Proposal
Phased approach to discharging the Statutory Biodiversity Gain Condition from the application S.24/2201/FUL.
As published by the council, reference S.26/0340/BGPCON
Timeline
Dates from the published record
-
12 Feb 2026
Received by Stroud
-
27 Feb 2026
Validated
Checked as complete and ready for consideration.
-
5 May 2026
Decision issued: Withdrawn
-
27 Jul 2026
Added to PlanIndex
What withdrawal means
The process from here
The applicant withdrew this application before the council decided it, so it carries no planning weight and no fee refund is automatic. Withdrawal often follows officer feedback that a refusal was likely.
The applicant is free to submit a revised application at any time, and many withdrawn schemes return in amended form, so the site is worth watching if the proposal affected you.
About conditions applications
How this application type works
This type of application deals with conditions attached to an existing permission, either by supplying the details a condition requires, called discharging it, or by asking to vary or remove one. It does not reopen the principle of the permission itself. Building often cannot lawfully start, or continue past a set stage, until the named conditions are discharged.
Nearby applications
Within 500 metres
-
S.26/0645/MINAM Granted
Gloucester 12 Halpern Way Haresfield Gloucestershire GL10 3WT
Non-material amendment to S.24/2201/FUL - inclusion of a phasing plan to approved drawing list.
-
S.26/0969/BGPCON Awaiting decision
Gloucester 12 Halpern Way Haresfield Gloucestershire GL10 3WT
Phased discharge of the Biodiversity Gain Condition from S.26/0645/MINAM.
-
S.26/0556/DISCON Decided
Symmetry Park Bath Road Haresfield Stonehouse Gloucestershire
Discharge of condition 59 (resurvey for badgers) from S.25/0221/VAR.
-
S.26/0825/VAR Decided
Symmetry Park Bath Road Haresfield Stonehouse Gloucestershire
Variation of conditions 1, 3, 4, 5, 6, 7 & 8 from S.25/1980/REM (Approval of the reserved matters of appearance, layout, scale and landscaping for the erection of a B8 (storage & distribution) warehouse with ancillary office accommodation, vehicle parking and associated works, pursuant to condition 34 of outline consent reference S.25/0221/VAR).
-
S.26/0290/DISCON Decided
Symmetry Park Bath Road Haresfield Stonehouse Gloucestershire
Discharge of planning conditions 47 (Site Waste Management Plan), 49 (Drainage Construction Controls), 52 (Noise Impact Assessment), 55 (Construction Management Plan) & 63 (Remediation Strategy) from planning permission S.25/0221/VAR
-
S.26/0700/DISCON Decided
Symmetry Park Bath Road Haresfield Stonehouse Gloucestershire
Discharge of condition 8 (detailed drainage maintenance and management plan) from S.25/1980/REM.
Other conditions applications
In Stroud
-
S.26/1021/DISCON Decided
The White House Cam Dursley Gloucestershire GL11 5JA
Discharge of condition 3 (roof light) from S.26/0203/LBC.
-
S.26/1133/DISCON Decided
Workshop At Home Farm Park Lane Stancombe Dursley Gloucestershire GL11 6AT
Discharge of condition 4 (pre-commencement contaminated land) from S.26/0268/VAR.
-
S.26/0970/DISCON Split decision
Former Cotswold Indoor Bowls Club Merrywalks Stroud Gloucestershire
Discharge of conditions 3 (PRE-COM Soft & Hard Landscaping), 4 (PRE-COM site levels), 6 (PRE-COM Details of windows/door openings), 7 (PRE-COM Construction Management Plan), 8 (PRE-COM Pedestrians), 10 (PRE-COM Surface Water Drainage System), 11 (Pre-Occ Flood Evacuation Plan), 12 (PRE-OCC details of plant & machinery) & 16 (Contamination 1) from S.23/0402/FUL.
-
S.26/0849/DISCON Refused
Land At Colethrop Farm Bath Road Hardwicke Gloucester Gloucestershire
Discharge of condition 12 (contaminated land) from S.15/1498/VAR for parcels R2, R6, R8 and R10b only
-
S.25/1588/DISCON Decided
Land At M5 Junction 13 West Of Stonehouse Eastington Gloucestershire
Discharge of condition 8 (ground and floor levels), 17 (archaeology), 18 (detailed drainage strategy), 19 (SuDS), 21 (CEMP), 22 (landscape and habitat management plan), 23 (ecological design strategy), 24 (arboricultural protection method statement), 26 (tree and hedgerow retention method statement), 27 (external lighting assessment), 36 (construction method statement and construction traffic management plan), 44 (cycle parking), 46 (construction noise management plan) and 53 (employment and skills plan) from S.19/1418/OUT.