Decision times · West Midlands
How long planning decisions take in Solihull
68 days. Ranked 35 of 45.
In the year to December 2026, the median planning application decided by Solihull took 68 days from submission to decision — 12 days beyond the eight week target. That is measured across 1,105 decisions where the council published both dates.
How Solihull compares
Year to December 2026
Solihull takes longer than the country as a whole: 11 days above the national median of 57 days. Nationally 49% of applications are decided within eight weeks; here it is 41%.
The average here is 110 days, longer than the median because a handful of applications take very much longer than the rest. For planning around, 225 days is the more useful number: nine applications in ten were decided inside it.
-
Within eight weeks the statutory target 455 41%
-
Eight to thirteen weeks the major development band 243 22%
-
Over thirteen weeks commonly an agreed extension 407 37%
The last few years
Each row is a full twelve months of decisions, ending in the quarter shown
Rolling twelve month windows overlap by nine months, so this reads as a trend rather than as four separate quarters. Only windows our records reach far enough back to measure in full are listed.
| Twelve months to | Median days | UK rank |
|---|---|---|
| December 2026 | 68 | 35 of 45 |
| September 2026 | 74 | 49 of 56 |
| March 2026 | 200 | 38 of 38 |
| December 2025 | 153 | 23 of 24 |
| September 2025 | 80 | 24 of 27 |
| June 2025 | 67 | 26 of 31 |
| March 2025 | 61 | 22 of 30 |
| December 2024 | 59 | 35 of 57 |
Against the same twelve months a year earlier, when the median was 153 days, Solihull has moved down 12 places in the table.
By type of application
Year to December 2026 · types with at least ten decisions
The headline median mixes every kind of application together. A householder extension and an outline application for a housing site are not the same job, and the difference between them is usually larger than the difference between two councils.
-
Prior approval 56 decided 41 days
-
Lawful development 93 decided 55 days
-
Advertising 21 decided 56 days
-
Amendments 55 decided 57 days
-
Householder 221 decided 65 days
-
Trees 120 decided 99 days
-
Conditions 66 decided 104 days
-
Full applications 118 decided 180 days
-
Outline 18 decided 220 days
What Solihull decides
Year to December 2026
Solihull issued 1,105 decisions in the year to December 2026. Of the clear-cut outcomes, 88% were approvals: 941 granted against 126 refused. Split decisions, withdrawals and other outcomes sit outside that percentage rather than being counted as either.
Speed and approval rate are separate things. A council that refuses quickly is not doing the same job as one that negotiates an approval slowly, and neither figure alone says which served the applicant better.
Common questions
How long does a planning decision take in Solihull?
The median planning application decided by Solihull in the year to December 2026 took 68 days from submission to decision, 12 days beyond the eight week target. That is measured across 1,105 decisions where the council published both a start date and a decision date. It ranks 35 of 45 UK councils on decision speed.
Does Solihull meet the eight week target?
41% of the 1,105 decisions Solihull made in the year to December 2026 came within eight weeks of the application being received, and 63% within thirteen weeks. Nine in ten were decided within 225 days. Councils can agree an extension of time with an applicant, so a decision past eight weeks is not necessarily a missed deadline.
Is Solihull faster or slower than average?
Solihull is slower than average: its median of 68 days is 11 days above the national median of 57 days.
Is Solihull getting faster or slower?
Against the same twelve month window a year earlier, when its median was 153 days, Solihull has moved down 12 places in the table. Its median has fallen by 85 days.
What proportion of applications does Solihull approve?
88% of the clear-cut outcomes Solihull issued in the year to December 2026 were approvals: 941 granted against 126 refused. Split decisions, withdrawals and other outcomes are excluded from that percentage.
Cite these figures
Click the text to select the whole citation.
Solihull planning decision times, year to December 2026: median 68 days from application to decision (12 days beyond the eight week target), across 1,105 decisions with both dates published. 41% were decided within the eight week statutory target, 63% within thirteen weeks; nine in ten within 225 days. Ranked 35 of 45 UK councils on decision speed (national median 57 days). 88% of clear-cut outcomes were approvals. Source: PlanIndex, planindex.co.uk.
Or take the data itself: this council's history (CSV) or the full league table (CSV).
Embed these figures
Paste either snippet into your page. Click a snippet to select all of it. The credit line is part of the embed.
<script src="https://planindex.co.uk/embed/decision-times.js" data-council="solihull" defer></script>
If your CMS strips scripts, use the frame directly:
<iframe src="https://planindex.co.uk/embed/decision-times/solihull" title="Planning decision times in Solihull" width="100%" height="215" loading="lazy" frameborder="0"></iframe>
<p>Data: <a href="https://planindex.co.uk/planning-decision-times/solihull">Planning decision times, from PlanIndex</a></p>