Proposal
Discharge of condition 3 (CTMP) of planning permission 25/0364/PA (Installation of a 6 inch 10 bar low pressure hydrogen pipeline and associated Above Ground Installation).
As published by the council, reference 26/0462/DC
Application record
- Reference
- 26/0462/DC
- Type
- Discharge of Conditions
- Status
- Consultations Sent
- Received
- 6 Oct 2026
- Validated
- 6 Oct 2026
- Ward
- St Ishmael's, Milford Hubberston
- Decision by
- Decision to be made by officer
- Postcode
- SA73 3SU
Timeline
Dates from the published record
-
6 Oct 2026
Received by Pembrokeshire
-
19 Nov 2026
Added to PlanIndex
-
Decision
Awaiting decision
Decision expected by 1 December 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.
Pembrokeshire took a median of 55 days over the applications it decided in the last year.
Documents
9 documents on file for this application
A planning file usually holds the application form, the consultee responses, the officer's report and the decision notice.
Watch members (£5 a month) open the document list from here.
Open the documentsWorking a patch? Trade sends you every new job in your area each morning. 14 days free.
What happens while it is decided
This application is with Pembrokeshire for determination, against a statutory target of eight weeks. Over the last year Pembrokeshire decided condition discharge and variation applications in a median of 53 days. More in our guide to how long planning decisions take.
About condition discharge and variation applications
This application deals with conditions on an existing permission, supplying the details a condition requires or asking to vary or remove one, without reopening the permission itself. More in our guide to planning application types.
Nearby applications
Within 0.3 miles
-
Impala Terminal to South Hook LNG
92% historically approved · decision due ~15 Dec
Discharge of condition 4 (archaeology) pf planning permission 25/0364/PA (Installation of a 6 inch 10 bar low pressure hydrogen pipeline and associated Above Ground Installation)
Awaiting decision Conditions 7 docs -
Land attached to, Stable Cottage, Lodge Farm, Dale Road, Hubberston, Milford Haven, Pembrokeshire, SA73 3RX
Construction of dog kennels for business use.
Granted Full applications 12 docs
Other condition discharge and variation applications
In Pembrokeshire
-
26/0433/DC Granted
Land South of Pembroke Power Station, Pembroke, SA71 5TP
Discharge of Conditions 3 (Construction Environment Management Plan) & 4 (Landscaping) of Planning Permission 25/0524/PA (Installation of underground cable)
-
26/0409/DC Split decision
20, Hamilton Terrace, Milford Haven, Pembrokeshire, SA73 3JA
Discharge of conditions 3 (parking details) and 4 (Construction Environmental Management Plan) to planning permission 25/0418/PA (Change of use from redundant restaurant and accommodation to 1 flat and 8 bedsits together with extension and alterations).
-
26/0434/DC Granted
Land East of the Greenlink Converter Station, Off Goldborough Road, Pembroke
Discharge of condition 11 (contamination) of planning permission 23/0857/PA (Installation of a Battery Energy Storage System (BESS), associated infrastructure including a 132kv substation and engineering works to create earth bunds).
-
26/0553/DC Awaiting decision
Fenton Home Farm, CRUNDALE, Haverfordwest, Pembrokeshire, SA62 4PY
Discharge of condition 3 (surface water) of planning permission 24/0754/PA (Proposed agricultural solid muck storage shed).
-
26/0416/DC Split decision
Unit 1, West Estate, WITHYBUSH, Haverfordwest, Pembrokeshire, SA62 4BN
Discharge of Condition 5 (Construction Management Statement) of Planning Permission 25/0496/PA (Extension to an existing gymnasium)