Planning application
S.26/0700/DISCON
Symmetry Park Bath Road Haresfield Stonehouse Gloucestershire
Proposal
Discharge of condition 8 (detailed drainage maintenance and management plan) from S.25/1980/REM.
As published by the council, reference S.26/0700/DISCON
Timeline
Dates from the published record
-
21 Apr 2026
Received by Stroud
-
30 Apr 2026
Decision issued: Permission
-
27 Jul 2026
Added to PlanIndex
After the decision
The process from here
The council has decided this application; the published outcome sits in the record above and the decision notice on the council portal carries the detail, including any conditions.
If permission was granted, work must normally begin within three years of the decision. If it was refused, the applicant can appeal within the statutory time limit or submit a revised scheme.
About conditions applications
How this application type works
This type of application deals with conditions attached to an existing permission, either by supplying the details a condition requires, called discharging it, or by asking to vary or remove one. It does not reopen the principle of the permission itself. Building often cannot lawfully start, or continue past a set stage, until the named conditions are discharged.
Nearby applications
Within 500 metres
-
S.26/0825/VAR Decided
Symmetry Park Bath Road Haresfield Stonehouse Gloucestershire
Variation of conditions 1, 3, 4, 5, 6, 7 & 8 from S.25/1980/REM (Approval of the reserved matters of appearance, layout, scale and landscaping for the erection of a B8 (storage & distribution) warehouse with ancillary office accommodation, vehicle parking and associated works, pursuant to condition 34 of outline consent reference S.25/0221/VAR).
-
S.26/0290/DISCON Decided
Symmetry Park Bath Road Haresfield Stonehouse Gloucestershire
Discharge of planning conditions 47 (Site Waste Management Plan), 49 (Drainage Construction Controls), 52 (Noise Impact Assessment), 55 (Construction Management Plan) & 63 (Remediation Strategy) from planning permission S.25/0221/VAR
-
S.26/0874/MINAM Granted
Symmetry Park Bath Road Haresfield Stonehouse Gloucestershire
Non-material amendment to S.25/0221/VAR - amendment to Condition 54 part d (highway works).
-
S.26/0556/DISCON Decided
Symmetry Park Bath Road Haresfield Stonehouse Gloucestershire
Discharge of condition 59 (resurvey for badgers) from S.25/0221/VAR.
-
S.26/0555/MINAM Granted
Symmetry Park Bath Road Haresfield Stonehouse Gloucestershire
Non-material amendment to Condition 68 to refer to amended Sustainability Statement from S.25/0221/VAR
-
S.26/0645/MINAM Granted
Gloucester 12 Halpern Way Haresfield Gloucestershire GL10 3WT
Non-material amendment to S.24/2201/FUL - inclusion of a phasing plan to approved drawing list.
Other conditions applications
In Stroud
-
S.26/1021/DISCON Decided
The White House Cam Dursley Gloucestershire GL11 5JA
Discharge of condition 3 (roof light) from S.26/0203/LBC.
-
S.26/1133/DISCON Decided
Workshop At Home Farm Park Lane Stancombe Dursley Gloucestershire GL11 6AT
Discharge of condition 4 (pre-commencement contaminated land) from S.26/0268/VAR.
-
S.26/0970/DISCON Split decision
Former Cotswold Indoor Bowls Club Merrywalks Stroud Gloucestershire
Discharge of conditions 3 (PRE-COM Soft & Hard Landscaping), 4 (PRE-COM site levels), 6 (PRE-COM Details of windows/door openings), 7 (PRE-COM Construction Management Plan), 8 (PRE-COM Pedestrians), 10 (PRE-COM Surface Water Drainage System), 11 (Pre-Occ Flood Evacuation Plan), 12 (PRE-OCC details of plant & machinery) & 16 (Contamination 1) from S.23/0402/FUL.
-
S.26/0849/DISCON Refused
Land At Colethrop Farm Bath Road Hardwicke Gloucester Gloucestershire
Discharge of condition 12 (contaminated land) from S.15/1498/VAR for parcels R2, R6, R8 and R10b only
-
S.25/1588/DISCON Decided
Land At M5 Junction 13 West Of Stonehouse Eastington Gloucestershire
Discharge of condition 8 (ground and floor levels), 17 (archaeology), 18 (detailed drainage strategy), 19 (SuDS), 21 (CEMP), 22 (landscape and habitat management plan), 23 (ecological design strategy), 24 (arboricultural protection method statement), 26 (tree and hedgerow retention method statement), 27 (external lighting assessment), 36 (construction method statement and construction traffic management plan), 44 (cycle parking), 46 (construction noise management plan) and 53 (employment and skills plan) from S.19/1418/OUT.