26/00412/ECU36

Land 750 Metres South Of Newbigging Farm Tibbermore Perth PH1 1QH

Awaiting decision Perth and Kinross Electricity Consent Unit - Section 36

Proposal

Proposed Solar PV Development with 75 MW export capacity and 97MW build-out and accompanying infrastructure ECU00006264

As published by the council, reference 26/00412/ECU36

Timeline

Dates from the published record

  1. 26 Mar 2026

    Received by Perth and Kinross

  2. 30 Mar 2026

    Validated

    Checked as complete and ready for consideration.

  3. 28 Jul 2026

    Added to PlanIndex

  4. Decision

    Awaiting decision

    The statutory target is eight weeks for most applications and thirteen for major development. Extensions of time are common.

What happens while it is decided

The process from here

This application is with Perth and Kinross for determination. The council publicises it, consults neighbours and technical bodies where required, and weighs the responses against local and national planning policy.

The statutory target is eight weeks for most applications and thirteen for major development, though extensions of time are common. Comments carry most weight while the case is undecided, so check the council portal for the deadline if you want to respond.

About other applications

How this application type works

This application sits outside the common categories, which can include county matters such as minerals and waste, works by statutory undertakers, demolition notifications and other less frequent procedures. The council record linked below sets out the specific procedure that applies, and the description above is taken directly from the published register.

More on other applications in our guide

In Perth and Kinross

  • 26/00574/HS Granted

    Bells Distillery Perth Road Pitlochry PH16 5LY

    Hazardous substances consent

    29 Apr 2026 Other
  • 26/00828/ECU37 Decided

    Land 1.3 Kilometres East Of Keepers Cottage Cashlie Glenlyon Aberfeldy PH15 2PX

    Installation of 33kV overhead line to supply telecommunications mast

    5 Jun 2026 Other