Skip to content
PlanIndex Get alerts
Menu

Planning application

Esso Pipeline Rushmoor Borough Area Farnborough Hampshire

Granted Rushmoor 19/00432/PINS Consultation from PINS

Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

Southampton to London Esso Fuel Pipeline from the A327 crossing the western section of Southwood Country Park, through land to the west of Cove Brook, Cove Road and Nash Close, crossing the South Western main railway line to the west of Farnborough. Running east alongside the railway line to Stake Lane through Queen Elizabeth Park to the north of Farnborough Station, crossing open land at Farnborough Hill School under the North Downs railway line, A331, and River Blackwater

As published by the council, reference 19/00432/PINS

Application record

Reference
19/00432/PINS
Type
Consultation from PINS
Status
Decided
Decision
Granted As published: Permission Granted
Received
25 Jun 2019
Validated
1 Jul 2019
Decided
7 Oct 2020
Ward
Empress
Decision by
Committee

Timeline

Dates from the published record

  1. 25 Jun 2019

    Received by Rushmoor

  2. 1 Jul 2019

    Validated

    Checked as complete and ready for consideration.

  3. 7 Oct 2020

    Decision issued: Permission Granted

  4. 1 Sep 2026

    Added to PlanIndex

Who's behind it

Company information only, from the register and Companies House

Planning Inspectorate Applicant, a planning consultancy

20 applications on PlanIndex · across 14 councils

Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.

See their track record

Documents

Plans, drawings, consultee responses and the officer's report

146 documents on file for this application

  • Stages of authorised development requirement 3 Report · 03 Jun 2021
  • Stages of authorised development requirement 3 Report · 03 Jun 2021
  • Rushmoor vegetation plans Plans · 03 Jun 2021
  • R6 letter Correspondence · 05 Sep 2019
  • Pins acknowledgement Correspondence · 27 Jul 2019
  • Initial reps Correspondence · 19 Jul 2019
  • Self completed section 55 checklist Report · 27 Jun 2019
  • Glossary Report · 27 Jun 2019
  • Bramshot road Plans · 26 Jun 2019
  • Cody technology park Plans · 26 Jun 2019
  • Cove brook Plans · 26 Jun 2019
  • Queen elizabeth country park Plans · 26 Jun 2019
  • Farnborough railway station Plans · 26 Jun 2019
  • Farnborough hill school Plans · 26 Jun 2019
  • Ship lane cemetery Plans · 26 Jun 2019
  • Non rushmoor plans Plans · 26 Jun 2019
  • Railway line frimley Plans · 26 Jun 2019
  • Beacon hill road Plans · 26 Jun 2019
  • Cover letter Correspondence · 21 Jun 2019
  • Copies of newspaper notices Report · 21 Jun 2019
  • Electronic application index Report · 21 Jun 2019
  • Navigation document Report · 21 Jun 2019
  • Land plans 1 of 4 Plans · 21 Jun 2019
  • Land plans 2 of 4 Plans · 21 Jun 2019
  • Land plans 3 of 4 Plans · 21 Jun 2019
  • Land plans 4 of 4 Plans · 21 Jun 2019
  • Work plans 1 of 3 Plans · 21 Jun 2019
  • Work plans 2 of 3 Plans · 21 Jun 2019
  • Work plans 3 of 3 Plans · 21 Jun 2019
  • Special category land plans 1 of 3 Plans · 21 Jun 2019
  • Special category land plans 2 of 3 Plans · 21 Jun 2019
  • Special category land plans 3 of 3 Plans · 21 Jun 2019
  • Crown land plans Plans · 21 Jun 2019
  • Access public right of way 1 of 3 Plans · 21 Jun 2019
  • Access public right of way 2 of 3 Plans · 21 Jun 2019
  • Access public right of way 3 of 3 Plans · 21 Jun 2019
  • General arrangement plans 1 of 3 Plans · 21 Jun 2019
  • General arrangement plans 2 of 3 Plans · 21 Jun 2019
  • General arrangement plans 3 of 3 Plans · 21 Jun 2019
  • Other plans Plans · 21 Jun 2019
  • Draft development consent order Report · 21 Jun 2019
  • Explanatory memorandum Report · 21 Jun 2019
  • Validation report for draft development consent order Report · 21 Jun 2019
  • Statement of reasons Report · 21 Jun 2019
  • Funding statement Report · 21 Jun 2019
  • Book of reference Report · 21 Jun 2019
  • Appendix 2 initial engagement Report · 21 Jun 2019
  • Appendix 3 pipeline corridor consultation Report · 21 Jun 2019
  • Appendix 4 interim engagement Report · 21 Jun 2019
  • Appendix 5 preferred route consultation Report · 21 Jun 2019
  • Appendix 6 design refinements Report · 21 Jun 2019
  • Appendix 7 route release Report · 21 Jun 2019
  • Consultation report Report · 21 Jun 2019
  • Non technical summary Report · 21 Jun 2019
  • Acronyms Report · 21 Jun 2019
  • Chapter 1 introduction Report · 21 Jun 2019
  • Chapter 2 regulatory and policy context Report · 21 Jun 2019
  • Chapter 3 project description Report · 21 Jun 2019
  • Chapter 4 design evolution Report · 21 Jun 2019
  • Chapter 5 consultation and scoping Report · 21 Jun 2019
  • Chapter 6 overview of assessment process Report · 21 Jun 2019
  • Chapter 7 biodiversity Report · 21 Jun 2019
  • Chapter 8 water Report · 21 Jun 2019
  • Chapter 9 historic environment Report · 21 Jun 2019
  • Chapter 10 landscape and visual Report · 21 Jun 2019
  • Chapter 11 soils and geology Report · 21 Jun 2019
  • Chapter 12 land use Report · 21 Jun 2019
  • Chapter 13 people and communities Report · 21 Jun 2019
  • Chapter 14 major accidents Report · 21 Jun 2019
  • Chapter 15 cumulative effects Report · 21 Jun 2019
  • Chapter 16 environmental management and mitigation Report · 21 Jun 2019
  • Chapter 17 summary of significant residual effects Report · 21 Jun 2019
  • Figures chapter 1 introduction Report · 21 Jun 2019
  • Figures chapter 3 project description Report · 21 Jun 2019
  • Figures chapter 4 design evolution Report · 21 Jun 2019
  • Figures chapter 7 biodiversity Report · 21 Jun 2019
  • Figures chapter 8 water Report · 21 Jun 2019
  • Figures chapter 9 historic environment Report · 21 Jun 2019
  • Figures chapter 10 landscape and visual Report · 21 Jun 2019
  • Figures chapter 11 soils and geology Report · 21 Jun 2019
  • Figures chapter 12 land use Report · 21 Jun 2019
  • Figures chapter 13 people and communities Report · 21 Jun 2019
  • Figures chapter 15 cumulative effects Report · 21 Jun 2019
  • Appendix 1.1 environmental statement content and linkages Report · 21 Jun 2019
  • Appendix 1.2 index of photographs Report · 21 Jun 2019
  • Appendix 1.3 compliance of es with schedule 4 of eia regs Report · 21 Jun 2019
  • Appendix 1.4 list of author qualifications Report · 21 Jun 2019
  • Appendix 2.1 environmental legislation and policy Report · 21 Jun 2019
  • Appendix 2.2 regional and local planning policy Report · 21 Jun 2019
  • Appendix 3.1 table of trenchless crossings Report · 21 Jun 2019
  • Appendix 3.2 proposed construction schedule Report · 21 Jun 2019
  • Appendix 4.1 pipeline route corridor options Report · 21 Jun 2019
  • Appendix 5.1 scoping opinion response Report · 21 Jun 2019
  • Appendix 5.2 responses to scoping report Report · 21 Jun 2019
  • Appendix 7.1 habitats and botany factual report Report · 21 Jun 2019
  • Appendix 7.1 2 habitats and botany factual report Report · 21 Jun 2019
  • Appendix 7.2 hedgerow factual report Report · 21 Jun 2019
  • Appendix 7.3 ancient woodland factual report Report · 21 Jun 2019
  • Appendix 7.4 invasive non native plant species factual report Report · 21 Jun 2019
  • Appendix 7.5 aquatic ecology factual report Report · 21 Jun 2019
  • Appendix 7.7 1 bat factual report Report · 21 Jun 2019
  • Appendix 7.7 2 bat factual report Report · 21 Jun 2019
  • Appendix 7.7 3 bat factual report Report · 21 Jun 2019
  • Appendix 7.8 bird factual report Report · 21 Jun 2019
  • Appendix 7.9 dormouse factual report Report · 21 Jun 2019
  • Appendix 7.10 great crested newt factual report Report · 21 Jun 2019
  • Appendix 7.11 reptile factual report Report · 21 Jun 2019
  • Appendix 7.12 riparian mammals factual report Report · 21 Jun 2019
  • Appendix 7.14 draft dormouse eps licence Report · 21 Jun 2019
  • Appendix 7.15 draft great crested newt eps licence Report · 21 Jun 2019
  • Appendix 7.16 draft rare reptiles eps licence Report · 21 Jun 2019
  • Appendix 7.17 protected and controlled species legislation compliance report Report · 21 Jun 2019
  • Appendix 8.1 groundwater baseline Report · 21 Jun 2019
  • Appendix 8.2 detailed trenchless and targeted open cut assessment Report · 21 Jun 2019
  • Appendix 8.3 groundwater dependent terrestrial ecosystems Report · 21 Jun 2019
  • Appendix 8.4 ground water abstraction assessment Report · 21 Jun 2019
  • Appendix 8.5 potential effects on groundwater Report · 21 Jun 2019
  • Appendix 8.6 water framework directive compliance assessment Report · 21 Jun 2019
  • Appendix 9.1 historic environment desk survey Report · 21 Jun 2019
  • Appendix 9.2 1 geophysical survey Report · 21 Jun 2019
  • Appendix 9.2 2 geophysical survey Report · 21 Jun 2019
  • Appendix 9.3 historic environment gazetteer Report · 21 Jun 2019
  • Appendix 9.4 effects on historic environment Report · 21 Jun 2019
  • Appendix 9.5 archaeological mitigation strategy Report · 21 Jun 2019
  • Appendix 10.1 representative viewpoints Report · 21 Jun 2019
  • Appendix 10.2 schedule of notable trees Report · 21 Jun 2019
  • Appendix 10.3 visual impact schedules Report · 21 Jun 2019
  • Appendix 11.1 soils and geology supporting info Report · 21 Jun 2019
  • Appendix 12.1 land use baseline conditions Report · 21 Jun 2019
  • Appendix 13.1 traffic and transport technical note Report · 21 Jun 2019
  • Appendix 13.2 air quality technical note Report · 21 Jun 2019
  • Appendix 13.3 noise and vibration tech note Report · 21 Jun 2019
  • Appendix 13.4 human health tech note Report · 21 Jun 2019
  • Appendix 13.5 statement of statutory nuisance Report · 21 Jun 2019
  • Appendix 14.1 material safety data sheets Report · 21 Jun 2019
  • Appendix 15.1 long list of other developments Report · 21 Jun 2019
  • Appendix 15.2 intra project cumulative effects assessment Report · 21 Jun 2019
  • Appendix 15.3 inter project cumulative effects assessment Report · 21 Jun 2019
  • Appendix 16.1 code of construction practice Report · 21 Jun 2019
  • Appendix 16.2 outline construction environmental management plan Report · 21 Jun 2019
  • Habitats regulations 1 Report · 21 Jun 2019
  • Habitats regulations 2 Report · 21 Jun 2019
  • Planning statement Report · 21 Jun 2019
  • Draft statements of common ground Report · 21 Jun 2019
  • Flood risk assessment Report · 21 Jun 2019
  • Transport assessment Report · 21 Jun 2019

Watch members (£5 a month) open the document list from here.

Open the documents

What this grant of permission means

Rushmoor granted permission on 7 October 2020, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About outline applications

An outline application tests the principle of developing a site, holding back details such as appearance and landscaping as reserved matters for later approval. More in our guide to planning application types.

Nearby applications

Within 0.3 miles

In Rushmoor

  • 26/00139/PDCPP Withdrawn

    Village Hotel Pinehurst Road Farnborough Hampshire GU14 7BF

    CERTIFICATE OF LAWFULNESS FOR A PROPOSED USE OR DEVELOPMENT: 6no. Electric Vehicle charging bays, 3no. EV Charging Posts and associated electric equipment

    Received 18 Mar, published by the council 26 Jul 2026 Outline
  • 26/00110/PDC Granted

    22 Churchill Avenue Aldershot Hampshire GU12 4JR

    LAWFUL DEVELOPMENT CERTIFICATE FOR PROPOSED DEVELOPMENT OR USE: Roof alterations in connection with a loft conversion including alterations to flue/soil vent pipe and installation of Solar PV Panels.

    Received 4 Mar, published by the council 26 Jul 2026 Outline
  • 26/00126/HCC Granted

    The Wavell School Lynchford Road Farnborough Hampshire GU14 6BH

    HAMPSHIRE COUNTY COUNCIL CONSULTATION : construction of external hard surfacing relating to the provision of a new modular classroom

    Received 12 Mar, published by the council 26 Jul 2026 Outline
  • 26/00133/PDCPP Granted

    4 Montacute Close Farnborough Hampshire GU14 7HG

    Certificate of Lawfulness for Proposed Development: Formation of a dormer within rear roof slope and two roof lights in the front roof slope

    Received 16 Mar, published by the council 26 Jul 2026 Outline
  • 26/00074/PDCPP Withdrawn

    Copthall House 77 - 79 Victoria Road Aldershot Hampshire GU11 1SH

    CERTIFICATE OF LAWFULNESS FOR A PROPOSED USE OR DEVELOPMENT: Change of use of part ground floor from Gym (Use Class E(d)) to Grocery Retail shop (Use Class E(a))

    Received 14 Feb, published by the council 26 Jul 2026 Outline