Proposal

Development of site to deliver data centre campus (sui generis use) consisting of (a) data centre buildings (b) energy, power, and water infrastructure (c) site access and internal roads (d) site security arrangements (e) hard and soft, green and blue, landscaping and (f) other ancillary and auxiliary forms of development (application includes elements approved under ref. RU.21/0780 and already constructed)

As published by the council, reference RU.25/1538

Application record

Reference
RU.25/1538
Status
REGISTERED
Received
11 Nov 2025
Validated
11 Nov 2025
Postcode
KT16 0EE

Timeline

Dates from the published record

  1. 11 Nov 2025

    Received by Runnymede

  2. 30 Jul 2026

    Added to PlanIndex

  3. Decision

    Awaiting decision

    Decision expected by 6 January 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.

    Runnymede took a median of 46 days over the applications it decided in the last year.

Documents

Plans, drawings, consultee responses and the officer's report

53 documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Trade members open them from here.

Open the documents

What happens while it is decided

This application is with Runnymede for determination, against a statutory target of eight weeks. Over the last year Runnymede's median decision took 46 days. More in our guide to how long planning decisions take.

About this record

The published feed does not state which type of application this is; the register entry on Runnymede's portal will say. Our guide explains the common types.

Nearby applications

Within 500 metres

  • Longcross Studios Chobham Lane Longcross Chertsey KT16 0EE

    RU.25/1392 Submitted 13 Oct 2025 0m away

    Details pursuant to Discharge Condition 7 (SuDS) of planning permission RU.23/1712 Construction of a workshop building on existing hardstanding and associated works

    Granted Conditions 3 docs
  • Longcross North Data Centre Campus CHOBHAM LANE CHERTSEY KT16 0EE

    RU.24/1339 Submitted 9 Oct 2024 0m away

    Details pursuant to Discharge Condition 37 (Provision of electric vehicle charging and hierarchy for priority of use) of planning permission RU.13/0856 in respect of the Phase 3 Data Centre campus

    Granted Conditions 4 docs
  • Longcross North - Longcross Studios Chobham Lane Chertsey KT16 0EE

    RU.25/1749 Submitted 11 Dec 2025 0m away

    Details pursuant to Discharge Condition 2 (drainage) of planning permission RU.25/0213 Full planning permission for the retention of film studio workshop building 1 (previously granted temporary planning permission under reference RU.19/1851 and RU.23/0651)

    Granted Conditions 4 docs
  • Longcross Studios Chobham Lane Longcross Chertsey KT16 0EE

    RU.23/1712 Submitted 23 Jan 2024 0m away

    Construction of a workshop building on existing hardstanding and associated works

    Granted 18 docs
  • Longcross North Chobham Lane Longcross Chertsey KT16 0EE

    RU.21/1476 Submitted 26 Aug 2021 0m away

    Details pursuant to Condition 22 (Car park management and allocation) of planning permission RU.20/1206 [Hybrid planning application: full planning application for a re-configured discovery building car park (to that approved under RU.17/1191); retention of the stage 2 building and associated hardstanding; Outline planning permission sought for proposed sports provision, public open space and associated landscaping; vehicular access, drop-off and car parking to the railway station; and associated engineering works (all matters reserved) and proposed security fence (all matters reserved except layout)]

    Granted Conditions 6 docs
    Small domestic
  • Longcross North Chobham Lane Chertsey KT16 0EE

    RU.21/1350 Submitted 5 Aug 2021 0m away

    Details pursant to Condition 3 (surfacing materials), 4 (Badger survey), 5 (Construction Environmental Management Plan), 6 (Construction Transport Management Plan) and 8 (Relacement Trees and Hedging) of planning permission RU.20/1436 (foul water pumping station with associated compound area, permanent access and extended parking bay to Chobham Lane to be formed incorporating alterations to public footway).

    Granted Trees 11 docs