Planning application
Land East Of The A968 Firth ZE2 9TE
Relates to 2025/234/PPF
Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.
Proposal
Application for consent, agreement or approval required by planning Condition: 03 (Biodiversity Implementation Scheme) of planning application 2025/234/PPF
As published by the council, reference 2025/234/DCON1
Application record
- Reference
- 2025/234/DCON1
- Status
- Pending Consideration
- Received
- 22 Oct 2026
- Validated
- 22 Oct 2026
- Ward
- Delting
- Postcode
- ZE2 9TE
Site history
Applications at this address on the Shetland Islands register
This site has had 2 applications since 2025: 1 approved, 0 refused.
-
2025/234/PPF Granted
Land East Of The A968 Firth ZE2 9TE
Erection of substation building comprising of 1 x switchroom, palisade fencing, associated hard standing/storage, parking and access; change of use to industrial land.
Timeline
Dates from the published record
-
22 Oct 2026
Received by Shetland Islands
-
22 Oct 2026
Added to PlanIndex
-
Decision
Awaiting decision
Decision expected by 17 December 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.
Shetland Islands took a median of 60 days over the applications it decided in the last year.
Related applications
Cases linked to this one on the register
-
2025/234/PPF Granted
Land East Of The A968 Firth ZE2 9TE
Erection of substation building comprising of 1 x switchroom, palisade fencing, associated hard standing/storage, parking and access; change of use to industrial land.
Who's behind it
Company information only, from the register and Companies House
Savills Limited Agent, registered in London
Active · incorporated 1987 · London
2,469 applications on PlanIndex · across 194 councils · 92% granted
Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.
See their track recordDocuments
Plans, drawings, consultee responses and the officer's report
2 documents on file for this application
- FIRTH - BNG IMPLEMENTATION SCHEME
- REQUEST TO DISCHARGE CONDITION 3
Watch members (£5 a month) open the document list from here.
Open the documentsWhat happens while it is decided
This application is with Shetland Islands for determination, against a statutory target of eight weeks. Over the last year Shetland Islands's median decision took 60 days. More in our guide to how long planning decisions take.
About this record
The published feed does not state which type of application this is; the register entry on Shetland Islands's portal will say. Our guide explains the common types.
Nearby applications
Within 0.3 miles
-
Land East Of The A968 Firth ZE2 9TE
Erection of substation building comprising of 1 x switchroom, palisade fencing, associated hard standing/storage, parking and access; change of use to industrial land.
Granted Full applications 33 docs