Planning application
Land to the west of Cowbridge Road Bicker Fen South Holland and Boston
Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.
Proposal
Proposed development of a photovoltaic solar array, grid connection, access improvement works & ancillary development on land at Bicker Fen, Boston and South Holland - approved under H04-0849-22. Amendments to proposed site layout.
As published by the council, reference H04-0965-26
Application record
- Reference
- H04-0965-26
- Type
- NON MAT AMENDMENT
- Status
- Undecided
- Received
- 8 Oct 2026
- Validated
- 8 Oct 2026
- Parish
- Donington
Site history
Applications at this address on the South Holland register
This site has had 2 applications since 2026.
-
H04-0979-26 Awaiting decision
Land to the West of Cowbridge Road Bicker Fen South Holland and Boston
Details of all external lighting (Condition 17 of H04-0849-22)
Timeline
Dates from the published record
-
8 Oct 2026
Received by South Holland
-
9 Oct 2026
Added to PlanIndex
-
Decision
Awaiting decision
Decision expected by 3 December 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.
South Holland took a median of 56 days over the applications it decided in the last year.
Who's behind it
Company information only, from the register and Companies House
AGR Solar Applicant
5 applications on PlanIndex
Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.
See their track recordWhat happens while it is decided
This application is with South Holland for determination, against a statutory target of eight weeks. Over the last year South Holland decided amendment applications in a median of 28 days. More in our guide to how long planning decisions take.
About amendment applications
An amendment application makes limited changes to a permission that already exists; anything beyond modest adjustment needs a fresh application. More in our guide to planning application types.
Other amendment applications
In South Holland
-
H18-0995-26 Awaiting decision
Boud Minerals & Polymers Warehouse West Bank Road Sutton Bridge PE12 9UR
Proposed Open Storage Buildings, Concrete Yard & Access - approved under H18-0310-23. Amendments to site access and amendments to position and height of building.
-
H09-1001-26 Awaiting decision
Holbeach Methodist Chapel Chapel Drove Holbeach Drove PE12 0PT
Change of use from Methodist Church to single dwelling - approved under H09-0697-24. Amendment to omit the proposed addition of roof lights and internal mezzanine floor shown on approved plan 4283-24 01
-
H17-0795-26 Granted
28 WOODS LANE SURFLEET SPALDING PE11 4AN
Retention of dwelling without complying with agricultural habitation clause (Condition 2 of H17-0432-97)
-
H09-0949-26 Awaiting decision
FIVE ACRES PENNY HILL ROAD HOLBEACH PE12 8DN
Removal of Agricultural Occupancy Condition (Condition 4 of application H09-0413-86)
-
H09-0898-26 Granted
35 Forest Way Holbeach Spalding PE12 7FE
Erection of Domestic Garage & Workshop. Approved under H09-0569-26. Amendment to position & site of garage, removal of 1 roof light, additional windows & change to garage door on south elevation