY REV 3 Supporting Information · 10 Sep 2026
  • REVISED TRANSPORT NOTE Supporting Information · 10 Sep 2026
  • REVISED EXISTING SITE LAYOUT Drawing · 10 Sep 2026
  • REVISED LANDSCAPE STRATEGY PLAN Drawing · 10 Sep 2026
  • REVISED VISIBILITY SPLAY SITE ACCESS Drawing · 10 Sep 2026
  • REVISED APPLICATION FORM Supporting Information · 10 Sep 2026
  • REVISED PLANNING STATEMENT Supporting Information · 10 Sep 2026
  • REVISED TREE PROTECTION PLAN Drawing · 10 Sep 2026
  • REVISED ECOLOGICAL IMPACT ASSESSMENT VERSION 3 Supporting Information · 10 Sep 2026
  • REVISED LANDSCAPE AND VISUAL IMPACT ASSESSMENT Supporting Information · 10 Sep 2026
  • REVISED LANDSCAPE AND VISUAL IMPACT ASSESSMENT Supporting Information · 10 Sep 2026
  • REVISED LANDSCAPE AND VISUAL IMPACT ASSESSMENT Supporting Information · 10 Sep 2026
  • REVISED LANDSCAPE AND VISUAL IMPACT ASSESSMENT Supporting Information · 10 Sep 2026
  • LEAD FLOOD AUTHORITY Consultation Responses · 14 Oct 2025
  • MR CHRISTOPHER LOCKHART-MUMMERY(FULL) Public Comments · 25 Sep 2025
  • ADDITIONAL - ADDENDUM TO SURFACE WATER DRAINAGE STRATEGY & FLOOD RISK ASSESSMENT Supporting Information · 04 Sep 2025
  • GOODWORTH CLATFORD PARISH COUNCIL Consultation Responses · 26 Aug 2025
  • ECOLOGY (TVBC) Consultation Responses · 20 Aug 2025
  • TREES (TVBC) Consultation Responses · 07 Aug 2025
  • ARCHAEOLOGY (HCC) Consultation Responses · 06 Aug 2025
  • FLOOD WATER MANAGEMENT (HCC) Consultation Responses · 31 Jul 2025
  • FLOOD WATER MANAGEMENT (HCC) Consultation Responses · 31 Jul 2025
  • REVISED ARCHAEOLOGICAL DESK-BASED ASSESSMENT Supporting Information · 30 Jul 2025
  • WHERWELL PARISH COUNCIL Consultation Responses · 24 Jul 2025
  • _ ALISON UWINS(FULL) Public Comments · 14 Jul 2025
  • ECOLOGY (TVBC) Consultation Responses · 16 Jun 2025
  • GOODWORTH CLATFORD PARISH COUNCIL Consultation Responses · 11 Jun 2025
  • LANDSCAPE (TVBC) Consultation Responses · 10 Jun 2025
  • ENVIRONMENTAL PROTECTION Consultation Responses · 06 Jun 2025
  • FLOOD WATER MANAGEMENT (HCC) Consultation Responses · 06 Jun 2025
  • HIGHWAYS (HCC) Consultation Responses · 28 May 2025
  • TREES (TVBC) Consultation Responses · 27 May 2025
  • ARCHAEOLOGY (HCC) Consultation Responses · 20 May 2025
  • AMENDED PROPOSAL Supporting Information · 15 May 2025
  • PROPOSED ELEVATIONS & LAYOUT Drawing · 14 May 2025
  • PROPOSED ELEVATIONS & FLOOR PLANS - SWITCH ROOM Drawing · 14 May 2025
  • PROPOSED ELEVATIONS & FLOOR PLANS - CONTOL ROOM Drawing · 14 May 2025

Watch members (£5 a month) open the document list from here.

Open the documents

What happens while it is decided

This application is with Test Valley for determination, against a statutory target of eight weeks. Over the last year Test Valley's median decision took 51 days. More in our guide to how long planning decisions take.

About this record

The published feed does not state which type of application this is; the register entry on Test Valley's portal will say. Our guide explains the common types.