2026/0754

Land Adj The Grove Booton Norfolk

Granted South Norfolk Full

Proposal

Installation of post construction field drainage to support the operation of the Hornsea Project Three onshore export cable route (EIA Development).

As published by the council, reference 2026/0754

Timeline

Dates from the published record

  1. 19 Mar 2026

    Received by South Norfolk

  2. 29 Apr 2026

    Validated

    Checked as complete and ready for consideration.

  3. 24 Jul 2026

    Added to PlanIndex

  4. 31 Jul 2026

    Decision issued: Approval with Conditions

What a grant of permission means

The process from here

Permission has been granted, usually subject to conditions listed on the decision notice, some of which must be discharged before work starts. The decision notice on the council portal sets out exactly what was approved.

Work must normally begin within three years of the decision or the permission lapses. Neighbours cannot appeal a grant; challenging one means judicial review of how the decision was made, within tight time limits.

About full applications applications

How this application type works

A full application seeks permission for a complete, detailed proposal in one go: siting, design, access and landscaping are all fixed at this stage. It is the standard route for new buildings, conversions and changes of use. The statutory target is eight weeks for smaller schemes and thirteen weeks for major development, though complex cases often take longer by agreement.

More on full applications applications in our guide

Nearby applications

Within 500 metres

  • 2026/0754 Granted

    Land Adj The Grove Booton Norfolk

    Installation of post construction field drainage to support the operation of the Hornsea Project Three onshore export cable route (EIA Development).

    19 Mar 2026 0m away Full applications

In South Norfolk

  • 2025/2830 Granted

    Land South Of Dairy Farm Burgh Road Wheatacre Norfolk

    Erection of new self build 3-bedroom detached single storey dwelling/farmhouse

    9 Sep 2025 Full applications
  • 2026/0612 Granted

    Land South East Of Easton Road Marlingford Norfolk

    Retention of vehicular crossover Access Point 32 created by Orsted Power (UK) Ltd for the 'Hornsea Project Three Offshore Wind Farm' Project

    27 Feb 2026 Full applications
  • 2026/0861 Granted

    The School House The Street Framingham Earl Norfolk NR14 7QY

    Change of use from a fostering agency (sui generis) to children's day nursery (class E(f)) and associated external alterations

    26 Mar 2026 Full applications
  • 2026/2106 Awaiting decision

    The Old Vineyard Overwood Lane Forncett St Peter Norfolk

    Construction of 1no. rural worker and self build dwelling.

    21 Jul 2026 Full applications
  • 2026/0725 Granted

    Longwood House Denton Road Topcroft Norfolk NR35 2BA

    Erect a steel framed agricultural building used to temporarily store pig manure.

    17 Mar 2026 Full applications