Site 1 Land East Of Hodgetts Lane Berkswell Solihull

Awaiting decision Solihull PL/2026/01532/NONMC

Relates to PL/2023/02196/PPFL

Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.

Proposal

Non-material amendment following planning approval PL/2025/00934/VAR dated 05.08.2026 for 'Amendments to planning permission PL/2023/02196/PPFL dated 28 January 2025 (Allowed on appeal APP/Q4625/W/24/3348223) for installation of a flexible electricity storage facility to supplement the local electricity grid in order to stabilise and secure electricity supply.' Namely: refinement to the internal site layout and the addition of a secondary access route within the application boundary and the overall number of BESS modules reduced by two, from 26 to 24 and the number of AC units reduced from 13 to 6.

As published by the council, reference PL/2026/01532/NONMC

Application record

Reference
PL/2026/01532/NONMC
Status
Awaiting decision
Received
11 Aug 2026
Validated
11 Aug 2026
Ward
Balsall & Berkswell
Parish
Berkswell Parish Council

Site history

Applications at this address on the Solihull register

This site has had 3 applications since 2026: 1 approved, 0 refused.

  • PL/2026/01427/DIS Awaiting decision

    Site 1 Land East Of Hodgetts Lane Berkswell Solihull

    Discharge condition no. 4 (LEMP) and 10 (hard and soft landscaping) following planning approval PL/2025/00934/VAR dated 05.08.2025 for 'Amendments to planning permission PL/2023/02196/PPFL dated 28.01.2025 (Allowed on appeal APP/Q4625/W/24/3348223) for installation of a flexible electricity storage facility to supplement the local electricity grid in order to stabilise and secure electricity supply.'

    Submitted 14 Jul 2026
  • Site 1 Land East Of Hodgetts Lane Berkswell Solihull

    Discharge condition Nos. 5ii and 5iii (Archaeology) following planning application PL/2023/02196/PPFL for Installation of a flexible electricity storage facility to supplement the local electricity grid in order to stabilise and secure electricity supply. (Allowed on appeal APP/Q4625/W/24/3348223 28.01.2025).

    Decided 12 Jun 2026 Conditions

Timeline

Dates from the published record

  1. 11 Aug 2026

    Received by Solihull

  2. 20 Aug 2026

    Added to PlanIndex

  3. Decision

    Awaiting decision

    Decision expected by 6 October 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.

    Solihull took a median of 106 days over the applications it decided in the last year.

Cases linked to this one on the register

  • Land East Of Hodgetts Lane Berkswell Solihull

    Installation of a flexible electricity storage facility to supplement the local electricity grid in order to stabilise and secure electricity supply.

    Decided 28 Mar 2024 Full applications
  • Application: PL/2025/00934/VAR (Decided)

Who's behind it

Company information only, from the register and Companies House

Agent on file, registered in York

43 applications on PlanIndex · across 7 councils

Trade members see who it is, their full track record, and every application they have filed.

See who's behind it

Documents

Plans, drawings, consultee responses and the officer's report

3 documents on file for this application

  • APPLICATION FORM REDACTED Application Form · 11 Aug 2026
  • SITE LAYOUT Drawing · 11 Aug 2026
  • SUPPORTING LETTER Correspondence · 11 Aug 2026

Trade members open them from here.

Open the documents

What happens while it is decided

This application is with Solihull for determination, against a statutory target of eight weeks. Over the last year Solihull's median decision took 106 days. More in our guide to how long planning decisions take.

About this record

The published feed does not state which type of application this is; the register entry on Solihull's portal will say. Our guide explains the common types.