Planning application
26/02089/FUL
Pheasants Grove Milton Road Impington Cambridgeshire CB24 9NF
Proposal
Revised access arrangements.
As published by the council, reference 26/02089/FUL
Timeline
Dates from the published record
-
4 Jun 2026
Received by South Cambridgeshire
-
18 Jun 2026
Validated
Checked as complete and ready for consideration.
-
23 Jul 2026
Added to PlanIndex
-
Decision
Awaiting decision
The statutory target is eight weeks for most applications and thirteen for major development. Extensions of time are common.
What happens while it is decided
The process from here
This application is with South Cambridgeshire for determination. The council publicises it, consults neighbours and technical bodies where required, and weighs the responses against local and national planning policy.
The statutory target is eight weeks for most applications and thirteen for major development, though extensions of time are common. Comments carry most weight while the case is undecided, so check the council portal for the deadline if you want to respond.
About full applications applications
How this application type works
A full application seeks permission for a complete, detailed proposal in one go: siting, design, access and landscaping are all fixed at this stage. It is the standard route for new buildings, conversions and changes of use. The statutory target is eight weeks for smaller schemes and thirteen weeks for major development, though complex cases often take longer by agreement.
Nearby applications
Within 500 metres
-
20/04250/HFUL Granted
7 Woodcock Close Impington CB24 9LD
Construction of garden wall and erection of garden shed building to front of site
-
25/00850/TTHR Awaiting decision
32 St Georges Way Impington Cambridgeshire CB24 9AF
Hedge removal
-
20/03104/HFUL Granted
16 Woodcock Close Impington CB24 9LD
Alterations to porch, first floor side extension, new cladding and roofing, internal alterations.
-
26/01983/LBC Awaiting decision
Impington Village College New Road Impington Cambridgeshire CB24 9LX
Localised repairs to structural cracks caused by tree roots.
-
25/02806/CONDA Awaiting decision
71 New Road Impington Cambridgeshire CB24 9LU
Submission of details required by condition 4 (Arboricultural Method Statement and Tree Protection Plan) of planning permission 25/02806/HFUL
-
26/01190/LBC Refused
Impington Village College New Road Impington Cambridgeshire CB24 9LX
Change of fire doors to meet modern regulations in 5 classrooms and 2 stairwells.
Other full applications applications
In South Cambridgeshire
-
26/02779/FUL Awaiting decision
3 Royston Road Whittlesford Cambridgeshire CB22 4NW
3 bedroom replacement self build dwelling following demolition of existing bungalow.
-
26/02151/FUL Granted
3 Comberton Road Barton Cambridgeshire CB23 7BA
Installation of a Solar PV system to the roof pitches of the detached garage outbuilding.
-
26/01627/FUL Granted
Valley Farm House Valley Farm Road West Wratting Cambridgeshire CB21 4HH
Change of use of an agricultural building to uses falling within classes B8 storage/distribution or E(g)(iii) light industrial use.
-
26/02708/FUL Awaiting decision
Rectory Farm Middle Street Thriplow Cambridge Cambridgeshire SG8 7RD
Partial demolition of existing collapsed wall and erection of a new wall.
-
25/02739/FUL Granted
Land To The South Of Munceys Farm London Way Melbourn Cambridgeshire SG8 6DJ
Construction and operation of a 25MW solar photovoltaic farm and a 25MW Battery Energy Storage System (BESS) including access, fencing, CCTV, internal service tracks, ancillary equipment and scheme of landscaping for an operational lifespan of 40 years.