Skip to content
PlanIndex Get alerts
Menu

Planning application

Burgar Hill Wind Farm, Evie, Orkney

Awaiting decision Orkney Islands 26/148/TPPMAJ

Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.

Proposal

Replace five existing turbines (up to 116m to tip, 11.3MW) with 5 wind turbines (up to 149.9m to tip, up to 30MW export) with associated auxiliary infrastructure

As published by the council, reference 26/148/TPPMAJ

Application record

Reference
26/148/TPPMAJ
Status
Awaiting decision
Received
19 May 2026
Validated
13 Aug 2026
Ward
West Mainland

Site history

Applications at this address on the Orkney Islands register

This site has had 2 applications since 2026.

  • 26/209/VR Awaiting decision

    Burgar Hill Wind Farm, Evie, Orkney

    Application to vary Condition 2 of 21/512/VR (varying 02/16/00189/PPF) to extend the operational life of two turbines at Burgar Hill from 20 years to 25 years from date of commissioning

    Submitted 13 Jul 2026

Timeline

Dates from the published record

  1. 19 May 2026

    Received by Orkney Islands

  2. 13 Aug 2026

    Validated

    Checked as complete and ready for consideration.

  3. 14 Aug 2026

    Added to PlanIndex

  4. Decision

    Awaiting decision

    Decision expected by 8 October 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.

    Orkney Islands took a median of 99 days over the applications it decided in the last year.

Who's behind it

Company information only, from the register and Companies House

Agent on file, registered in Roslin

21 applications on PlanIndex · across 13 councils

Trade members see who it is, their full track record, and every application they have filed.

See who's behind it

Applicant on file, registered in Orkney

2 applications on PlanIndex

Trade members see who it is, their full track record, and every application they have filed.

See who's behind it

Documents

Plans, drawings, consultee responses and the officer's report

197 documents on file for this application

  • MoD (Ministry of Defence) Consultation Response · 01 Sep 2026
  • Environmental Health Consultation Response · 25 Aug 2026
  • HIAL (Highlands & Islands Airports Ltd) Consultation Response · 25 Aug 2026
  • NATS (National Air Traffic Services) Consultation Response · 17 Aug 2026
  • Confirmation - Turbine Detail Correspondence · 08 Jul 2026
  • Response to Agent - Turbine Elevations Correspondence · 07 Jul 2026
  • Location Plan Drawing · 01 Jul 2026
  • Site Plan Drawing · 01 Jul 2026
  • Site Plan - Access Track Drawing · 01 Jul 2026
  • Site Plan - Substation Drawing · 01 Jul 2026
  • Site Plan - Turbine 3 & Turbine 4 Drawing · 01 Jul 2026
  • Site Plan - Turbine 1 & Turbine 2 Drawing · 01 Jul 2026
  • Site Plan Turbine 4 & Turbine 5 Drawing · 01 Jul 2026
  • Existing Site Plan 1:5000 Drawing · 01 Jul 2026
  • Existing Site Plan Drawing · 01 Jul 2026
  • Existing Site Plan Drawing · 01 Jul 2026
  • Biodiversity Form Supporting Document · 23 Jun 2026
  • Elevations & Floor Plan - Substation Drawing · 23 Jun 2026
  • Turbine Elevation Drawing · 23 Jun 2026
  • Biodiversity Plan Drawing · 23 Jun 2026
  • Biodiversity Photographs Supporting Document · 23 Jun 2026
  • Response to Invalid Letter Correspondence · 23 Jun 2026
  • Response to Invalid Letter Correspondence · 17 Jun 2026
  • Invalid Letter Correspondence · 16 Jun 2026
  • Confirmation of 4 Sensitive Documents Correspondence · 05 Jun 2026
  • Non-Technical Summary Supporting Document · 19 May 2026
  • Design and Access Statement Supporting Document · 19 May 2026
  • Planning and Policy Statement Supporting Document · 19 May 2026
  • Turbine Planning Permission Application Form · 19 May 2026
  • Pre-Application Consultation Report Supporting Document · 19 May 2026
  • Socio-economic Statement Supporting Document · 19 May 2026
  • Volume 1 - Chapter 1 - Introduction Supporting Document · 19 May 2026
  • Volume 1 - Chapter 10 - Hydrology and Hydrogeology Supporting Document · 19 May 2026
  • Volume 1 - Chapter 11 - Traffic and Transport Supporting Document · 19 May 2026
  • Volume 1 - Chapter 12 - Shadow Flicker Supporting Document · 19 May 2026
  • Volume 1 - Chapter 13 - Tourism and Recreation Supporting Document · 19 May 2026
  • Volume 1 - Chapter 14 - Other Issues Supporting Document · 19 May 2026
  • Volume 1 - Chapter 15 - Summary of Mitigation Supporting Document · 19 May 2026
  • Volume 1 - Chapter 2 - EIA Methodology Supporting Document · 19 May 2026
  • Volume 1 - Chapter 3 - Assessment of Alternatives Supporting Document · 19 May 2026
  • Volume 1 - Chapter 4 - The Proposed Development Supporting Document · 19 May 2026
  • Volume 1 - Chapter 5 - Landscape and Visual Impact Assessment Supporting Document · 19 May 2026
  • Volume 1 - Chapter 6 - Cultural Heritage and Archaeology Supporting Document · 19 May 2026
  • Volume 1 - Chapter 7 - Noise Supporting Document · 19 May 2026
  • Volume 1 - Chapter 8 - Ecology Supporting Document · 19 May 2026
  • Location Plan Drawing · 19 May 2026
  • Volume 2 - Figure 10_1 - Hydrological Context Map Supporting Document · 19 May 2026
  • Volume 2 - Figure 10_1_1a - Peat Depth Map A Supporting Document · 19 May 2026
  • Volume 2 - Figure 10_1_1b - Peat Depth Map B Supporting Document · 19 May 2026
  • Volume 2 - Figure 10_1_1c - Peat Depth Map C Supporting Document · 19 May 2026
  • Volume 2 - Figure 10_1_1d - Peat Depth Map D Supporting Document · 19 May 2026
  • Volume 2 - Figure 10_1_1e- Peat Depth Map E Supporting Document · 19 May 2026
  • Volume 2 - Figure 10_1_1f - Peat Depth Map F Supporting Document · 19 May 2026
  • Volume 2 - Figure 10_1_1g - Peat Depth Map G Supporting Document · 19 May 2026
  • Volume 2 - Figure 10_1_2a - GWDTE Map A Supporting Document · 19 May 2026
  • Volume 2 - Figure 10_1_2b - GWDTE Map B Supporting Document · 19 May 2026
  • Volume 2 - Figure 10_1_2c - GWDTE Map C Supporting Document · 19 May 2026
  • Volume 2 - Figure 10_1_2d - GWDTE Map D Supporting Document · 19 May 2026
  • Volume 2 - Figure 10_1_2e - GWDTE Map E Supporting Document · 19 May 2026
  • Volume 2 - Figure 10_1_2f - GWDTE Map F Supporting Document · 19 May 2026
  • Volume 2 - Figure 10_1_2g - GWDTE Map G Supporting Document · 19 May 2026
  • Volume 2 - Figure 11_1 - ABL Route to Site Supporting Document · 19 May 2026
  • Volume 2 - Figure 11_2 - Traffic Count Locations Supporting Document · 19 May 2026
  • Volume 2 - Figure 12_1 - Shadow Flicker Study Area Supporting Document · 19 May 2026
  • Volume 2 - Figure 12_2 - Cumulative Shadow Flicker Study Area Supporting Document · 19 May 2026
  • Volume 2 - Figure 13_1 - Tourism Receptors within 5km Supporting Document · 19 May 2026
  • Volume 2 - Figure 13_2 - Recreational Receptors within 5km Supporting Document · 19 May 2026
  • Volume 2 - Figure 14_1 - Telecommunications within 1km Study Area Supporting Document · 19 May 2026
  • Volume 2 - Figure 14_2 - Utilities Infrastructure within 1km Study Area Supporting Document · 19 May 2026
  • Volume 2 - Figure 3_1 - Site Constraints Plan Supporting Document · 19 May 2026
  • Volume 2 - Figure 3_2 - Pre-app and Scoping Layout Supporting Document · 19 May 2026
  • Volume 2 - Figure 3_3 - Post-scoping Layout Supporting Document · 19 May 2026
  • Volume 2 - Figure 3_4 - Site Constraints Plan with Layout Supporting Document · 19 May 2026
  • Volume 2 - Figure 4_10 - Site Entrance Details Supporting Document · 19 May 2026
  • Volume 2 - Figure 4_11 - Indicative Substation Telecoms Mast Detail Supporting Document · 19 May 2026
  • Site Plan Drawing · 19 May 2026
  • Volume 2 - Figure 4_3 - Existing Site Plan Overview Supporting Document · 19 May 2026
  • Volume 2 - Figure 4_3_1 - Existing Site Block Plan 1 Supporting Document · 19 May 2026
  • Volume 2 - Figure 4_3_2 - Existing Site Block Plan 2 Supporting Document · 19 May 2026
  • Volume 2 - Figure 4_4 - Drainage Details Supporting Document · 19 May 2026
  • Volume 2 - Figure 4_5 - Foundation Details Supporting Document · 19 May 2026
  • Volume 2 - Figure 4_6 - Crane Hardstanding Details Supporting Document · 19 May 2026
  • Volume 2 - Figure 4_7 - Access Track Details Supporting Document · 19 May 2026
  • Volume 2 - Figure 4_8 - Substation Details Supporting Document · 19 May 2026
  • Volume 3 - Appendix 10_1 - Phase 1 Peat Probing Report Supporting Document · 19 May 2026
  • Volume 3 - Appendix 11_1 and 11_2 - Framework CTMP and Monitoring Plan Supporting Document · 19 May 2026
  • Volume 3 - Appendix 14_1 - Carbon Calculator Supporting Document · 19 May 2026
  • Volume 3 - Appendix 5_1 - LVIA Methodology Supporting Document · 19 May 2026
  • Volume 3 - Appendix 5_2 - Viewpoint Assessment Supporting Document · 19 May 2026
  • Volume 3 - Appendix 5_3 - Residential Visual Amenity Assessment Supporting Document · 19 May 2026
  • Volume 3 - Appendix 6_1 - Setting Assessment Supporting Document · 19 May 2026
  • Volume 3 - Appendix 6_2 - Potential Cumulative Assessment Supporting Document · 19 May 2026
  • Volume 3 - Appendix 6_3 - Gazetteer Supporting Document · 19 May 2026
  • Volume 3 - Appendix 6_4 - Plates Supporting Document · 19 May 2026
  • Volume 3 - Appendix 8_4 - Peatland Condition Assessment Supporting Document · 19 May 2026
  • Volume 2 - Figure 5_1 - 45km Study Area Supporting Document · 19 May 2026
  • Volume 2 - Figure 5_10 - Residential Visual Amenity Assessment Map Supporting Document · 19 May 2026
  • Volume 2 - Figure 5_11 - Route Assessment Overview Supporting Document · 19 May 2026
  • Volume 2 - Figure 5_12 - Route Assessment - A966 between Finstown and Birsay Supporting Document · 19 May 2026
  • Volume 2 - Figure 5_13 - Route Assessment - A967 between Birsay and Hestwall Supporting Document · 19 May 2026
  • Volume 2 - Figure 5_14 - Route Assessment - B9057 between Evie and Sandwick Supporting Document · 19 May 2026
  • Volume 2 - Figure 5_14 - Route Assessment - B9057 between Evie and Sandwick Supporting Document · 19 May 2026
  • Volume 2 - Figure 5_16 - Route Assessment - Ferry Route between Tingwall and Rou Supporting Document · 19 May 2026
  • Volume 2 - Figure 5_17 - Route Assessment - Ferry Route between Kirkwall and Rap Supporting Document · 19 May 2026
  • Volume 2 - Figure 5_18 - Viewpoint 1 - Costa Supporting Document · 19 May 2026
  • Volume 2 - Figure 5_19 - Viewpoint 2 - A966 Evie Supporting Document · 19 May 2026
  • Volume 2 - Figure 5_2 - Landscape Character Types Supporting Document · 19 May 2026
  • Volume 2 - Figure 5_20 - Viewpoint 3 - Broch of Gurness Supporting Document · 19 May 2026
  • Volume 2 - Figure 5_21 - Viewpoint 4 - Loch of Swannay Supporting Document · 19 May 2026
  • Volume 2 - Figure 5_22 - Viewpoint 5 - Midhowe Rousay Supporting Document · 19 May 2026
  • Volume 2 - Figure 5_23 - Viewpoint 6 - Dounby Supporting Document · 19 May 2026
  • Volume 2 - Figure 5_24 - Viewpoint 7 - A967 Twatt Supporting Document · 19 May 2026
  • Volume 2 - Figure 5_25 - Viewpoint 8 - A967 Birsay Supporting Document · 19 May 2026
  • Volume 2 - Figure 5_26 - Viewpoint 9 - Russness Road Wyre Supporting Document · 19 May 2026
  • Volume 2 - Figure 5_27 - Viewpoint 10 - Quoyloo Supporting Document · 19 May 2026
  • Volume 2 - Figure 5_28 - Viewpoint 11 - Skara Brae Supporting Document · 19 May 2026
  • Volume 2 - Figure 5_29 - Viewpoint 12 - Standing Stones of Stenness Supporting Document · 19 May 2026
  • Volume 2 - Figure 5_3 - Landscape Character Areas Supporting Document · 19 May 2026
  • Volume 2 - Figure 5_30 - Viewpoint 13 - Wideford Hill Supporting Document · 19 May 2026
  • Volume 2 - Figure 5_31 - Viewpoint 14 - Carness Road Kirkwall Supporting Document · 19 May 2026
  • Volume 2 - Figure 5_32 - Viewpoint 15 - Hillock Road Shapinsay Supporting Document · 19 May 2026
  • Volume 2 - Figure 5_4 - Landscape Character Areas with Tip ZTV Supporting Document · 19 May 2026
  • Volume 2 - Figure 5_5 - Landscape Planning Designations Supporting Document · 19 May 2026
  • Volume 2 - Figure 5_6 - Landscape Planning Designations with Tip ZTV Supporting Document · 19 May 2026
  • Volume 2 - Figure 5_7 - ZTV to 149_9m Tip Supporting Document · 19 May 2026
  • Volume 2 - Figure 5_8 - ZTV to 81m Hub Supporting Document · 19 May 2026
  • Volume 2 - Figure 5_9 - Cumulative Basemap Supporting Document · 19 May 2026
  • Volume 2 - Figure 6_10 - Extract from Ordnance Survey map of 1902 Supporting Document · 19 May 2026
  • Volume 2 - Figure 6_3 - All Heritage Assets included in Setting Assessment Supporting Document · 19 May 2026
  • Volume 2 - Figure 6_45a-b - View from the east towards Cubbie Rows Castle Supporting Document · 19 May 2026
  • Volume 2 - Figure _12a-d - Scheduled Maes Howe Supporting Document · 19 May 2026
  • Volume 2 - Figure 5_33 - Viewpoint 16 - A961 Kirkwall Supporting Document · 19 May 2026
  • Volume 2 - Figure 5_34 - Viewpoint 17 - B9047 Hoy Supporting Document · 19 May 2026
  • Volume 2 - Figure 5_35 - Viewpoint 18 - Vinquoy Hill Eday Supporting Document · 19 May 2026
  • Volume 2 - Figure 5_36 - Viewpoint 19 - Ring of Brodgar Supporting Document · 19 May 2026
  • Volume 2 - Figure 5_37 - Additional Visibility ZTV Supporting Document · 19 May 2026
  • Volume 2 - Figure 6_1 - Non-designated Assets within 1km Supporting Document · 19 May 2026
  • Volume 2 - Figure 6_11 - Heritage Assets within the ZTV Supporting Document · 19 May 2026
  • Volume 2 - Figure 6_13a-d - Scheduled Skara Brae Supporting Document · 19 May 2026
  • Volume 2 - Figure 6_14a-d - Ring of Brodgar Supporting Document · 19 May 2026
  • Volume 2 - Figure 6_15a-d - Stenness stone circle and henge Supporting Document · 19 May 2026
  • Volume 2 - Figure 6_16a-d - Aiker Ness Broch of Gurness Supporting Document · 19 May 2026
  • Volume 2 - Figure 6_17a-b - Vinquin broch Supporting Document · 19 May 2026
  • Volume 2 - Figure 6_18a-d - Midhowe Broch Supporting Document · 19 May 2026
  • Volume 2 - Figure 6_19a-b - North Howe broch Supporting Document · 19 May 2026
  • Volume 2 - Figure 6_2 - Heritage Assests within the Site Supporting Document · 19 May 2026
  • Volume 2 - Figure 6_20a-d - Howana Gruna Cairn Supporting Document · 19 May 2026
  • Volume 2 - Figure 6_21a-b - Knowe of Yarso Supporting Document · 19 May 2026
  • Volume 2 - Figure 6_22a-b - Knowes of Lingro Supporting Document · 19 May 2026
  • Volume 2 - Figure 6_23a-b - Vestra Fiold Supporting Document · 19 May 2026
  • Volume 2 - Figure 6_24a-d - Hundland Hill Supporting Document · 19 May 2026
  • Volume 2 - Figure 6_25a-b - Brough of Birsay Supporting Document · 19 May 2026
  • Volume 2 - Figure 6_26a-b - Eynhallow Church and Settlement Supporting Document · 19 May 2026
  • Volume 2 - Figure 6_27a-b - Click Mill Supporting Document · 19 May 2026
  • Volume 2 - Figure 6_28a-b - St Magnus Cathedral Supporting Document · 19 May 2026
  • Volume 2 - Figure 6_29a-b - Hundland Settlement Mound Supporting Document · 19 May 2026
  • Volume 2 - Figure 6_30a-b - Burgar chambered cairn Supporting Document · 19 May 2026
  • Volume 2 - Figure 6_31a-b - Midhowe Chambered Cairn Supporting Document · 19 May 2026
  • Volume 2 - Figure 6_32a-b - Nisthouse Burial Mound Supporting Document · 19 May 2026
  • Volume 2 - Figure 6_33a-b - Knap Knowes Supporting Document · 19 May 2026
  • Volume 2 - Figure 6_34a-b - Eynhallow Standing Stone Supporting Document · 19 May 2026
  • Volume 2 - Figure 6_35a-b - Stoney Holm Supporting Document · 19 May 2026
  • Volume 2 - Figure 6_36a-b - Park Holm Supporting Document · 19 May 2026
  • Volume 2 - Figure 6_37a-b - View from Knowe of Onston chambered cairn Supporting Document · 19 May 2026
  • Volume 2 - Figure 6_38a-b - View from Quoyhorrie Supporting Document · 19 May 2026
  • Volume 2 - Figure 6_39a-b - View from Verron Broch Supporting Document · 19 May 2026
  • Volume 2 - Figure 6_4 - Designated Heritage Assets along the Eynhallow Sound Rou Supporting Document · 19 May 2026
  • Volume 2 - Figure 6_40a-b - View from Aiker Ness Broch of Gurness Supporting Document · 19 May 2026
  • Volume 2 - Figure 6_41a-b - View from easternmost interpretation panel at Broch Supporting Document · 19 May 2026
  • Volume 2 - Figure 6_42a-b - View from the top of Knowe of Burrian Supporting Document · 19 May 2026
  • Volume 2 - Figure 6_43a-d - View towards Eynhallow from The Wirk tower and hall Supporting Document · 19 May 2026
  • Volume 2 - Figure 6_44a-b - View from Knowe of Hunclett Supporting Document · 19 May 2026
  • Volume 2 - Figure 6_46a-b - View from western edge of Cubbie Rows Castle Supporting Document · 19 May 2026
  • Volume 2 - Figure 6_47a-b - View from southern visitor entrance to Stones of Ste Supporting Document · 19 May 2026
  • Volume 2 - Figure 6_48 - Heart of Neolithic Orkney Sensitive Area and Ridgelines Supporting Document · 19 May 2026
  • Volume 2 - Figure 6_5 - Designated Assets to the west of the Site Supporting Document · 19 May 2026
  • Volume 2 - Figure 6_6 - Designated Assets to the south of the Site Supporting Document · 19 May 2026
  • Volume 2 - Figure 6_7 - Selected Designated Heritage Assets beyond 10 km of the Supporting Document · 19 May 2026
  • Volume 2 - Figure 6_8 - Extract from Ordnance Survey map of 1881 Supporting Document · 19 May 2026
  • Volume 2 - Figure 6_9 - Extract from The Admiralty Chart of 1807 - surveyed in 1 Supporting Document · 19 May 2026
  • Volume 2 - Figure 7_1 - Noise Study Area Supporting Document · 19 May 2026
  • Volume 2 - Figure 7_2 - Cumulative Noise Study Area Supporting Document · 19 May 2026
  • Volume 3 - Appendix 7_1 - Background Noise Supporting Document · 19 May 2026
  • Volume 3 - Appendix 7_2 - Sound Power Levels of Cumulative Developments Supporting Document · 19 May 2026
  • Volume 3 - Appendix 7_3 - Cumulative Noise Supporting Document · 19 May 2026
  • Volume 3 - Appendix 8_1 - Habitat and National Vegetation Classification Survey Supporting Document · 19 May 2026
  • Volume 3 - Appendix 8_1 - Maps 1 - 9 Supporting Document · 19 May 2026
  • Volume 3 - Appendix 8_3 - Figure 8_3_01 - Peatland Restoration Option Areas Supporting Document · 19 May 2026
  • Volume 3 - Appendix 8_3 - Figure 8_3_02 - Grassland Habitat for Waders Supporting Document · 19 May 2026
  • Volume 3 - Appendix 8_3 - Figure 8_3_03 - Nature Species Rich Hedge Row Supporting Document · 19 May 2026
  • Volume 3 - Appendix 8_3 - Figure 8_3_04 - Location for Proposed Wildflower Mix Supporting Document · 19 May 2026
  • Volume 3 - Appendix 8_3 - Outline Biodiversity Enhancement Management Plan Supporting Document · 19 May 2026
  • Volume 3 - Appendix 9_1 - Annex C - Map 1 - Protected Sites Supporting Document · 19 May 2026
  • Volume 3 - Appendix 9_1 - Annex C - Maps 12 - 18 - Skua and Diver Flights Supporting Document · 19 May 2026
  • Volume 3 - Appendix 9_1 - Annex C - Maps 19 - 23 - Carcass Search Results Supporting Document · 19 May 2026
  • Volume 3 - Appendix 9_1 - Annex C - Maps 2 - 11 - Waders and Skua Supporting Document · 19 May 2026
  • Volume 3 - Appendix 9_1 - Ornithological Technical Report Supporting Document · 19 May 2026

Trade members open them from here.

Open the documents

What happens while it is decided

This application is with Orkney Islands for determination, against a statutory target of eight weeks. Over the last year Orkney Islands's median decision took 99 days. More in our guide to how long planning decisions take.

About this record

The published feed does not state which type of application this is; the register entry on Orkney Islands's portal will say. Our guide explains the common types.