Skip to content
PlanIndex Get alerts
Menu

Planning application

S.26/0608/DISCON

Five Valleys Shopping Centre King Street Stroud Gloucestershire GL5 3DA

Decided Stroud Discharge of Condition

Proposal

Discharge of condition 11 (Rodborough Common SAC) from S.24/0702/VAR.

As published by the council, reference S.26/0608/DISCON

Timeline

Dates from the published record

  1. 31 Mar 2026

    Received by Stroud

  2. 29 May 2026

    Decision issued: Permission

  3. 27 Jul 2026

    Added to PlanIndex

After the decision

The process from here

The council has decided this application; the published outcome sits in the record above and the decision notice on the council portal carries the detail, including any conditions.

If permission was granted, work must normally begin within three years of the decision. If it was refused, the applicant can appeal within the statutory time limit or submit a revised scheme.

About conditions applications

How this application type works

This type of application deals with conditions attached to an existing permission, either by supplying the details a condition requires, called discharging it, or by asking to vary or remove one. It does not reopen the principle of the permission itself. Building often cannot lawfully start, or continue past a set stage, until the named conditions are discharged.

More on conditions applications in our guide

Nearby applications

Within 500 metres

  • S.25/2424/FUL Decided

    King Street And High Street Stroud Gloucestershire GL5 3BX

    Erection of two event billing noticeboards.

    18 Dec 2025 32m away Full applications
  • S.25/2425/ADV Granted

    King Street And High Street Stroud Gloucestershire GL5 3BX

    Erection of two event billing noticeboards.

    18 Dec 2025 33m away Advertising
  • S.26/1130/FUL Awaiting decision

    16 King Street Stroud Gloucestershire GL5 3DQ

    Installation of combined defibrillator and bleed kit cabinet to external wall

    30 Jun 2026 42m away Full applications
  • S.26/0403/FUL Decided

    4 King Street Stroud Gloucestershire GL5 3DS

    Change of use of the upper floors (offices Class E) to 3 small HMO flats (class C4)& associated bin & bike storage.

    9 Mar 2026 61m away Full applications
  • 2014/1092/WIG Decided

    Sorrento Russell Street Stroud Gloucestershire GL5 3AJ

    Conversion of existing adjoining flat into additional floor space for the restaurant together with providing toilets to be used in connection with the restaurant.

    6 May 2014 85m away
  • S.26/0220/FUL Decided

    8A George Street Stroud Gloucestershire GL5 3DX

    Single storey extension within rear courtyard of commercial premises to replace courtyard & polycarbonate roof.

    9 Feb 2026 93m away Full applications

In Stroud

  • The White House Cam Dursley Gloucestershire GL11 5JA

    Discharge of condition 3 (roof light) from S.26/0203/LBC.

    5 Jun 2026 Conditions
  • Workshop At Home Farm Park Lane Stancombe Dursley Gloucestershire GL11 6AT

    Discharge of condition 4 (pre-commencement contaminated land) from S.26/0268/VAR.

    30 Jun 2026 Conditions
  • S.26/0970/DISCON Split decision

    Former Cotswold Indoor Bowls Club Merrywalks Stroud Gloucestershire

    Discharge of conditions 3 (PRE-COM Soft & Hard Landscaping), 4 (PRE-COM site levels), 6 (PRE-COM Details of windows/door openings), 7 (PRE-COM Construction Management Plan), 8 (PRE-COM Pedestrians), 10 (PRE-COM Surface Water Drainage System), 11 (Pre-Occ Flood Evacuation Plan), 12 (PRE-OCC details of plant & machinery) & 16 (Contamination 1) from S.23/0402/FUL.

    3 Jun 2026 Conditions
  • Land At Colethrop Farm Bath Road Hardwicke Gloucester Gloucestershire

    Discharge of condition 12 (contaminated land) from S.15/1498/VAR for parcels R2, R6, R8 and R10b only

    13 May 2026 Conditions
  • Land At M5 Junction 13 West Of Stonehouse Eastington Gloucestershire

    Discharge of condition 8 (ground and floor levels), 17 (archaeology), 18 (detailed drainage strategy), 19 (SuDS), 21 (CEMP), 22 (landscape and habitat management plan), 23 (ecological design strategy), 24 (arboricultural protection method statement), 26 (tree and hedgerow retention method statement), 27 (external lighting assessment), 36 (construction method statement and construction traffic management plan), 44 (cycle parking), 46 (construction noise management plan) and 53 (employment and skills plan) from S.19/1418/OUT.

    20 Aug 2025 Conditions