Land At Little Bytham Sewage Treatment Works Little Bytham Road South Kesteven Little Bytham NG33 4SU
Proposal
Installation of a 12m streetworks telecommunications pole supporting smart metering equipment, including omni, GPS and 3G antennas, together with an equipment enclosure at the tower base and four concrete bollards associated with the Anglian Water smart metering network.
As published by the council, reference S26/1150
Timeline
Dates from the published record
-
1 Jul 2026
Received by South Kesteven
-
26 Jul 2026
Added to PlanIndex
-
Decision
Awaiting decision
The statutory target is eight weeks for most applications and thirteen for major development. Extensions of time are common.
What happens while it is decided
The process from here
This application is with South Kesteven for determination. The council publicises it, consults neighbours and technical bodies where required, and weighs the responses against local and national planning policy.
The statutory target is eight weeks for most applications and thirteen for major development, though extensions of time are common. Comments carry most weight while the case is undecided, so check the council portal for the deadline if you want to respond.
About telecoms applications
How this application type works
Telecommunications applications cover masts, antennas and cabinets, most of which come forward as prior approval cases under permitted development rules. The council typically has 56 days to consider siting and appearance only. The need for the network itself is treated as established, so objections carry most weight where they address visual impact or siting.
Nearby applications
Within 500 metres
-
S25/1721 Awaiting decision
The Old Rectory 37 High Street Little Bytham Lincolnshire NG33 4QJ
Section 211 notice to remove Acacia tree and pollard Ash tree.
Other telecoms applications
In South Kesteven
-
S21/1120 Granted
Highway Verge Junction Of Cherry Holt Road And South Road Bourne PE10 9HX
The installation of a new 18.00m monopole supporting 6 no. antennas with a wrap-around equipment cabinet at the base of the column, installation of 3 no.new equipment cabinets and ancillary development thereto.