Land Northeast Of Bredbury Industrial Estate Off Bredbury Park Way / Ashton Road (A6017), Bredbury, Stockport SK6 2SB; Referred To As Bredbury Gateway

Awaiting decision Stockport DC/097903 Outline Application

Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.

Proposal

Part A: Detailed planning permission for construction, engineering and change of use including; realignment of Bredbury Park Way and relocation of its junction with Ashton Road, means of access and related transportation infrastructure; remodelling/regrading of land, related engineering and infrastructure works; landscaping, tree planting and related works; green components of wider SUDS drainage strategy; main means of enclosure/security; general enabling works and ancillary development; and change of use Finland Park Farm (Uses Classes E(b), F1 or F2); AND, Part B: Outline planning permission with all matters reserved except means of access for commercial / industrial / warehousing development providing up to 70,310 sqm of floorspace (including ancillary office accommodation) in Use Classes E(g)(iii), B2 and B8; along with associated infrastructure (including means of plot / unit enclosure, internal access and service roads, parking, servicing, footpaths, landscaping, built infrastructure components of wider SUDS drainage strategy and ancillary works)

As published by the council, reference DC/097903

Application record

Reference
DC/097903
Type
Outline Application
Status
Registered
Received
19 Dec 2025
Validated
2 Mar 2026
Ward
Bredbury & Woodley (Wern)
Postcode
SK6 2SB

Timeline

Dates from the published record

  1. 19 Dec 2025

    Received by Stockport

  2. 2 Mar 2026

    Validated

    Checked as complete and ready for consideration.

  3. 21 Jul 2026

    Added to PlanIndex

  4. Decision

    Awaiting decision

    Decision expected by 27 April 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.

    Stockport took a median of 51 days over the applications it decided in the last year.

Who's behind it

Company information only, from the register and Companies House

Plan Red Ltd Agent, registered in Manchester

Active · incorporated 2021 · Manchester

34 applications on PlanIndex · across 8 councils · 80% granted

Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.

See their track record

Documents

Plans, drawings, consultee responses and the officer's report

213 documents on file for this application

  • NATIONAL HIGHWAYS Consultee Comment · 28 Aug 2026
  • DRAINAGE_STRATEGY-2_OF_2_ Report · 13 Aug 2026
  • DRAINAGE_STRATEGY-1_OF_2_ Report · 13 Aug 2026
  • GMEU Consultee Comment · 06 Aug 2026
  • LLFA RESPONSE - REV A. Report · 28 Jul 2026
  • EXTERNAL LIGHTING LAYOUT 2OF2 (C5).PDF Plan · 28 Jul 2026
  • EXTERNAL LIGHTING LAYOUT 1OF2 (C5).PDF Plan · 28 Jul 2026
  • DRAINAGE STRATEGY-2 OF 2 P06.PDF Plan · 28 Jul 2026
  • DRAINAGE STRATEGY-1 OF 2 P06.PDF Plan · 28 Jul 2026
  • CULTURAL HERITAGE AND ARCHAEOLOGY TECHNICAL NOTE 10861.005.PDF Report · 28 Jul 2026
  • EXTERNAL LIGHTING CALCULATION L-250011 R07 ARTECH.PDF Report · 28 Jul 2026
  • CIBSE GUIDE AGAINST DESIGN RESULTS R07 ARTECH.PDF Report · 28 Jul 2026
  • LETTER SUBMISSION RESPONSES TO SMBC. Report · 28 Jul 2026
  • 9891.02.001 BREDBURY - PWMS Report · 28 Jul 2026
  • 1244_02-005_PROPOSED SITE PLAN-P11 Plan · 28 Jul 2026
  • 9891.02.003 BREDBURY, BAT AND BIRD BOX SCHEME. Report · 28 Jul 2026
  • ENVIRONMENTAL HEALTH - AIR QUALITY Consultee Comment · 15 Jul 2026
  • ARCHAEOLOGICAL EVALUATION Report · 24 Jun 2026
  • GMAAS Consultee Comment · 24 Jun 2026
  • CONSERVATION Consultee Comment · 10 Jun 2026
  • UNITED UILITIES Consultee Comment · 01 Jun 2026
  • TRANSPORT ASSESSMENT REVIEW Report · 27 May 2026
  • NATIONAL HIGHWAYS Consultee Comment · 27 May 2026
  • TFGM Consultee Comment · 15 May 2026
  • ENVIRONMENTAL HEALTH - ENVIRONMENTAL QUALITY Consultee Comment · 30 Apr 2026
  • GMEU Consultee Comment · 24 Apr 2026
  • ECOLOGY Consultee Comment · 14 Apr 2026
  • TRANSPORT ASSESSMENT APPENDICES Report · 14 Apr 2026
  • NATIONAL HIGHWAYS Consultee Comment · 09 Apr 2026
  • GMAAS Consultee Comment · 08 Apr 2026
  • TAMESIDE GOV Consultee Comment · 08 Apr 2026
  • PLANNING POLICY (GROWTH) Consultee Comment · 08 Apr 2026
  • NATURAL ENGLAND Consultee Comment · 01 Apr 2026
  • PRESS NOTICE Notice · 01 Apr 2026
  • COAL AUTHORITY Consultee Comment · 26 Mar 2026
  • LLFA / FLOOD RISK OFFICER Consultee Comment · 26 Mar 2026
  • ENVIRONMENT AGENCY Consultee Comment · 23 Mar 2026
  • PROW Consultee Comment · 19 Mar 2026
  • BREDBURY GATEWAY FI030-006 V3 PROW STRATEGY Report · 19 Mar 2026
  • AIR QUALITY ASSESSMENT INPUT DATA Plan · 05 Mar 2026
  • SUSTAINABILITY ENERGY AND CLIMATE STATEMENT Report · 03 Mar 2026
  • SUSTAINABILITY, ENERGY AND CLIMATE CHANGE REPORT Report · 02 Mar 2026
  • BIODIVERSITY NET GAIN SUPPORT DETAILS Report · 02 Mar 2026
  • SEQUENTIAL TEST NOTE Report · 02 Mar 2026
  • PROPOSED BOUNDARY FENCING Plan · 02 Mar 2026
  • PROPOSED SITE SECTIONS Plan · 02 Mar 2026
  • FINLAND PARK FARM BUNGALOW EXISTING PLANS AND ELEVATIONS Plan · 24 Feb 2026
  • FINLAND PARK FARM STABLES EXISTING ELEVATIONS Plan · 24 Feb 2026
  • FINLAND PARK FARM EXISTING SITE PLAN AND ELEVATION Plan · 24 Feb 2026
  • PROPOSED ACCESS AND ASHTON ROAD SIGNALISATION Plan · 24 Feb 2026
  • PROPOSED ACCESS AND ASHTON ROAD SIGNALISATION Plan · 24 Feb 2026
  • APPLICATIONFORMREDACTED ApplicationNoPersonalData · 19 Dec 2025
  • ES_VOLUME 3_FIGURE 9.17_POND LOCATION PLAN Report · 19 Dec 2025
  • ES_VOLUME 3_FIGURE 9.18_ARBORICULTURAL SITE OVERVIEW PLAN Plan · 19 Dec 2025
  • ES_VOLUME 3_FIGURE 9.19_TREE CONSTRAINTS PLAN Plan · 19 Dec 2025
  • ES_VOLUME 3_FIGURE 9.20_TREE WORKS PLAN (KNOWN EFFECTS) Plan · 19 Dec 2025
  • ES_VOLUME 3_FIGURE 9.21_ARBORICULTURAL METHOD STATEMENT HEADS OF TERMS PLAN (KNO Plan · 19 Dec 2025
  • ES_VOLUME 3_FIGURE 9.22_BASELINE UK HABITATS Plan · 19 Dec 2025
  • ES_VOLUME 3_FIGURE 9.23_BASELINE CONDITION AND SIGNIFICANCE Plan · 19 Dec 2025
  • ES_VOLUME 3_FIGURE 9.24_PROPOSED UK HABITATS Plan · 19 Dec 2025
  • ES_VOLUME 3_FIGURE 9.25_PROPOSED HABITAT CONDITION - STRATEGIC SIGNIFICANCE Plan · 19 Dec 2025
  • ES_VOLUME 3_FIGURE 9.26_HABITAT IMPACT Plan · 19 Dec 2025
  • ES_VOLUME 3_FIGURE 15.1_LOCATION OF KNOWN HERITAGE ASSETS Plan · 19 Dec 2025
  • ES_VOLUME 3_FIGURE 15.2_ORDNANCE SURVEY MAP 1872 Plan · 19 Dec 2025
  • ES_VOLUME 3_FIGURE 15.3_TERRAIN PLAN Report · 19 Dec 2025
  • ES_VOLUME 3_FIGURE 15.4_HISTORIC LANDSCAPE CHARACTERISATION Plan · 19 Dec 2025
  • ES_VOLUME 3_FIGURE 15.5_IMPORTANT HEDGEROW LOCATION PLAN Plan · 19 Dec 2025
  • ES_VOLUME 3_FIGURE 15.6_BEDROCK GEOLOGY Plan · 19 Dec 2025
  • ES_VOLUME 3_FIGURE 15.7_SUPERFICIAL GEOLOGY Plan · 19 Dec 2025
  • ES_VOLUME 3_FIGURES 12.1 TO 12.4_NOISE AND VIBRATION Plan · 19 Dec 2025
  • ES VOLUME 3_DRAWING 10.1 SENSITIVE RECEPTOR LOCATION PLAN Plan · 19 Dec 2025
  • ES VOLUME 3_DRAWING 16.1_EXTERNAL LIGHTING LAYOUT ILLUMINANCE INFORMATION Plan · 19 Dec 2025
  • ES VOLUME 3_DRAWING 16.2_EXTERNAL LUX LIGHTING PLOT LAYOUTS Plan · 19 Dec 2025
  • ES VOLUME 3_DRAWING_DEVELOPMENT FRAMEWORK PLAN_EXISTING-P10 Plan · 19 Dec 2025
  • ES VOLUME 3_DRAWING_DEVELOPMENT FRAMEWORK PLAN_PROPOSED-P10 Plan · 19 Dec 2025
  • ES VOLUME 3_DRAWING_EXISTING SITE PLAN-P8 Plan · 19 Dec 2025
  • ES VOLUME 3_DRAWING_OUTLINE AND DETAILED PERMISSION EXTENTS-P4 Plan · 19 Dec 2025
  • ES VOLUME 3_DRAWING_P11-DEVELOPMENT STRATEGY PLAN Plan · 19 Dec 2025
  • ES VOLUME 3_DRAWING_PROPOSED CUT AND FILL Plan · 19 Dec 2025
  • ES VOLUME 3_DRAWING_PROPOSED FINISHED LEVELS 1OF2 Plan · 19 Dec 2025
  • ES VOLUME 3_DRAWING_PROPOSED FINISHED LEVELS 2OF2 Plan · 19 Dec 2025
  • ES VOLUME 3_DRAWING_PROPOSED SITE PLAN-P10 Plan · 19 Dec 2025
  • ES VOLUME 3_SITE LOCATION PLAN-REV_P7 1250 Plan · 19 Dec 2025
  • ES_VOLUME 3_DRAWING 8.1_ ILLUSTRATIVE LANDSCAPE MASTERPLAN (SITE ONLY) Report · 19 Dec 2025
  • ES_VOLUME 3_DRAWING 8.2_ILLUSTRATIVE LANDSCAPE MASTERPLAN (INCLUDING OFF SITE AR Report · 19 Dec 2025
  • ES_VOLUME 3_DRAWING 11.1_ADMS-ROADS INPUTS Plan · 19 Dec 2025
  • ES_VOLUME 3_DRAWING 11.2_MONITORING LOCATIONS Plan · 19 Dec 2025
  • ES_VOLUME 3_DRAWING 11.3_OPERATIONAL PHASE SENSITIVE RECEPTOR Plan · 19 Dec 2025
  • ES_VOLUME 3_DRAWING 11.4_WIND ROSE OF 2023 MANCHESTER AIRPORT Plan · 19 Dec 2025
  • ES_VOLUME 3_DRAWING 14-1_SURFACE WATER ENVIRONMENT BASELINE CONDITIONS_REVISION Plan · 19 Dec 2025
  • ES_VOLUME 3_DRAWING 14-2_DRAINAGE STRATEGY-1 OF 2 Plan · 19 Dec 2025
  • ES_VOLUME 3_DRAWING 14-3_DRAINAGE STRATEGY-2 OF 2 Plan · 19 Dec 2025
  • ES_VOLUME 3_DRAWING 16.1_EXTERNAL LIGHTING LAYOUT 1 OF 2 Plan · 19 Dec 2025
  • ES_VOLUME 3_DRAWING 16.1_EXTERNAL LIGHTING LAYOUT 2 OF 2 Plan · 19 Dec 2025
  • ES_VOLUME 3_FIGURE 8.1 SITE LOCATION AND LVIA STUDY AREA Plan · 19 Dec 2025
  • ES_VOLUME 3_FIGURE 8.2 ENVIRONMENTAL DESIGNATIONS Plan · 19 Dec 2025
  • ES_VOLUME 3_FIGURE 8.3 PUBLISHED LANDSCAPE CHARACTER TYPES AND AREAS Plan · 19 Dec 2025
  • ES_VOLUME 3_FIGURE 8.4 LANDSCAPE CONTEXT Plan · 19 Dec 2025
  • ES_VOLUME 3_FIGURE 8.5 TOPOGRAPHY Plan · 19 Dec 2025
  • ES_VOLUME 3_FIGURE 8.6 ZONE OF THEORETICAL VISIBILITY (BARE EARTH) Plan · 19 Dec 2025
  • ES_VOLUME 3_FIGURE 8.7 ZONE OF THEORETICAL VISIBILITY (SCREENED) AND VIEWPOINT L Plan · 19 Dec 2025
  • ES_VOLUME 3_FIGURE 8.8-8.15_VIEWPOINTS 1-6 Plan · 19 Dec 2025
  • ES_VOLUME 3_FIGURE 8.27_VERIFIED PHOTOMONTAGE VIEWPOINT 5 Plan · 19 Dec 2025
  • ES_VOLUME 3_FIGURE 8.28__VERIFIED PHOTOMONTAGE VIEWPOINT 6 Plan · 19 Dec 2025
  • ES_VOLUME 3_FIGURE 8.29_VERIFIED PHOTOMONTAGE VIEWPOINT 10 Plan · 19 Dec 2025
  • ES_VOLUME 3_FIGURE 8.30_VERIFIED PHOTOMONTAGE VIEWPOINT 14 Plan · 19 Dec 2025
  • ES_VOLUME 3_FIGURE 8.31_VERIFIED PHOTOMONTAGE VIEWPOINT 15 Plan · 19 Dec 2025
  • ES_VOLUME 3_FIGURE 9.1_PHASE 1 HABITAT SURVEY Report · 19 Dec 2025
  • ES_VOLUME 3_FIGURE 9.3_BAT TRANSECT ROUTE AND STATIC DETECTOR LOCATIONS Report · 19 Dec 2025
  • ES_VOLUME 3_FIGURE 9.4_BAT TRANSECT SURVEY RESULTS - VISIT 1 - 03-05-2023 Report · 19 Dec 2025
  • ES_VOLUME 3_FIGURE 9.5_BAT TRANSECT SURVEY RESULTS - VISIT 2 - 24-05-2023 Report · 19 Dec 2025
  • ES_VOLUME 3_FIGURE 9.6_BAT TRANSECT SURVEY RESULTS - VISIT 3 - 26-06-2023 Report · 19 Dec 2025
  • ES_VOLUME 3_FIGURE 9.7_BAT TRANSECT SURVEY RESULTS - VISIT 4 - 25-07-2023 Report · 19 Dec 2025
  • ES_VOLUME 3_FIGURE 9.8_BAT TRANSECT SURVEY RESULTS - VISIT 5 - 24-08-2023 Report · 19 Dec 2025
  • ES_VOLUME 3_FIGURE 9.9_BAT TRANSECT SURVEY RESULTS - VISIT 6 - 25-09-2023 Report · 19 Dec 2025
  • ES_VOLUME 3_FIGURE 9.10_BAT TRANSECT SURVEY RESULTS - VISIT 7 - 16-10-2023 Report · 19 Dec 2025
  • ES_VOLUME 3_FIGURE 9.11_BREEDING BIRDS SURVEY RESULTS VISIT 1- 28-04-23 Report · 19 Dec 2025
  • ES_VOLUME 3_FIGURE 9.12_BREEDING BIRDS SURVEY RESULTS VISIT 2 - 11-05-23 Report · 19 Dec 2025
  • ES_VOLUME 3_FIGURE 9.13_BREEDING BIRDS SURVEY RESULTS VISIT 3- 22-05-23 Report · 19 Dec 2025
  • ES_VOLUME 3_FIGURE 9.14_BREEDING BIRDS SURVEY RESULTS VISIT 4- 06-06-23 Report · 19 Dec 2025
  • ES_VOLUME 3_FIGURE 9.15_BREEDING BIRDS SURVEY RESULTS VISIT 5- 23-06-23 Report · 19 Dec 2025
  • ES_VOLUME 3_FIGURE 9.16_BREEDING BIRDS SURVEY RESULTS VISIT 6- 06-07-23 Report · 19 Dec 2025
  • ES_VOLUME 3_FIGURE 8.16-8.26_VIEWPOINTS 7-16 Report · 19 Dec 2025
  • ES_VOLUME 2_APPENDIX 13.1_PART D_ GEO-ENVIRONMENTAL DESK STUDY Report · 19 Dec 2025
  • ES_VOLUME 2_APPENDIX 13.1_PART J_ GEO-ENVIRONMENTAL DESK STUDY Report · 19 Dec 2025
  • ES_VOLUME 2_APPENDIX 13.1_PART I_ GEO-ENVIRONMENTAL DESK STUDY Report · 19 Dec 2025
  • ES_VOLUME 2_APPENDIX 13.1_PART F_ GEO-ENVIRONMENTAL DESK STUDY Report · 19 Dec 2025
  • ES_VOLUME 2_APPENDIX 14.1_PART A_FLOOD RISK ASSESSMENT Report · 19 Dec 2025
  • ES_VOLUME 2_APPENDIX 14.1_PART B_FLOOD RISK ASSESSMENT Report · 19 Dec 2025
  • ES_VOLUME 2_APPENDIX 13.1_PART E GEO-ENVIRONMENTAL DESK STUDY Report · 19 Dec 2025
  • ES_VOLUME 2_APPENDIX 13.1_PART G_ GEO-ENVIRONMENTAL DESK STUDY Report · 19 Dec 2025
  • ES_VOLUME 2_APPENDIX 13.1_PART C_ GEO-ENVIRONMENTAL DESK STUDY Report · 19 Dec 2025
  • ES_VOLUME 2_APPENDIX 13.1_PART H_ GEO-ENVIRONMENTAL DESK STUDY Report · 19 Dec 2025
  • ES_VOLUME 2_APPENDIX 13.1_PART B_ GEO-ENVIRONMENTAL DESK STUDY Report · 19 Dec 2025
  • ES_VOLUME 2_APPENDIX 13.1_PART A_ GEO-ENVIRONMENTAL DESK STUDY Report · 19 Dec 2025
  • ES_VOLUME 2_APPENDIX 15.1_PART A_HISTORIC ENVIRONMENT DESK BASED ASSESSMENT Report · 19 Dec 2025
  • ES_VOLUME 2_APPENDIX 13.2_MINING STABILITY REPORT INCLUDING PAST MINING RISK ASS Report · 19 Dec 2025
  • ES_VOLUME 2_APPENDIX 14.1_PART C_FLOOD RISK ASSESSMENT Report · 19 Dec 2025
  • ES_VOLUME 2_APPENDIX 16.2 - BASELINE LIGHTING SURVEY REPORT Report · 19 Dec 2025
  • ES_VOLUME 2_APPENDIX 9.8_ARBORICULTURAL IMPACT ASSESSMENT IN SUPPORT OF HYBRID P Report · 19 Dec 2025
  • ES_VOLUME 2_APPENDIX 15.1_PART B_HISTORIC ENVIRONMENT DESK BASED ASSESSMENT Report · 19 Dec 2025
  • ES_VOLUME 2_APPENDIX 9.9A_BNG STATUTORY METRIC_TEP X9891.004 (MACRO DISABLED) Report · 19 Dec 2025
  • ES_VOLUME 2_APPENDIX 17.1_ALC REPORT Report · 19 Dec 2025
  • ES_VOLUME 2_APPENDIX 9.1_ECOLOGY DESK STUDY Report · 19 Dec 2025
  • ES_VOLUME 2_APPENDIX 9.2_PHASE 1 HABITAT SURVEY AND TARGET NOTES Report · 19 Dec 2025
  • ES_VOLUME 2_APPENDIX 8.3_LANDSCAPE STRATEGY Report · 19 Dec 2025
  • ES_VOLUME 2_APPENDIX 9.4_BADGER SURVEY_REDACTED Report · 19 Dec 2025
  • ES_VOLUME 2_APPENDIX 9.9_BNG ASSESSMENT Report · 19 Dec 2025
  • ES_VOLUME 2_APPENDIX 9.3_HEDGEROW REGULATIONS ASSESSMENT Report · 19 Dec 2025
  • ES_VOLUME 2_APPENDIX 9.5_BAT SURVEY Report · 19 Dec 2025
  • ES VOLUME 2_APPENDIX 9.10_FRAMEWORK CEMP Report · 19 Dec 2025
  • ES_VOLUME 2_APPENDIX 9.7_AMPHIBIAN SURVEY Report · 19 Dec 2025
  • ES_VOLUME 2_APPENDIX 9.6_BREEDING BIRD SURVEY Report · 19 Dec 2025
  • ES_VOLUME 2_APPENDIX 12.1_MEASURED SOUND PRESSURE LEVELS Report · 19 Dec 2025
  • ES_VOLUME 2_APPENDIX 8.1_LVIA METHOD Report · 19 Dec 2025
  • ES_VOLUME 2_APPENDIX 16.3 - EXTERNAL LIGHTING STRATEGY Report · 19 Dec 2025
  • ES_VOLUME 2_APPENDIX 16.1 - BASELINE LIGHTING SURVEY MAP Report · 19 Dec 2025
  • ES_VOLUME 2_APPENDIX 1.1_EIA SCOPING OPINION Report · 19 Dec 2025
  • ES_VOLUME 2_APPENDIX 2.1_BREDBURY_AREA SCHEDULE_PROPOSED_(REV D) Report · 19 Dec 2025
  • ES_VOLUME 1_ INTRODUCTORY CHAPTERS_V16_NOV 2025 Report · 19 Dec 2025
  • ES_VOLUME 1_CHAPTER 19_MITIGATION AND MONITORING Report · 19 Dec 2025
  • ES_VOLUME 1_CHAPTER 8_LANDSCAPE AND VISUAL Report · 19 Dec 2025
  • ES_VOUME 1_ CHAPTER 7_SOCIO ECONOMICS_V4_NOV 25 Report · 19 Dec 2025
  • ES_VOLUME 1_ CHAPTER 13_GROUND CONDITIONS Report · 19 Dec 2025
  • ES_VOLUME 1_CHAPTER 9_BIODIVERSITY Report · 19 Dec 2025
  • ES_VOLUME 1_CHAPTER 10_TRAFFIC AND TRANSPORT Report · 19 Dec 2025
  • ES_VOLUME 1_CHAPTER 11_AIR QUALITY Report · 19 Dec 2025
  • ES_VOLUME 1_CHAPTER 12_NOISE AND VIBRATION Report · 19 Dec 2025
  • ES_VOLUME 1_CHAPTER 14_WATER ENVIRONMENT Report · 19 Dec 2025
  • ES_VOLUME 1_CHAPTER 15_CULTURAL HERITAGE AND ARCHAEOLOGY Report · 19 Dec 2025
  • ES_VOLUME 1_CHAPTER 16_LIGHTING Report · 19 Dec 2025
  • ES_VOLUME 1_CHAPTER 17_AGRICULTURE AND SOILS Report · 19 Dec 2025
  • ES_VOLUME 1_CHAPTER 18_CUMULATIVE EFFECTS Report · 19 Dec 2025
  • ES_VOLUME 1_CHAPTER 20_STATEMENT OF SIGNIFICANCE AND CONCLUSIONS Report · 19 Dec 2025
  • NON TECHNICAL SUMMARY_V2_NOV 2025 Report · 19 Dec 2025
  • DESIGN AND ACCESS STATEMENT _REV B Report · 19 Dec 2025
  • SOLAR PHOTOVOLTAIC GLINT AND GLARE STUDY 09.10.25 Report · 19 Dec 2025
  • BREDBURY EMPLOYMENT PARK CIS Report · 19 Dec 2025
  • BREDBURY GATEWAY EMPLOYMENT NEEDS ASSESSMENT FINAL REPORT - ICENI Report · 19 Dec 2025
  • BREDBURY GATEWAY LOGISTICS STUDY_V1_2025 - MODEL LOGIC Report · 19 Dec 2025
  • BREDBURY LOW ZERO CARBON REPORT - ALDROCK Report · 19 Dec 2025
  • BREDBURY SOCIAL VALUE EMPLOYMENT SKILLS PLAN 004 - SONAR Report · 19 Dec 2025
  • BREDBURY GATEWAY FI030-006 V2 PROW STRATERGY Superseded Document · 19 Dec 2025
  • BREDBURY GATEWAY FI030-005 V1 S106 HEADS OF TERMS Report · 19 Dec 2025
  • BREDBURY GATEWAY FI030-002 V3 GREY BELT ASSESSMENT Report · 19 Dec 2025
  • BREDBURY GATEWAY FI030-001 V12 PLANNING STATEMENT W APPENDIX Report · 19 Dec 2025
  • BREDBURY GATEWAY FI030-003 V12 DEVELPOMENT SCHEDULE Report · 19 Dec 2025
  • BREDBURY GATEWAY EMPLOYMENT REPORT JLL Report · 19 Dec 2025
  • BREDBURY GATEWAY FI030-004 V4 SUMMARY STATEMENT Report · 19 Dec 2025
  • BREDBURY GATEWAY SUSTAINABILITY CHECKLIST Report · 19 Dec 2025
  • BREDBURY GATEWAY STATEMENT OF COMMUNITY INVOLVEMENT Report · 19 Dec 2025
  • BREDBURY GATEWAY HEALTH IMPACT ASSESSMENT_ V8 Report · 19 Dec 2025
  • SITE LOCATION PLAN 1250 Plan · 19 Dec 2025
  • EXISTING SITE PLAN Plan · 19 Dec 2025
  • DEVELOPMENT FRAMEWORK PLAN_EXISTING Plan · 19 Dec 2025
  • DEVELOPMENT FRAMEWORK PLAN_PROPOSED Plan · 19 Dec 2025
  • DEVELOPMENT STRATEGY PLAN Plan · 19 Dec 2025
  • PROPOSED SITE PLAN Plan · 19 Dec 2025
  • OUTLINE AND DETAILED PERMISSION EXTENTS Plan · 19 Dec 2025
  • PROPOSED FINISHED LEVELS 1OF2 Plan · 19 Dec 2025
  • PROPOSED FINISHED LEVELS 2OF2 Plan · 19 Dec 2025
  • PROPOSED CUT AND FILL Plan · 19 Dec 2025
  • D9687.001C ILLUSTRATIVE LANDSCAPE MASTERPLAN (SITE ONLY) Report · 19 Dec 2025
  • D9697.002B ILLUSTRATIVE LANDSCAPE MASTERPLAN (INCLUDING OFF SITE AREA) Report · 19 Dec 2025
  • ES_VOLUME 2_APPENDIX 10.2 TRAVEL PLAN-FINAL Report · 19 Dec 2025
  • ES_VOLUME 2_APPENDIX 10.1 610-2025-126-01 REV 1 STAGE 1 RSA REPORT FINAL Report · 19 Dec 2025
  • ES_VOLUME 2_APPENDIX 10.1 P24009-005F PROPOSED ACCESS Report · 19 Dec 2025
  • ES_VOLUME 2_APPENDIX 10.1 P24009-006 ILLUSTRATIVE CYCLE ACCESS Report · 19 Dec 2025
  • ES_VOLUME 2_APPENDIX 10.1 TRANSPORT ASSESSMENT-FINAL-TEXT Report · 19 Dec 2025
  • BREDBURY GATEWAY COVERING LETTER Report · 19 Dec 2025
  • ES_VOLUME 2_APPENDIX 11.1 AIR QUALITY ASSESSMENT INPUT DATA Report · 19 Dec 2025
  • BREDBURY - APPLICATION VALIDATION ROLLING CHECKLIST V5 Report · 19 Dec 2025

Watch members (£5 a month) open the document list from here.

Open the documents

What happens while it is decided

This application is with Stockport for determination, against a statutory target of eight weeks. Over the last year Stockport decided outline applications in a median of 70 days. More in our guide to how long planning decisions take.

About outline applications

An outline application tests the principle of developing a site, holding back details such as appearance and landscaping as reserved matters for later approval. More in our guide to planning application types.

Nearby applications

Within 0.3 miles

  • Land Adjacent To Ashton Road Bredbury Park Way Bredbury Stockport

    DC/092181 Submitted 30 May 2024 100 yards away

    EIA Scoping Opinion in relation to an extension to Bredbury Park Industrial Estate to comprise creation of storage/ distribution warehouses (B8 Use Class) (including ancillary office accommodation); General Industrial units (B2 Use Class); and Commercial and Business uses (Class E (g)(iii)), along with the provision of other associated infrastructure (including internal plot access, roads, vehicular and cycling parking, footpaths, earthworks, drainage and internal landscaping).

    Decided Outline Extension 2 docs
  • Land At Junction Of Bredbury Parkway/Horsfield Way

    DC/092022 Submitted 8 May 2024 200 yards away

    Confirmation that conditions of planning permission J/72099 have been discharged.

    Granted Conditions 1 doc
  • Gate Centre Bredbury Park Way Bredbury Stockport SK6 2SN

    DC/092509 Submitted 1 Jul 2024 400 yards away

    Discharge of condition 8 of DC/086187

    Granted Conditions 11 docs
  • Gate Centre Bredbury Park Way Bredbury Stockport SK6 2SN

    DC/086187 Submitted 5 Aug 2022 400 yards away

    Erection of 2 single storey light industrial starter units

    Granted Full applications 13 docs
    Small domestic
  • Castle Hill Farm Castle Hill Bredbury Stockport SK6 2RY

    DC/092072 Submitted 10 May 2024 400 yards away

    Listed Building Consent for the repair and re-roofing of a Grade II listed barn.

    Granted Heritage and listed buildings 11 docs
  • Allied Bakeries Castle Hill Bredbury Stockport

    DC/091862 Submitted 22 Apr 2024 0.3 miles away

    Repositioning of wall adjacent to Allied Bakeries site entrance and relocation of fence along Castle Hill to allow road widening works approved under Planning Ref. DC/083927.

    Granted Full applications 6 docs
    Small domestic

In Stockport

  • DC/100057 Granted

    Ajax Works Whitehill Street South Reddish Stockport SK4 1NT

    PV solar installation 220x 'Hengdian group DMEG Magnetic Co Ltd' DM450M10RT-54HBB modules

    Received 27 Aug, published by the council 9 Sep 2026 Outline
  • DC/099921 Decided

    65 - 83 St Petersgate Stockport SK1 1DS

    EIA Screening Opinion - To determine whether the proposed redevelopment of the site at 65-83 St Petersgate, Stockport constitutes Environmental Impact Assessment (EIA) development.

    Received 14 Aug, published by the council 24 Aug 2026 Outline
  • DC/098795 Decided

    Land At Hyde Bank Meadows Romiley Stockport

    Request for Screening Opinion under the Town and Country Planning Environmental Impact Assessment Regulations 2017 (as amended) for an outline planning application with all matters reserved, except access for the development of up to 250 dwellings (Use Class C3) with associated access roads and provision of open spaces.

    Received 2 Apr, published by the council 21 Jul 2026 Outline
  • DC/099773 Decided

    Vitality House 217 Wellington Road South Heaviley Stockport SK2 6NG

    EIA Screening Opinion - The proposed development will seek permission for the demolition of the existing building and structures on site and redevelopment of the site with a residential apartment scheme comprising of up to a maximum of 290 dwellings, together with 45sqm of commercial space at ground floor.

    Received 17 Jul, published by the council 13 Aug 2026 Outline
  • DC/100207 Awaiting decision

    Land At Crescent Road Crescent Road Cheadle

    Stage 1 Permission in Principle (PIP) application for up to 7 no. dwellings

    Received 15 Sep, published by the council 6 Oct 2026 Outline